Which of the following is true about tracking schedule performance in a project?
Which of the following is true about tracking schedule performance in a project?
- It is unrelated to a project's budget
- It is related to a project's budget
- It is unrelated to a project's scope
- It is related to a project's scope (correct)
In order to be realistic, a project manager should set
In order to be realistic, a project manager should set
- Discrete goals
- No goals at all
- A range of objectives (correct)
- Vague goals
Is it necessary for every project to have a well-defined objective?
Is it necessary for every project to have a well-defined objective?
- It depends on the project
- Yes (correct)
- It depends on the project manager
- No
Which characteristic highlights a difference between projects and operations?
Which characteristic highlights a difference between projects and operations?
Which of the following is true about projects and operations?
Which of the following is true about projects and operations?