Podcast
Questions and Answers
What is the primary objective of the requirements for signalling in a 25 KV AC electrified area?
What is the primary objective of the requirements for signalling in a 25 KV AC electrified area?
- To eliminate the need for protective measures.
- To ensure signalling equipment functions normally in traction current. (correct)
- To minimize the use of electrical equipment.
- To reduce the visibility of signals.
Which factor is NOT mentioned as affecting signalling in an AC electrified area?
Which factor is NOT mentioned as affecting signalling in an AC electrified area?
- Electrostatic and electromagnetic induction.
- Electrical clearances of signals.
- Visibility of signals due to OHE structure.
- Weather conditions such as rain. (correct)
To maintain electrical clearances, what must be done if a minimum distance of 2 meters cannot be achieved?
To maintain electrical clearances, what must be done if a minimum distance of 2 meters cannot be achieved?
- Use less sensitive signalling equipment.
- Provide suitable protective shields for signal structures. (correct)
- Install larger signs.
- Reduce the height of the signals.
What is the purpose of installing protective wire-mesh screens near signalling equipment?
What is the purpose of installing protective wire-mesh screens near signalling equipment?
How is electrostatic induction practically eliminated according to the requirements?
How is electrostatic induction practically eliminated according to the requirements?
Which of the following describes electromagnetic induction in rail signalling?
Which of the following describes electromagnetic induction in rail signalling?
What type of bond must be provided by the electrical department in yard and block sections?
What type of bond must be provided by the electrical department in yard and block sections?
What is a required practice if it is impossible to maintain electrical clearances from live OHE?
What is a required practice if it is impossible to maintain electrical clearances from live OHE?
In which areas are the diagrams for Broad Gauge not applicable?
In which areas are the diagrams for Broad Gauge not applicable?
What is the normal height of the contact wire at supports for Broad Gauge?
What is the normal height of the contact wire at supports for Broad Gauge?
What clearance must be maintained from the live parts of the O.H.E. under normal conditions?
What clearance must be maintained from the live parts of the O.H.E. under normal conditions?
Where may the contact wire be lowered due to limited clearance?
Where may the contact wire be lowered due to limited clearance?
What should be provided on a signal post if it is within 2 meters of a live conductor and screening is not practicable?
What should be provided on a signal post if it is within 2 meters of a live conductor and screening is not practicable?
What is the highest normal height of the catenary wire for Broad Gauge?
What is the highest normal height of the catenary wire for Broad Gauge?
What should be done if the signal post fittings fall within 2 meters of a live conductor?
What should be done if the signal post fittings fall within 2 meters of a live conductor?
What allowance does the clearance diagram make for regarding catenary and contact wires?
What allowance does the clearance diagram make for regarding catenary and contact wires?
Which factor does NOT influence the value of induced voltage in cables?
Which factor does NOT influence the value of induced voltage in cables?
What type of signals shall be used in electrified areas?
What type of signals shall be used in electrified areas?
Who is responsible for checking the actual visibility of signals?
Who is responsible for checking the actual visibility of signals?
Which clearance diagram is used for tangent tracks and those with super elevation less than 60 mm?
Which clearance diagram is used for tangent tracks and those with super elevation less than 60 mm?
What is required when a signal post or its fittings infringe into the shaded area of the clearance diagram?
What is required when a signal post or its fittings infringe into the shaded area of the clearance diagram?
Which of the following is NOT a factor affecting induced voltage as mentioned?
Which of the following is NOT a factor affecting induced voltage as mentioned?
What does the un-shaded portion of the clearance diagram represent?
What does the un-shaded portion of the clearance diagram represent?
What must be maintained from the live parts of the O.H.E.?
What must be maintained from the live parts of the O.H.E.?
What precaution should be taken if tools or equipment may come within 2 meters of live equipment?
What precaution should be taken if tools or equipment may come within 2 meters of live equipment?
What is required if the neutral section is located after a stop signal?
What is required if the neutral section is located after a stop signal?
Where should a neutral section ideally be located?
Where should a neutral section ideally be located?
What is the preferred distance for a neutral section away from a stop signal on flat gradients?
What is the preferred distance for a neutral section away from a stop signal on flat gradients?
What should the SSE/JE (Signal) do regarding safety instructions?
What should the SSE/JE (Signal) do regarding safety instructions?
What should be avoided when positioning neutral sections in terms of train operation?
What should be avoided when positioning neutral sections in terms of train operation?
What height and distance requirements do Drg.Nos. 22-D4 and 22-D5 illustrate?
What height and distance requirements do Drg.Nos. 22-D4 and 22-D5 illustrate?
What should be done if modifications to comply with guidelines are difficult?
What should be done if modifications to comply with guidelines are difficult?
Where should signals normally be located in relation to the track?
Where should signals normally be located in relation to the track?
What is the minimum distance required between a traction mast and a signal post to ensure visibility?
What is the minimum distance required between a traction mast and a signal post to ensure visibility?
In what situation may the distance requirement between traction masts and signal posts be reduced?
In what situation may the distance requirement between traction masts and signal posts be reduced?
What is an important consideration when setting signal posts on curved tracks?
What is an important consideration when setting signal posts on curved tracks?
What is the requirement for the height of the signal post?
What is the requirement for the height of the signal post?
What should be avoided regarding the placement of traction masts in relation to signal posts?
What should be avoided regarding the placement of traction masts in relation to signal posts?
What is a guideline regarding the signal's location on tangent tracks?
What is a guideline regarding the signal's location on tangent tracks?
What should not infringe upon the schedule of dimensions from the track's centerline?
What should not infringe upon the schedule of dimensions from the track's centerline?
What is the standard height of the center line of the red signal above rail level?
What is the standard height of the center line of the red signal above rail level?
What is the minimum distance that OHE structures should be kept from signals located between tracks?
What is the minimum distance that OHE structures should be kept from signals located between tracks?
What precautions should be taken for portal drop arms located in rear of signals?
What precautions should be taken for portal drop arms located in rear of signals?
What action should an official take if signal visibility is deemed inadequate after any phase of OHE work?
What action should an official take if signal visibility is deemed inadequate after any phase of OHE work?
For signals with junction indicators outside tracks, the setting distances of OHE masts should align with which document?
For signals with junction indicators outside tracks, the setting distances of OHE masts should align with which document?
What is the maximum height without a route indicator for a signal above rail level?
What is the maximum height without a route indicator for a signal above rail level?
How often should signal visibility be checked by the official in charge?
How often should signal visibility be checked by the official in charge?
What is required for signals with junction indicators between tracks?
What is required for signals with junction indicators between tracks?
Flashcards
Induced voltage
Induced voltage
Voltage created in conductors due to factors like the length of parallelism with electrified tracks and soil conductivity.
Signal visibility
Signal visibility
The ability of a train driver to see a signal.
Signal clearance diagrams
Signal clearance diagrams
Technical drawings demonstrating the allowed and disallowed areas for signal posts based on track types (tangent, curves with different elevations).
Signal post dimensions
Signal post dimensions
The standard size limits of signal posts for safety.
Signup and view all the flashcards
Electrified areas
Electrified areas
Railway sections with overhead electrical systems.
Signup and view all the flashcards
Signal erection
Signal erection
Installation and positioning of signal posts, observing clearances.
Signup and view all the flashcards
Signal sighting committee
Signal sighting committee
A group that checks the visibility of signals to ensure safe train operation.
Signup and view all the flashcards
Cable screening
Cable screening
Protecting cable sheaths from influencing electric fields to minimize induced voltage.
Signup and view all the flashcards
Signalling equipment requirements in AC electrified areas
Signalling equipment requirements in AC electrified areas
Signalling equipment must function correctly even with traction current and in faulty conditions, preventing false signals and ensuring train safety.
Signup and view all the flashcards
Factors affecting signalling in electrified areas
Factors affecting signalling in electrified areas
Visibility of signals, electrical clearances from overhead lines, traction return current, and electromagnetic induction.
Signup and view all the flashcards
Overhead Line Equipment (OHE) visibility
Overhead Line Equipment (OHE) visibility
OHE structures must be designed to maximize signal visibility.
Signup and view all the flashcards
Electrical clearances of signals
Electrical clearances of signals
Signals must have enough space from live overhead lines to avoid electrical issues.
Signup and view all the flashcards
Electrostatic induction
Electrostatic induction
Minimized by using underground cables to insulate circuits from outside electrical fields.
Signup and view all the flashcards
Electromagnetic induction
Electromagnetic induction
Causes voltage variations in parallel conductors like rails, return conductors, cable sheaths, and signalling circuits.
Signup and view all the flashcards
Protective shields for signals
Protective shields for signals
Used to maintain safe electrical distances when signals are too close to live OHE for wires.
Signup and view all the flashcards
OHE bonding
OHE bonding
Electrical connections for overhead lines that are needed for proper operation of Signal & Telecommunication (S&T) equipment.
Signup and view all the flashcards
Catenary and Contact Wire Diagram Applicability
Catenary and Contact Wire Diagram Applicability
Diagrams 22-D1, 22-D2, and 22-D3 show clearances for double-wired catenary systems, excluding anchor spans, turnouts, areas 3 meters from masts, and loco sheds/inspection pits; also excluded are areas with feeder lines near masts, boosters, and return conductors.
Signup and view all the flashcards
Normal Contact Wire Height
Normal Contact Wire Height
Typically 5.60 meters above supports for broad gauge.
Signup and view all the flashcards
Normal Catenary Height
Normal Catenary Height
Usually 7.05 meters at the highest point for broad gauge.
Signup and view all the flashcards
Reduced Clearances
Reduced Clearances
In tunnels and under bridges, clearances can be reduced to 4.58 meters for the contact wire; the catenary is lowered or terminated accordingly.
Signup and view all the flashcards
Safety Clearance Rule
Safety Clearance Rule
No one should approach live overhead line parts (O.H.E) closer than 2 meters.
Signup and view all the flashcards
Signal Post Protection
Signal Post Protection
Signal posts within 2 meters of live conductors must have iron screening, or caution boards, if screening is not feasible.
Signup and view all the flashcards
Safety Measures for OHE
Safety Measures for OHE
Protective measures are taken when signalling staff work near 25 kV live conductors. This is done by constructing or providing safety screens or signage indicating caution.
Signup and view all the flashcards
Caution Board Height
Caution Board Height
If iron screening is not possible, a caution board must be placed 3 meters above rail level on signal posts.
Signup and view all the flashcards
Safe Distance from Live Equipment
Safe Distance from Live Equipment
Tools and equipment must remain at least 2 meters away from live electrical equipment and return conductors, which are considered live.
Signup and view all the flashcards
Signal Location Precautions
Signal Location Precautions
Signal locations (22-D4/22-D5) on Broad Gauge tracks need specific minimum heights and distances from the track to prevent electrical interference.
Signup and view all the flashcards
Neutral Section Placement
Neutral Section Placement
Neutral sections should be placed away from stop signals, level crossings, and preferably on tangent tracks, to ensure train safety and prevent stalling.
Signup and view all the flashcards
Neutral Section Distance (Gradient)
Neutral Section Distance (Gradient)
The distance between a neutral section and stop signals varies depending on gradient. 1600 meters for up to 1 in 300 gradient, and 2500 meters for steeper gradients up to 1 in 200. Distance must ensure sufficient train speed before or after signal.
Signup and view all the flashcards
PTFE Neutral Section Location
PTFE Neutral Section Location
PTFE-type short neutral sections should be positioned 400 meters after or 200 meters before the stop signal on level tangent tracks.
Signup and view all the flashcards
Chief Electrical Engineer's Authority
Chief Electrical Engineer's Authority
If complying with neutral section guidelines is difficult/expensive, the Chief Electrical Engineer can authorize alternative arrangements that are safe and reliable, but must comply with gradient rules.
Signup and view all the flashcards
Signal Staff Training
Signal Staff Training
SSE/JE (Signal) personnel must instruct staff on safety procedures around live equipment and ensure their compliance with safety rules.
Signup and view all the flashcards
Electrical Safety Requirements
Electrical Safety Requirements
Electrical engineers prioritize safety when locating signals and neutral sections, considering factors like train speed and track conditions.
Signup and view all the flashcards
Signal placement
Signal placement
Signals are typically placed on the left side of the track they control. In special cases, they may be on the right.
Signup and view all the flashcards
Visibility
Visibility
Signals must be clearly visible, so extra care is taken to avoid obstructions like traction masts and structures.
Signup and view all the flashcards
Mast positioning
Mast positioning
Spacing of traction masts around signals follows strict rules to ensure good visibility.
Signup and view all the flashcards
Signal post height
Signal post height
Signal posts must be tall enough to be seen easily.
Signup and view all the flashcards
Signal on curves
Signal on curves
Signals on curves or near obstructions need special attention to ensure good visibility.
Signup and view all the flashcards
Signal clearance
Signal clearance
Signal posts and fittings must be positioned within defined limits to avoid interfering with the track.
Signup and view all the flashcards
Junction indicators
Junction indicators
Special signals that show the direction a departing train will take.
Signup and view all the flashcards
Signal Height
Signal Height
The center line of a red signal must be approximately 3.65 meters above rail level, and the entire signal (without a route indicator) should not exceed 5.2 meters.
Signup and view all the flashcards
Signal Separation
Signal Separation
Signals located between tracks require a clear space of at least 600 meters behind them for OHE structures and portal drop arms.
Signup and view all the flashcards
Offset Bracket
Offset Bracket
If a portal drop arm is unavoidable near a signal, the signal must be mounted on an offset bracket. Extra study is also needed for the drop arm placement.
Signup and view all the flashcards
Speed Restrictions
Speed Restrictions
If the signal's visibility is inadequate, speed restrictions may be imposed, and actions must be taken to re-establish a clear line of sight.
Signup and view all the flashcards
Signalling Requirements in Electrified Areas
Signalling Requirements in Electrified Areas
Signalling equipment needs to operate flawlessly despite the presence of traction current and potential faults to ensure safe train operations.
Signup and view all the flashcards
High Rise OHE Clearance
High Rise OHE Clearance
Special clearance regulations apply for signals in areas with high-rise overhead equipment (for double-stack containers or three-tier cars).
Signup and view all the flashcardsStudy Notes
Signalling in 25 KV AC Electrified Areas
- Objectives: Ensure signalling equipment functions normally in the presence of traction current. Prevent false indications from the traction system. Safeguard equipment and staff from electric shock.
Factors Affecting Signalling
- Visibility: Signal visibility affected by overhead line equipment (OHE) structures. Electrical clearances of signals from live OHE are crucial.
- Traction Return Current: Can cause interference in signalling systems.
- Electrostatic and Electromagnetic Induction: Can induce voltages and currents in parallel conductors (rails, traction return, cables), affecting signalling and telecommunication systems. Induced voltage depends on various factors (cable parallelism, soil conductivity, screening efficiency).
Visibility of Signals
- OHE structures should be designed to ensure signal visibility.
- Protective shields for signal structures may be needed where electrical clearances cannot be maintained.
- Layout plan for OHE should be based on approved signalling plan.
- Protective wire mesh screens are required where signal clearance from live OHE conductors is more than 2 meters.
- OHE bonds (structural, longitudinal, cross bonds) are provided by the electrical department for proper functioning of field signaling equipment (fastened to the structure/mast/rails, insulated for portions under positive rail).
Electrostatic Induction Elimination
- Transferring circuits into underground metal-sheathed cables helps eliminate electrostatic induction.
Signal Structures in Electrified Areas
- Only colour light signals are used in electrified areas.
- Signal masts, insulators, wires, and supports must not obstruct signal visibility.
- Signals should be erected to maintain a minimum clearance from live OHE parts.
- Signal location and required protection are determined based on signal clearance diagrams for broad gauge (different diagrams for tangent tracks, curves with varying degrees of super elevation).
- Signal posts and fittings must not infringe on marked safe areas.
Signal Clearances for Safety
- No one should approach live OHE parts closer than 2 meters.
- Protective iron screening is necessary if signal posts come within 2 meters of live 25 KV conductors.
- Caution boards are placed on signal posts if protective screening is not feasible.
Location of Neutral Section
- Neutral sections are located away from stop signals and level crossings (ideally on tangents).
- The distance between the signal and neutral section is crucial and must be sufficient for the train to gain safe speed to coast through the neutral section without stalling (at least 1600 meters on slight gradients and up to 2500 meters for sharper gradients).
- PTFE type short neutral sections are located 400 meters after and 200 meters before a stop signal on level tangent tracks.
Signal Erection in Electrified Areas
- Signals are typically located on the left side of the track, exceptions exist.
- Proper OHE design is essential for signal visibility (offset brackets if necessary, avoiding obstructions within 30 meters of the signal, sufficient height for clear visibility).
- Signal posts and components should not infringe on other signal components.
- Visibility of signals should be checked both day and night to ensure adequate speed restrictions; speed restrictions might be necessary.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.