Setting Out Base Lines and Pier Positions
80 Questions
0 Views

Setting Out Base Lines and Pier Positions

Created by
@SolicitousOklahomaCity

Questions and Answers

What is the primary method used to determine the position of piers/abutments?

Triangulation using three intersecting sight lines

What is the purpose of using tape readings in setting out base lines?

To correct for tension, temperature, and slope

What is the recommended approach for constructing pipe and box culverts?

Removing top soil and replacing it with lean concrete

What is the minimum depth requirement for open foundations in ordinary soil?

<p>1.75 metres below the lowest anticipated scoured bed level</p> Signup and view all the answers

What is the purpose of widening the base of open foundations?

<p>To reduce the bearing pressure on the soil</p> Signup and view all the answers

What type of equipment is recommended for giving specified tension to the tape?

<p>Spring balances</p> Signup and view all the answers

Where should pipe and box culverts not be provided?

<p>Where the bed is likely to be scoured</p> Signup and view all the answers

What is the purpose of providing footings in open foundations?

<p>To reduce the bearing pressure on the soil</p> Signup and view all the answers

What is the minimum depth recommended for soil exploration for design and construction of piles?

<p>10 metres below the anticipated level of pile tip</p> Signup and view all the answers

What is the primary function of friction piles?

<p>To transfer the load primarily by skin friction developed along their surface</p> Signup and view all the answers

What is the purpose of collecting data on ground water table and its tidal and seasonal fluctuations?

<p>To design the pile foundation for scour resistance</p> Signup and view all the answers

What type of piles are used in hard stratum?

<p>Bearing piles</p> Signup and view all the answers

What is the primary consideration while selecting driven piles?

<p>Availability of space and head room</p> Signup and view all the answers

Which of the following is NOT a type of pile classification based on construction methods?

<p>Drilled shafts</p> Signup and view all the answers

What is the typical application of large diameter bored piles?

<p>Railway bridge construction</p> Signup and view all the answers

What is the purpose of conducting Standard Penetration Test (SPT)?

<p>To determine the shear properties of soil</p> Signup and view all the answers

What is the primary reason for seepage of water being carefully watched during sinking of a well?

<p>To prevent sand blowing and ensure the safety of men working inside the well</p> Signup and view all the answers

What is the name of the phenomenon where a large quantity of sand is sucked into the well and a funnel-shaped depression is formed outside the well?

<p>Sand blowing</p> Signup and view all the answers

Why are divers with their equipment present during the sinking of wells in deep water?

<p>For emergencies</p> Signup and view all the answers

What is the permissible tilt of a well?

<p>1 in 100 (1%)</p> Signup and view all the answers

What is used to judge the verticality of a well when it is not sunk through water?

<p>Plumb bobs on all four sides</p> Signup and view all the answers

What is the purpose of throwing empty gunny bags and branches of a tree with green leaves into the funnel during sand blowing?

<p>To arrest the sand blow</p> Signup and view all the answers

What is the consequence of excessive tilt and shift of a well that cannot be corrected?

<p>Rechecking the design of the well and the resulting foundation pressure</p> Signup and view all the answers

What is measured using gauges marked at quarter points on the outer periphery of the steining?

<p>Direction and extent of tilt</p> Signup and view all the answers

Why is it important to make the joints as air tight as possible?

<p>To prevent air from escaping the well</p> Signup and view all the answers

What is the purpose of water proof cement plastering on the inside face of steining?

<p>To prevent water seepage</p> Signup and view all the answers

What is the primary objective of settling the well by blasting?

<p>To create a stable base for the well</p> Signup and view all the answers

What is the purpose of making one or more cylindrical holes in the base of the well?

<p>To give good anchorage to the well</p> Signup and view all the answers

In what scenario is it preferable to bench the rock and take the well down?

<p>When the well is constructed on a steeply sloping rocky base with sand overlay</p> Signup and view all the answers

What is the purpose of fixing MS dowels in drilled holes in the base of the well?

<p>To provide a good bond between the base rock and the bottom plug</p> Signup and view all the answers

What is the purpose of constructing the top plug of the well?

<p>To seal the top of the well</p> Signup and view all the answers

What is the purpose of setting out the piers on the top of the well?

<p>To distribute the weight of the well evenly</p> Signup and view all the answers

After acquiring a grip of about 6 metres, how much can the steining be raised at a time?

<p>3 metres</p> Signup and view all the answers

How long should inner shuttering and bracing not be removed after casting?

<p>24 hours</p> Signup and view all the answers

What is the maximum velocity of water for which construction of an island may be resorted to?

<p>2.0 m/s</p> Signup and view all the answers

What is the minimum free board that should be provided while constructing an island?

<p>0.6 metre</p> Signup and view all the answers

What is the maximum depth of water for which bamboo piles can be used?

<p>1.5 metres</p> Signup and view all the answers

What is the minimum grip that piles should have?

<p>3 metres</p> Signup and view all the answers

What is done to protect the island from scour?

<p>Dumping sand bags outside the island</p> Signup and view all the answers

What is used in place of bamboo piles beyond a certain depth?

<p>Steel sheet piles</p> Signup and view all the answers

What should be done with defective piles?

<p>They should be removed or left in place without affecting the performance of the adjacent piles</p> Signup and view all the answers

What is the purpose of making a boring nearby when there is a major variation between the depths of adjacent piles?

<p>To ascertain the cause of the variation</p> Signup and view all the answers

What is the minimum cement content required for tremie concreting?

<p>370 kg/m3</p> Signup and view all the answers

What is the purpose of installing a temporary casing in tremie concreting?

<p>To prevent fragments of ground from dropping into the concrete</p> Signup and view all the answers

What is the minimum diameter of the tremie pipe required for 20 mm sized aggregate?

<p>200 mm</p> Signup and view all the answers

What should be pushed down the tube ahead of the first charge of concrete?

<p>A sliding plug</p> Signup and view all the answers

Why is it necessary to have a closed system for the hopper and tremie in tremie concreting?

<p>To prevent water from passing through the system</p> Signup and view all the answers

What should be done when constructing piles in very soft soils?

<p>The driving should proceed from outside to inside</p> Signup and view all the answers

What type of material is used to build caissons in deeper channels and swift rivers?

<p>Steel plates</p> Signup and view all the answers

How can caissons be assembled and launched?

<p>Either on the river bank or on a temporary platform over two barges</p> Signup and view all the answers

What is the purpose of covering the dredge holes with steel plates and pumping compressed air into them?

<p>To reduce the draught</p> Signup and view all the answers

What is used for sinking of smaller wells?

<p>Timber scotch</p> Signup and view all the answers

What is the primary factor that determines the spacing of piles?

<p>Type of soil and empirical approach</p> Signup and view all the answers

Why are dredgers used in sinking of wells?

<p>For greater depths and high sub soil water level</p> Signup and view all the answers

In the case of piles deriving their bearing capacity mainly from friction, what is the minimum spacing recommended?

<p>3 times the diameter of the pile shaft</p> Signup and view all the answers

What is the purpose of assembling and launching caissons?

<p>To sink wells in deeper channels and swift rivers</p> Signup and view all the answers

What is the recommended minimum spacing for piles in loose sand or filling?

<p>2 times the diameter of the pile shaft</p> Signup and view all the answers

What is the alternative method of assembling caissons?

<p>Assembling in dry docks</p> Signup and view all the answers

What is the general guideline for centre-to-centre spacing of piles?

<p>4 times the diameter of the pile shaft</p> Signup and view all the answers

What is the primary consideration while assembling and launching caissons?

<p>To ensure the caisson is properly tied and strutted</p> Signup and view all the answers

What is the consideration for spacing of piles in the case of piles on a very hard stratum?

<p>Competency of the end bearing stratum</p> Signup and view all the answers

What is the purpose of ensuring that the zones of soil from which the piles derive support do not overlap?

<p>To ensure that the bearing values are not reduced</p> Signup and view all the answers

What is the consideration for determining the diameter of the circumscribing circle in the case of non-circular cross-section piles?

<p>Diameter of the pile shaft</p> Signup and view all the answers

What is the purpose of determining the spacing of piles?

<p>To ensure that the bearing values are not reduced</p> Signup and view all the answers

What is the primary reason for forming a triangle of error during the determination of pier/abutment positions?

<p>Inaccurate measurement due to human error</p> Signup and view all the answers

What is the purpose of using lean concrete in the construction of pipe and box culverts?

<p>To level and consolidate the bed</p> Signup and view all the answers

What is the minimum depth required for open foundations in ordinary soil?

<p>1.75 metres</p> Signup and view all the answers

What is the purpose of providing footings in open foundations?

<p>To reduce the bearing pressure</p> Signup and view all the answers

Why are pipe and box culverts not recommended in certain situations?

<p>Because of the risk of scouring</p> Signup and view all the answers

What is the purpose of using spring balances in setting out base lines?

<p>To provide specified tension to the tape</p> Signup and view all the answers

What is the importance of correcting tape readings for tension, temperature, and slope?

<p>To improve the accuracy of measurements</p> Signup and view all the answers

What is the purpose of locating concrete pillars with steel plates at tape lengths?

<p>To provide a reference point for measurement</p> Signup and view all the answers

What is the primary purpose of using plumb bobs?

<p>To check for tilt during sinking</p> Signup and view all the answers

What is the method of correcting tilt by dredging on the higher side of the well?

<p>Eccentric dredging</p> Signup and view all the answers

What is the purpose of applying a light pull to the well?

<p>To correct the tilt of the well</p> Signup and view all the answers

What is the method of correcting tilt by using wire ropes and a dead man anchorage?

<p>Applying pull to the well</p> Signup and view all the answers

In what scenario is pneumatic sinking of wells used?

<p>All of the above</p> Signup and view all the answers

What is the purpose of using divers during the sinking of wells?

<p>To ensure the safety of the sinking operation</p> Signup and view all the answers

What is the method of correcting tilt by packing the low side of the well with sand bags?

<p>Packing the low side with sand bags</p> Signup and view all the answers

What is the consequence of excessive tilt and shift of a well that cannot be corrected?

<p>The well has to be abandoned</p> Signup and view all the answers

Study Notes

Setting Out Base Lines and Pier Positions

  • The position of piers/abutments is determined by the intersection of three sight lines: alignment sighted from stations located on either end, base line on the down stream side, and base line on the upstream side.
  • Ideally, these three lines should intersect at one point, but a triangle of error may form, and the correct center is fixed by judgment within this triangle.

Setting Out Base Lines

  • Linear measurements should be carried out with invar tape or Electronic Distance Measuring (EDM) equipment.
  • Concrete pillars with steel plates should be located at tape lengths for accurate measurements.
  • Spring balances should be used to give specified tension to the tape.
  • Tape readings should be corrected for tension, temperature, and slope.

Pipe and Box Culverts with Open Foundation

  • Pipe and box culverts can be constructed by removing top soil, replacing it with a layer of lean concrete, and leveling and consolidating the bed.
  • They should not be used where the bed is likely to be scoured.

Other Bridges with Open Foundation

  • Open foundations must rest on a stratum with adequate bearing capacity.
  • The base can be widened by providing footings to reduce bearing pressure.
  • Footings will rest on a lean concrete bed of adequate thickness.
  • The foundation should be taken to a depth not less than 1.75 meters below the lowest anticipated scoured bed level in ordinary soil.

Soil Exploration for Design and Construction of Piles

  • Detailed soil exploration should be carried out to a depth generally not less than 10 meters below the anticipated level of pile tip.
  • The following particulars should be collected:
    • Groundwater table and its tidal and seasonal fluctuations
    • Soil profile and borehole log
    • In-situ bulk and dry density
    • Index properties of soil
    • Shear properties of soil (if required, Standard Penetration Test (SPT) may be done)
    • Consolidation properties (in case of clays)
    • Chemical analysis of soil and groundwater to identify sulfate and chloride content or any other deleterious chemical content
    • Additional data such as high flood level, maximum scour depth, normal water level during working season, etc.

Classification of Pile Foundations

  • Based on the manner of transfer of load:
    • Friction piles: transfer load primarily by skin friction developed along their surface
    • Bearing piles: transfer load primarily by bearing resistance developed at the pile tip or base, without taking into account frictional resistance
    • Bearing-cum-friction piles: transfer load by both skin friction and bearing resistance
  • Based on construction methods:
    • Driven pre-cast piles
    • Driven cast-in-situ piles
    • Bored cast-in-situ piles
  • Large diameter bored piles (more than 1 meter diameter) are normally used for Railway bridge construction.

Selection of Type of Piles

  • Factors to be considered while selecting the type of piles:
    • Availability of space and headroom
    • Type of soil and its properties
    • Load-carrying capacity required
    • Depth of water
    • Velocity of water
    • Depth of pile
    • Construction difficulties and costs

Sinking of Wells in Water

  • Sinking of well is done by removing soil with grabs or chiselling and drawing out the soil.
  • Sinking of steining should not be done within 48 hours of casting.
  • In stagnant water and in water with velocity up to about 2.0 m/s and of depth up to about 5 meters, construction of island may be resorted to.
  • In greater depths, the use of steel caissons would become unavoidable.

Construction of Island

  • The island should provide sufficient working space of about 2 to 3 meters all round the well.
  • A minimum freeboard of 0.6 meter should always be provided.
  • For depths of water up to 1 meter, an island may be constructed by laying a few rings of sandbags enclosing the area of the island and filling with sand.

Tilt and Shift of the Well

  • Limits of tilt and shift:
    • A tilt of up to 1 in 100 (1%) and a shift of D/40 subject to a maximum of 150 mm can be permitted.
    • Excessive tilt and shift, which cannot be corrected, should be taken into account for rechecking the design of the well and the resulting foundation pressure.

Founding the Well

  • Settling the well by blasting:
    • As far as possible, the well shall be evenly seated on sound rock devoid of fissures, cavities, etc.
    • One or more cylindrical holes may be made in the base to give good anchorage to the well.
    • Alternatively, anchorage can be provided by the rock itself, which is allowed to remain projecting at the center.

Bottom Plugging of the Well

  • Sand hearting:
    • The joints should be made as air-tight as possible to prevent escape of air.
    • Waterproof cement plastering can be resorted to on the inside face of steining.

Construction of the Top Plug

  • Setting out of the piers on top of the well:
    • The top plug should be constructed with a good bond between the base rock and the bottom plug.

Determination of Pier/Abutment Position

  • The position of piers/abutments is determined by the intersection of three sight lines: one along the alignment, one from a station on the base line on the downstream side, and one from a point on the base line on the upstream side.
  • Theoretically, all three lines should intersect at one point, but practically, a triangle of error forms, and the correct center is fixed by judgment within this triangle.

Setting Out Base Lines

  • Linear measurements should be carried out with invar tape or Electronic Distance Measuring (EDM) equipment.
  • Concrete pillars with steel plates fixed over them should be located at tape lengths for accurate measurements.
  • Spring balances should be used to give specified tension to the tape.
  • Tape readings should be corrected for tension, temperature, and slope.

Pipe and Box Culverts

  • Pipe and box culverts can be constructed after removing the top soil in the bed to the required depth and replacing it with a layer of lean concrete after the bed is levelled and well consolidated.
  • Pipe and box culverts should not be provided where the bed is likely to be scoured.

Open Foundations

  • Open foundations must rest on a stratum with adequate bearing capacity.
  • The base can be sufficiently widened by providing footings to reduce the bearing pressure.
  • The footings will rest on a lean concrete bed of adequate thickness.
  • The foundation should be taken to a depth not less than 1.75 meters below the lowest anticipated scoured bed level in ordinary soil.

Spacing of Piles

  • The spacing of piles is determined based on the type of soil and empirical approach.
  • The spacing will be governed by the competency of the end bearing stratum when piles are found on a very hard stratum and derive their capacity mainly from end bearing.
  • The minimum spacing in such cases shall be 2.5 times the diameter of the pile shaft.
  • Piles deriving their bearing capacity mainly from friction shall be sufficiently apart to ensure that the zones of soil from which the piles derive support do not overlap to such an extent that their bearing values are reduced.

Load Carrying Capacity of a Pile/Group of Piles

  • The load carrying capacity of a single pile is affected by the type of soil and the method of installation.

Defective Piles

  • Defective piles should be removed or left in place, whichever is convenient, without affecting the performance of the adjacent piles or the group as a whole.
  • Additional piles should be provided to replace them as necessary.

Tremie Concreting

  • The concrete should be coherent, rich in cement (not less than 370 kg/m3), and of slump between 150 and 180 mm.
  • When concreting is carried out under water, a temporary casing should be installed to the full depth of the bore hole or 2m into a non-collapsible stratum.
  • The hopper and the tremie should be a closed system embedded in the placed concrete, through which water cannot pass.

Sinking of Wells

  • Caissons can be used for sinking wells in deeper channels and swift rivers.
  • The caisson is assembled on a temporary platform, and after testing for leakages, it is lifted from the platform and lowered into position.
  • The process of open sinking of wells involves using timber shear leg, derrick, or timber scotch for smaller wells.

Tilt Correction

  • Tilt correction methods include eccentric dredging, eccentric loading, applying pull to the well, and applying push to the well.
  • The method of tilt correction depends on the site conditions.

Use of Divers

  • Divers can be used for sinking wells at greater depths.
  • Divers should follow the relevant British standard specifications for durations of ascends and stoppages at various depths and stay under water at various pressures.

Pneumatic Sinking of Wells

  • Pneumatic sinking is used when other methods are not found feasible, particularly when the wells have to pass through considerable depths of intervening layers of rock or when the bed is full of large boulders or interlocked small boulders.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Description

Learn how to determine the position of piers and abutments in engineering surveying, including the use of alignment sight lines and base lines to fix the center point.

More Quizzes Like This

Basic Civil Engineering Concepts
10 questions
Land Surveying in Civil Engineering
10 questions
Engineering Surveying Chapter 5
38 questions
Use Quizgecko on...
Browser
Browser