Podcast
Questions and Answers
What should be checked to ensure the proper functioning of MHO relays?
What should be checked to ensure the proper functioning of MHO relays?
- Each relay and contact mechanism individually (correct)
- General circuit connections
- Only the annunciation system
- The wiring diagrams only
Which of the following is NOT included in the checks for annunciations?
Which of the following is NOT included in the checks for annunciations?
- Buchholz trip
- Transformer efficiency reading (correct)
- 25 kV feeder circuit breaker trip
- Winding temperature trip
What is the importance of checking the detailed wiring diagrams after installation?
What is the importance of checking the detailed wiring diagrams after installation?
- To ensure no errors exist in the approved diagrams (correct)
- To simplify the operational process
- To evaluate compliance with manufacturer guidelines
- To verify the visual aesthetic of the panel
What should be done if indicating instruments are found to be malfunctioning?
What should be done if indicating instruments are found to be malfunctioning?
What is a recommended method for detecting errors in detailed wiring diagrams?
What is a recommended method for detecting errors in detailed wiring diagrams?
What should be examined on the isolators to ensure their proper function?
What should be examined on the isolators to ensure their proper function?
Why is it important to check the terminal connections of Current Transformers (CT)?
Why is it important to check the terminal connections of Current Transformers (CT)?
What is the purpose of the earth terminal on a lightning arrester?
What is the purpose of the earth terminal on a lightning arrester?
What should be checked for the operation of isolators regarding interlocking?
What should be checked for the operation of isolators regarding interlocking?
What is essential to confirm about the shielding conductors in a substation?
What is essential to confirm about the shielding conductors in a substation?
What aspect of Lightning Arrestors should be visually examined?
What aspect of Lightning Arrestors should be visually examined?
What must be checked regarding the oil level in Potential Transformers (PT)?
What must be checked regarding the oil level in Potential Transformers (PT)?
What is the recommended training timeline for switching station attendants before the commissioning date?
What is the recommended training timeline for switching station attendants before the commissioning date?
Which measurement method is used to measure individual levels of every frequency on the 'send' channel?
Which measurement method is used to measure individual levels of every frequency on the 'send' channel?
What should the measured levels on the receive side be between?
What should the measured levels on the receive side be between?
What reading should the send-channel levels not be lower than?
What reading should the send-channel levels not be lower than?
At which position should the VTVM selector switch be during normal measurements of active circuits?
At which position should the VTVM selector switch be during normal measurements of active circuits?
When should the VTVM selector switch be changed to 150 Ohm or 1120 Ohm?
When should the VTVM selector switch be changed to 150 Ohm or 1120 Ohm?
What is the impedance of the send and receive circuits mentioned?
What is the impedance of the send and receive circuits mentioned?
What permanent record should be noted after the final adjustment of the levels?
What permanent record should be noted after the final adjustment of the levels?
What should be used to measure composite levels between tele-command and tele-signal cable pairs?
What should be used to measure composite levels between tele-command and tele-signal cable pairs?
What is the impedance of the amplifier output?
What is the impedance of the amplifier output?
What is the primary requirement for the battery room environment?
What is the primary requirement for the battery room environment?
What should be checked regarding the condition of the battery plates?
What should be checked regarding the condition of the battery plates?
What must be ensured about the alarm bell in the battery system?
What must be ensured about the alarm bell in the battery system?
Which material should the battery stands be made from?
Which material should the battery stands be made from?
What is an important factor when inspecting the battery charger?
What is an important factor when inspecting the battery charger?
What type of paint should be used on the battery room walls and floor up to 2 m?
What type of paint should be used on the battery room walls and floor up to 2 m?
What should be checked regarding the inter-cell connectors in the battery system?
What should be checked regarding the inter-cell connectors in the battery system?
Which design feature must the control room building possess?
Which design feature must the control room building possess?
What type of access should the substation area have?
What type of access should the substation area have?
What is the standard number of discs required for tension strings for a 132 kV supply?
What is the standard number of discs required for tension strings for a 132 kV supply?
How many discs are used for suspension strings at a distance of 1.6 km from the sub-station?
How many discs are used for suspension strings at a distance of 1.6 km from the sub-station?
For railway crossings, which type of towers should be provided?
For railway crossings, which type of towers should be provided?
What is the minimum required insulation resistance for power conductors?
What is the minimum required insulation resistance for power conductors?
What device should every tower be fitted with during a detailed inspection?
What device should every tower be fitted with during a detailed inspection?
Which color discs are to be provided on terminal towers to indicate phases?
Which color discs are to be provided on terminal towers to indicate phases?
What action should be taken after defects are rectified during inspection?
What action should be taken after defects are rectified during inspection?
What should be done to warn the public before the lines are energized?
What should be done to warn the public before the lines are energized?
What is required to confirm the completion of inspections before energization?
What is required to confirm the completion of inspections before energization?
What should be recorded during the continuity test of each conductor?
What should be recorded during the continuity test of each conductor?
What are the two distinct parts of the pre-commissioning inspections and tests?
What are the two distinct parts of the pre-commissioning inspections and tests?
Which of the following standards should be considered during preparations for commissioning?
Which of the following standards should be considered during preparations for commissioning?
Which element is NOT included in the major heads outlined for detailed preparation work in Railway Electrification?
Which element is NOT included in the major heads outlined for detailed preparation work in Railway Electrification?
What is the primary focus of the chapter's outlined preparations for commissioning?
What is the primary focus of the chapter's outlined preparations for commissioning?
What is the significance of amendments to rules and standards during pre-commissioning preparations?
What is the significance of amendments to rules and standards during pre-commissioning preparations?
Which of the following does not form part of the legal framework for ensuring the safety of railway electrification?
Which of the following does not form part of the legal framework for ensuring the safety of railway electrification?
How should the procedures indicated in the manual be approached during preparations for commissioning?
How should the procedures indicated in the manual be approached during preparations for commissioning?
What condition must be evaluated to ensure the proper sealing of a cabinet in a substation?
What condition must be evaluated to ensure the proper sealing of a cabinet in a substation?
What must be checked to ensure isolators operate correctly?
What must be checked to ensure isolators operate correctly?
What should be examined on the potential transformers (PT) to ensure proper functioning?
What should be examined on the potential transformers (PT) to ensure proper functioning?
Which component connection is critical for lightning arrestors to function properly?
Which component connection is critical for lightning arrestors to function properly?
What aspect of the isolators needs verification regarding circuit breakers?
What aspect of the isolators needs verification regarding circuit breakers?
Which examination step is essential for ensuring the safety of shielding and earthing in a substation?
Which examination step is essential for ensuring the safety of shielding and earthing in a substation?
What is a necessary condition regarding the terminal connections of Current Transformers (CT)?
What is a necessary condition regarding the terminal connections of Current Transformers (CT)?
During the inspection of lightning arrestors, which condition should specifically be checked?
During the inspection of lightning arrestors, which condition should specifically be checked?
What must be ensured regarding the insulation resistance of transformers?
What must be ensured regarding the insulation resistance of transformers?
What is a necessary component to ensure that cabin staff understands the purpose of 'Yellow Warning Collars'?
What is a necessary component to ensure that cabin staff understands the purpose of 'Yellow Warning Collars'?
Which statement accurately describes the responsibility of the OHE supervisors?
Which statement accurately describes the responsibility of the OHE supervisors?
What is essential for Station Masters regarding the system of power blocks?
What is essential for Station Masters regarding the system of power blocks?
What kind of training format is suggested for Station Masters and related staff regarding the new electrified traction rules?
What kind of training format is suggested for Station Masters and related staff regarding the new electrified traction rules?
Which steps are taken to ensure the proper operation of protective relays before commissioning?
Which steps are taken to ensure the proper operation of protective relays before commissioning?
What must be confirmed in writing by the staff with respect to new procedures concerning unwired lines?
What must be confirmed in writing by the staff with respect to new procedures concerning unwired lines?
What is the minimum distance an earthed structure should be from live OHE for safety?
What is the minimum distance an earthed structure should be from live OHE for safety?
What factors must be inspected on a 25 kV feeder line before energization?
What factors must be inspected on a 25 kV feeder line before energization?
What procedure is recommended after defects are rectified during inspection?
What procedure is recommended after defects are rectified during inspection?
Which of the following is NOT a requirement for testing protective relays?
Which of the following is NOT a requirement for testing protective relays?
What should be included in the detailed and general inspection for 25 kV feeder lines?
What should be included in the detailed and general inspection for 25 kV feeder lines?
What is a critical requirement for the installation of protective relays?
What is a critical requirement for the installation of protective relays?
What must every tower be fitted with during a detailed inspection of the feeder lines?
What must every tower be fitted with during a detailed inspection of the feeder lines?
What does the commissioning engineer need to verify about protective relays after they have been energized?
What does the commissioning engineer need to verify about protective relays after they have been energized?
What is the primary consequence of an under-rated trip battery circuit fuse?
What is the primary consequence of an under-rated trip battery circuit fuse?
What is required to ensure that a battery fuse is adequately protected?
What is required to ensure that a battery fuse is adequately protected?
During insulation resistance testing, what should be done with earthing links?
During insulation resistance testing, what should be done with earthing links?
Which component is essential for conducting a primary injection test?
Which component is essential for conducting a primary injection test?
What should be the state of fuses in the control circuit regarding their size?
What should be the state of fuses in the control circuit regarding their size?
What is the implication of having connections in the trip circuit that are not tight?
What is the implication of having connections in the trip circuit that are not tight?
What should be monitored when manually closing relay contacts?
What should be monitored when manually closing relay contacts?
What type of ammeter is mentioned for use during testing?
What type of ammeter is mentioned for use during testing?
What should happen after modifications are made following testing?
What should happen after modifications are made following testing?
Which aspect of the primary injection test's setup is crucial?
Which aspect of the primary injection test's setup is crucial?
Flashcards
Equipment Condition Check
Equipment Condition Check
Inspect equipment for damage, cleanliness, and proper functioning of components like fuses, operation counters, and supports.
Insulator Inspection
Insulator Inspection
Examine insulators for cracks, cleanliness, and smooth manual operation of the isolator.
Isolator Interlocking
Isolator Interlocking
Verify proper connection between the circuit breaker and its isolator, and ensure the isolator is grounded independently.
Transformer Insulation
Transformer Insulation
Signup and view all the flashcards
Transformer Terminal Connections
Transformer Terminal Connections
Signup and view all the flashcards
Lightning Arrester Inspection
Lightning Arrester Inspection
Signup and view all the flashcards
Substation Shielding
Substation Shielding
Signup and view all the flashcards
Signal Level Measurement
Signal Level Measurement
Signup and view all the flashcards
Individual Frequency Levels
Individual Frequency Levels
Signup and view all the flashcards
Receiving Channel Levels
Receiving Channel Levels
Signup and view all the flashcards
Composite Levels
Composite Levels
Signup and view all the flashcards
Control Centre Level Measurement
Control Centre Level Measurement
Signup and view all the flashcards
Attenuation Pads
Attenuation Pads
Signup and view all the flashcards
Line Impedance
Line Impedance
Signup and view all the flashcards
VTVM/TVM 'High' Impedance
VTVM/TVM 'High' Impedance
Signup and view all the flashcards
Commissioning
Commissioning
Signup and view all the flashcards
Porcelain Discs for 132kV
Porcelain Discs for 132kV
Signup and view all the flashcards
Duplicate Strings (Road/Rail)
Duplicate Strings (Road/Rail)
Signup and view all the flashcards
Insulation Resistance Measurement
Insulation Resistance Measurement
Signup and view all the flashcards
Continuity Test
Continuity Test
Signup and view all the flashcards
Tower Accessories
Tower Accessories
Signup and view all the flashcards
General Inspection and Energization
General Inspection and Energization
Signup and view all the flashcards
Public Warning for Energization
Public Warning for Energization
Signup and view all the flashcards
Station Transformer Inspection
Station Transformer Inspection
Signup and view all the flashcards
Control Room Requirements
Control Room Requirements
Signup and view all the flashcards
Battery Room Conditions
Battery Room Conditions
Signup and view all the flashcards
Battery Support and Protection
Battery Support and Protection
Signup and view all the flashcards
Battery Charging Log Review
Battery Charging Log Review
Signup and view all the flashcards
Battery Gas Containment
Battery Gas Containment
Signup and view all the flashcards
Battery Plate Condition Check
Battery Plate Condition Check
Signup and view all the flashcards
Battery Fuse Inspection
Battery Fuse Inspection
Signup and view all the flashcards
Battery Charger Inspection
Battery Charger Inspection
Signup and view all the flashcards
Substation Drainage and Access
Substation Drainage and Access
Signup and view all the flashcards
Traction Transformer and Oil Drainage
Traction Transformer and Oil Drainage
Signup and view all the flashcards
MHO relay
MHO relay
Signup and view all the flashcards
Wrong Coupling
Wrong Coupling
Signup and view all the flashcards
EHV transformer circuit breaker auto-trip
EHV transformer circuit breaker auto-trip
Signup and view all the flashcards
Buchholz alarm/trip
Buchholz alarm/trip
Signup and view all the flashcards
Winding temperature alarm/trip
Winding temperature alarm/trip
Signup and view all the flashcards
Oil temperature alarm/trip
Oil temperature alarm/trip
Signup and view all the flashcards
Low oil trip
Low oil trip
Signup and view all the flashcards
25 kV transformer circuit breaker trip
25 kV transformer circuit breaker trip
Signup and view all the flashcards
25 kV feeder circuit breaker trip
25 kV feeder circuit breaker trip
Signup and view all the flashcards
Transformer circuit breaker inter-trip
Transformer circuit breaker inter-trip
Signup and view all the flashcards
Control panel instruments
Control panel instruments
Signup and view all the flashcards
Relay operation test plugs
Relay operation test plugs
Signup and view all the flashcards
Indicating lamps
Indicating lamps
Signup and view all the flashcards
CB tripping in 110 V DC failure
CB tripping in 110 V DC failure
Signup and view all the flashcards
Wiring diagram scrutiny
Wiring diagram scrutiny
Signup and view all the flashcards
Wiring verification
Wiring verification
Signup and view all the flashcards
Insulation and continuity tests
Insulation and continuity tests
Signup and view all the flashcards
Pre-Commissioning Inspections
Pre-Commissioning Inspections
Signup and view all the flashcards
Commissioning
Commissioning
Signup and view all the flashcards
Traction Sub-stations
Traction Sub-stations
Signup and view all the flashcards
Transmission lines and 25 kV feeders
Transmission lines and 25 kV feeders
Signup and view all the flashcards
Protective equipment
Protective equipment
Signup and view all the flashcards
Switching Stations
Switching Stations
Signup and view all the flashcards
Remote Control Equipment
Remote Control Equipment
Signup and view all the flashcards
Overhead equipment
Overhead equipment
Signup and view all the flashcards
Safety Rules Compliance
Safety Rules Compliance
Signup and view all the flashcards
Detailed inspection
Detailed inspection
Signup and view all the flashcards
General inspection
General inspection
Signup and view all the flashcards
Equipment General Condition
Equipment General Condition
Signup and view all the flashcards
Insulator Inspection
Insulator Inspection
Signup and view all the flashcards
Isolator Interlocking
Isolator Interlocking
Signup and view all the flashcards
Current/Potential Transformer Insulation
Current/Potential Transformer Insulation
Signup and view all the flashcards
Transformer Terminal Connection
Transformer Terminal Connection
Signup and view all the flashcards
Lightning Arrester
Lightning Arrester
Signup and view all the flashcards
Substation Shielding
Substation Shielding
Signup and view all the flashcards
Energizing Transmission Lines
Energizing Transmission Lines
Signup and view all the flashcards
25 kV Feeder Inspection
25 kV Feeder Inspection
Signup and view all the flashcards
Protective Relay Testing
Protective Relay Testing
Signup and view all the flashcards
Relay Setting and Calibration
Relay Setting and Calibration
Signup and view all the flashcards
Relay Contact Closure Check
Relay Contact Closure Check
Signup and view all the flashcards
Fuse Rating
Fuse Rating
Signup and view all the flashcards
Trip Battery Fuse
Trip Battery Fuse
Signup and view all the flashcards
Oversized Fuses
Oversized Fuses
Signup and view all the flashcards
Undersized Fuses
Undersized Fuses
Signup and view all the flashcards
Primary Injection Test
Primary Injection Test
Signup and view all the flashcards
Insulation Resistance
Insulation Resistance
Signup and view all the flashcards
Electrification Operational Rules
Electrification Operational Rules
Signup and view all the flashcards
Staff Training
Staff Training
Signup and view all the flashcards
Sectioning Diagram
Sectioning Diagram
Signup and view all the flashcards
OHE Sectioning Diagram
OHE Sectioning Diagram
Signup and view all the flashcards
Yellow Warning Collars
Yellow Warning Collars
Signup and view all the flashcards
Power Blocks/Protection
Power Blocks/Protection
Signup and view all the flashcards
Competency Certificates
Competency Certificates
Signup and view all the flashcards
First Aid for Electrical Shock
First Aid for Electrical Shock
Signup and view all the flashcards
Study Notes
Chapter IX: Preparation for Commissioning
- Prior to commissioning new railway electrification schemes, detailed preparation work is necessary.
- Instructions for various equipment are issued separately in technical manuals.
- Key aspects for preparation are outlined in this chapter.
- Traction sub-stations, transmission lines and 25 kV feeders, protective equipment, switching stations, remote control equipment, and overhead equipment are all major points of focus.
- The chapter discusses technical aspects for attention during inspections, tests before energization, and commissioning.
20901 Reference to Rules and Statutory Rules
- Safety of public, railway staff, and property is ensured through strict compliance with various rules.
- Indian Electricity Act 1910 (latest revision), Indian Electricity Rules (latest edition), Indian Railway Act (amended as needed), General Rules for Indian Railways, associated subsidiary rules, Indian Railways' Schedule of Dimensions, 1935 Rules for Opening of a Railway or Section of a Railway for Public Carriage of Passengers (amended as needed), Bonding and Earthing Code, and relevant IS or IRS specifications and codes of practice for various equipment are all covered.
20902 Pre-Commissioning Inspections
- Pre-commissioning inspections and tests cover two parts:
- Detailed inspection at the level of ACE and Senior Subordinates.
- General inspection at the level of Divisional Officers.
- These inspections cover all installations and are independent of inspections performed by administrative officers.
- Relevant officers and staff must be involved in the inspections and verification of work quality during construction.
- Defects and deficiencies are rectified before transferring sections to the open line.
- The three categories of defects and deficiencies are vital safety items, non-vital safety items with related serious shortcomings, and less critical issues.
20904 Planning of Power Supply
- Sub-stations in electric traction require substantial care during erection and commissioning.
- Careful tests are needed, using reliable and calibrated instruments.
- Section-by-section energization and partial traction-change commissioning should be adequately planned where needed.
- Operational order for sub-stations should be decided via consultation to maintain reliable supply to energized sections.
- The dates when the authorities require power supply must be communicated well in advance to ensure proper scheduling.
- Sub-station connections and transmission line crossings must be completed beforehand.
- Distribution of load for electric traction systems across the grid must be balanced to avoid strain.
20905 Commissioning of Traction Transformers
- Steps for commissioning traction transformers include drying, checking the tap-changer mechanism, verifying transformer bushing condition, ensuring oil tightness, ensuring sufficient oil, and verifying the functionality of Buchholz relay.
20906 Precautions During Commissioning of Traction Transformer
- Staff should take care to remove all loose articles from clothes, secure tools, and maintain dry conditions to avoid moisture entering during operations.
- Maintenance of electrical contacts and equipment should also be done.
20907 Tests on Transformer Windings
- Insulation resistance tests are conducted using a megger at specified temperatures.
- Insulation resistance values are determined between EHV winding/earth, 25kV winding/earth, and between EHV and 25kV windings.
- Phasing out tests are used for single phase transformers.
20908 Circuit Breakers and Interruptors
- Circuit breaker mounting should be vertical and secure.
- The operating mechanism and roller/bearing movement must be checked for proper functioning.
- All pins, locking plates and split pins should be secure.
- Electrical wiring, its insulation and terminal screws must be properly checked for tightness and contact conditions.
- Functionality of operation /closing solenoids/motors should be tested.
- Checking of dielectric strength of oil and other maintenance aspects.
- The porcelain housing condition must be assessed.
20909 Isolators
- Inspect insulators for cracks and cleanliness.
- Check operation of switch blades, spring pressure, interlocking mechanisms, and earthing (grounding).
20910 Current and Potential Transformers
- Check insulation resistance using a megger between primary and secondary winding to earth, and between primary and secondary.
20911 Lightning Arrestors
- Inspect outer porcelain housings (looking for cracks or chips).
- Ensure that earth connections to lightning arrestors are solid and direct.
- Connection to the general earthing grid, and to an independent earth electrode.
20912 Shielding and Earthing
- Confirm proper protection and metallic casings connectivity.
- Ensure correct neutral terminals connection to the substation earthing grid and comply with "Code for Earthing Power Supply Installations" (Appendix 111).
20913 Busbars and Insulators
- Visual inspection for cracks and any paint marks.
- Confirm smooth and clean contact surfaces for current carrying joints and pressure, suitable for different metals.
20914 Clearances
- Minimum clearances are defined for live equipment in different conditions (e.g., still air, maximum temperature).
- Measures, such as fencing and safety procedures, are necessary within a workplace
20915 Auxilaiary Power Supply for Traction Substations & Control Room
- Consideration for a 3-phase, 415/240 V, 50Hz supply of 100 kVA to meet power needs at the substation and control room, if possible.
20916 Batteries & Battery Charger
- Ensure battery room has good ventilation, protection from dust and moisture.
- Battery plates conditions are inspected(including the specific gravity of each cell and voltage across each cell on load. ).
- Check for proper functioning of battery charger capacity, indicating lamps and earths.
20917 General
- Substation area inspections to ensure proper drainage, roads, rail access, fences, and oil drainage arrangements.
- Correct numbering schemes for transformers, isolators, circuit breakers, feeders and correspondence in control panels, and on the mimic diagram board must be verified.
20918 General Inspection of Substations and Commissioning
- Confirming defects and deficiencies rectification.
- Joint inspections, by the related departments, are performed before energization.
- Inspections of equipment, including protective relays, and the care taken during erection.
- Compliance with Indian Electricity Act and Rules.
20919 Detailed Inspection of Transmission Lines
- A joint-effort inspection is done once contractors declare a section ready regarding the critical installation elements.
- Inspection team includes ACE (TrD), construction/contractor staff, and railway representatives.
- Any defects are noted, and rectification should be promptly addressed to ensure timely energization.
20920 Compliance with Rules and Approved
- Detailed compliance with Indian Electricity Act and Indian Electricity Rules.
- Conformity with specific specifications and sag/tension charts for clearances.
20921 Visual Inspection
- Visual inspection of masts(checking for defects or damage - paint and other elements)
- Testing the integrity and cleanliness of insulators.
- Checking tightness of bolts and nuts, and other installation elements including any necessary painting.
- Measurements of tower footings to meet minimum requirements and sag of earth wires and conductors.
20922 Clearances and Sag
- Clearances for different locations, like open routes, roads, and accessible areas, between live conductors and earth /various structures are mandatory.
20923 Earthing
- Correct and individual earthing connections for each tower with a maximum resistance of 10 ohms.
20924 Insulators and Insulation Resistance
- Visual inspections for chips, cracks, cleanliness, and arcing/horns on insulators are mandatory at prescribed intervals or distances along line and from stations.
- Measurements of insulation resistance using 2500 V to 5000 V megger are required with specific values given.
20925 Continuity Test
- Continuity testing across each conductor is done, and the results are documented.
20926 Accessories
- Checking and confirming that each tower has the necessary accessories (enamelled number plates, circular discs, and danger boards)
20927 General Inspection and Energization
- Inspections by Sr. DEE/DEE(TrD) and relevant construction/contractor staff.
- Ensuring proper working conditions for the installation and tele-command signals.
- Verification and documentation of earlier inspections.
20928 25 kV Feeders
- Inspection of 25kV line elements(such as towers, isolation elements, etc.) and through continuity.
- Checking clearances, comparing this with the planned/approved drawings.
20929 Testing of Protective Relays
- Equipment testing before commissioning.
- Three stages: prior-to-installation checks, post-installation and commissioning checks and confirmatory checks.
- Checking of all relays on the equipment for their correct operation.
- Ensuring correct operation during various circumstances.
- Checking relay functioning in the laboratory followed by commissioning and final checks after energization.
20930 Inspection of Setting of Relays and Calibration of Meters
- Checking of relay functionality with specific settings.
- Documentation of testing settings and calibration data.
- Correct relay operation for current and potential coils is crucial for proper functioning.
20931 Protective Devices at Sub-stations
- The types of protective devices to be checked in each electrical transformer station are: Differential protection, Restricted earth fault protection for EHV, 25 kV sides; Buchholz relay, Winding temperature protection and Oil temperature protection
- Indicating devices, such as oil level indicator for low oil levels
- Indicators for winding/oil temperature are present on the control panels for monitoring.
20936 Primary Injection Test
- Primary injection tests are carried out to ensure overall soundness of the circuits; including appropriate connections for testing
20937 Voltage Transformer Ratio and Polarity Check
- Procedures are described to confirm voltage transformer ratio and polarity using standard methods.
20938 Electrical Operation of Indicators and Associated Devices
- Checks for proper functioning of shunt-connected indicators, annunciators, auxiliary elements and (DC/Master) relays for specified minimum voltage levels.
20939 Secondary Injection Test
- Testing of relay settings including operating times and minimum closing values for induction/instantaneous armature, directional relays etc., and their characteristics.
20940 Alarm and Trip Check
- Ensure appropriate (fuse) circuits operate according to plan.
- Relay operations (manual and automatic) must be validated with alarm/trip indications.
20941 Load Test
- Final validation of voltmeter and ammeter operation when normal load currents are passed.
- Evaluating performance of differential (Protection) circuits under external/internal fault conditions.
- Check polarity of CT and PT for correct operation
20942 Confirmatory Test of OHE Protective Relays
- Tests under de-energized conditions to confirm relay operation during fault scenarios.
20943 Power Supply
- Power supply for switching stations is sourced from 10kVA transformers.
- Voltage records of transformers is mandatory.
20944 Installation of Equipment
- Interruptors, isolators, busbars, lightning arresters, wiring, batteries, and their chargers are included in checks.
- Minor differences in installations within switching stations.
20945 Clearances
- Live conductor clearances above ground level for 25 kV.
- Minimum distances between live and earth/earthed parts.
- Clearance parameters regarding safety and operation of electrical equipment
20946 Auxiliary Transformers & Booster Transformers
- Inspections and tests of (auxiliary/booster) transformers as per prescribed procedures
20947 General
- Fencing, gates and safety features for switching stations should be examined.
- Verify that the ground around the equipment is properly drained and leveled.
- Ensure accessibility for maintenance works at all locations.
20948 Interlocking
- Validate correct operation of double-pole isolators, combined with interlocks, and their position indication locks and RC control circuits to prevent accidental operation during critical conditions.
20949 Feeding Posts
- Verification of proper relay operation and safety during different scenarios (such as low voltage/faults) and emergency feeds
20950 Number Plates and Boards
- Ensure verification of the numbering of equipment (interruptors, isolators, etc.) with control panel schematics and diagrams.
- Presence of and conformity with safety, warning, and clearance boards for personnel and public.
20951-20965
- Earthing/bonding of structural steel and equipment.
- Insulation resistance testing, continuity checks and checks for correctness of connections in different location(s).
- Verification and maintenance checks of various relay systems and control equipment along with their corresponding indicators.
- Preparation and procedures for operating electrified services and testing with live conditions.
- Divisional Officers' inspection and certificate of conformity for proper functioning of installations prior to commencement/start of service.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.