Podcast
Questions and Answers
Which of the following is the MOST accurate description of why the processes of schedule management are presented as distinct processes?
Which of the following is the MOST accurate description of why the processes of schedule management are presented as distinct processes?
- The inputs and outputs of each process require isolation
- Each process is managed by a different team member
- Each process occurs in a different project phase
- The tools and techniques used in each process are different (correct)
In project schedule management, what is the PRIMARY role of the 'Define Activities' process?
In project schedule management, what is the PRIMARY role of the 'Define Activities' process?
- To estimate the resources required for each task
- To establish the sequence of work to be performed
- To identify and document the specific tasks to be conducted (correct)
- To decompose the work breakdown structure into management components
Which of the following is the MOST appropriate action to take when the scope of a project is not sufficiently defined to decompose a branch of the WBS to the work package level?
Which of the following is the MOST appropriate action to take when the scope of a project is not sufficiently defined to decompose a branch of the WBS to the work package level?
- Use the lowest level of the WBS branch that is defined to develop a high-level project schedule for that component. (correct)
- Delay scheduling efforts until the scope is fully defined
- Reassign project team members to scope definition tasks
- Request additional budget to engage external subject matter experts
What is the MAIN purpose of a 'control account' in project schedule planning?
What is the MAIN purpose of a 'control account' in project schedule planning?
Which of the following BEST describes the utility of a 'planning package' in project schedule development?
Which of the following BEST describes the utility of a 'planning package' in project schedule development?
In project management, why are project schedule activities specified in the activity list rather than as deliverables?
In project management, why are project schedule activities specified in the activity list rather than as deliverables?
What information should be included in the attributes of a project activity?
What information should be included in the attributes of a project activity?
How are milestones utilized in the project schedule management process?
How are milestones utilized in the project schedule management process?
In project schedule sequencing, what strategy helps develop a realistic project schedule?
In project schedule sequencing, what strategy helps develop a realistic project schedule?
What is the purpose of precedence diagramming method (PDM) in the context of project management?
What is the purpose of precedence diagramming method (PDM) in the context of project management?
Which dependency is MOST often utilized?
Which dependency is MOST often utilized?
What does the Arrow Diagramming Method (ADM) use arrows to show?
What does the Arrow Diagramming Method (ADM) use arrows to show?
Which of the following is the BEST explanation of why dummy activities are used in Arrow Diagramming Method (ADM)?
Which of the following is the BEST explanation of why dummy activities are used in Arrow Diagramming Method (ADM)?
In project scheduling, what is the MOST important reason for identifying mandatory dependencies?
In project scheduling, what is the MOST important reason for identifying mandatory dependencies?
In project management, what effect do discretionary dependencies have on the project timeline?
In project management, what effect do discretionary dependencies have on the project timeline?
What are the external dependencies defined in Project Management?
What are the external dependencies defined in Project Management?
The team is attempting to reduce production time of an item. By how much time should the second writing of the item start before the completion of the first?
The team is attempting to reduce production time of an item. By how much time should the second writing of the item start before the completion of the first?
To account for ten days of concrete cure time, what would you put into place that would hold the team back before proceeding?
To account for ten days of concrete cure time, what would you put into place that would hold the team back before proceeding?
How can the project manager communicate with the team when creating the scheduling network?
How can the project manager communicate with the team when creating the scheduling network?
Which strategy results in more coordination? (Choose the best answer)
Which strategy results in more coordination? (Choose the best answer)
Which of the following is the MOST accurate statement regarding analogous estimating for activity durations?
Which of the following is the MOST accurate statement regarding analogous estimating for activity durations?
What is the MAIN component of the Three-Point Estimates?
What is the MAIN component of the Three-Point Estimates?
What is the appropriate course of action when a project team decides to use reserves to manage a project?
What is the appropriate course of action when a project team decides to use reserves to manage a project?
What output should be derived when project time estimations are completed and known?
What output should be derived when project time estimations are completed and known?
If there are significant shifts in resources, tasks, or budgets, what action must be taken?
If there are significant shifts in resources, tasks, or budgets, what action must be taken?
If resources are constrained, and the project cannot operate smoothly, what action can be taken?
If resources are constrained, and the project cannot operate smoothly, what action can be taken?
What is a key element to account for when developing a management schedule plan?
What is a key element to account for when developing a management schedule plan?
Why is scheduling reviewed often?
Why is scheduling reviewed often?
What software is used to keep track of the original and modified base lines?
What software is used to keep track of the original and modified base lines?
What is a part of schedule control?
What is a part of schedule control?
What question should be asked when attempting to determine a more swift closure to a project?
What question should be asked when attempting to determine a more swift closure to a project?
What factors should be considered when the project is under a situation of external conditions (i.e. strike)?
What factors should be considered when the project is under a situation of external conditions (i.e. strike)?
A team has an activity that can have shared resources on certain occasions, what action is completed?
A team has an activity that can have shared resources on certain occasions, what action is completed?
What is the value in assigning the resources?
What is the value in assigning the resources?
What effort can reduce waste?
What effort can reduce waste?
Where do you combine the model data to achieve the tasks?
Where do you combine the model data to achieve the tasks?
How are imposed dates identified in a project schedule?
How are imposed dates identified in a project schedule?
During plan of management what plan requires to be up to date?
During plan of management what plan requires to be up to date?
Flashcards
Project Time Management
Project Time Management
Processes to ensure project completion on time
Define Activities
Define Activities
Identify specific schedule activities to create project deliverables
Sequence Activities
Sequence Activities
Identify and document dependencies between schedule activities
Estimate Activity Resources
Estimate Activity Resources
Signup and view all the flashcards
Estimate Activity Durations
Estimate Activity Durations
Signup and view all the flashcards
Develop Schedule
Develop Schedule
Signup and view all the flashcards
Control Schedule
Control Schedule
Signup and view all the flashcards
Activities of the cronogram
Activities of the cronogram
Signup and view all the flashcards
Project team
Project team
Signup and view all the flashcards
Decomposition
Decomposition
Signup and view all the flashcards
Templates Activity List
Templates Activity List
Signup and view all the flashcards
Rolling Wave Planning
Rolling Wave Planning
Signup and view all the flashcards
Outputs
Outputs
Signup and view all the flashcards
Activity Attributes
Activity Attributes
Signup and view all the flashcards
Milestone List
Milestone List
Signup and view all the flashcards
PDM
PDM
Signup and view all the flashcards
Final to Start
Final to Start
Signup and view all the flashcards
ADM
ADM
Signup and view all the flashcards
Dependencies Determination
Dependencies Determination
Signup and view all the flashcards
Mandatory Dependencies
Mandatory Dependencies
Signup and view all the flashcards
Discretionary Dependencies
Discretionary Dependencies
Signup and view all the flashcards
External Dependencies
External Dependencies
Signup and view all the flashcards
Advancement of activities
Advancement of activities
Signup and view all the flashcards
Setbacks Activities
Setbacks Activities
Signup and view all the flashcards
Baselines
Baselines
Signup and view all the flashcards
Estimate needed Resources
Estimate needed Resources
Signup and view all the flashcards
Expert Judgment
Expert Judgment
Signup and view all the flashcards
Alternative Analysis
Alternative Analysis
Signup and view all the flashcards
Similar Work Review
Similar Work Review
Signup and view all the flashcards
Software of Managment
Software of Managment
Signup and view all the flashcards
Rising Estimate
Rising Estimate
Signup and view all the flashcards
Resource Desglose Structure
Resource Desglose Structure
Signup and view all the flashcards
Calendar of Resources
Calendar of Resources
Signup and view all the flashcards
Duration estimate
Duration estimate
Signup and view all the flashcards
Three point
Three point
Signup and view all the flashcards
Analysis of Reserve
Analysis of Reserve
Signup and view all the flashcards
Determination of Dates
Determination of Dates
Signup and view all the flashcards
Limits of scope
Limits of scope
Signup and view all the flashcards
Comprension Timeline
Comprension Timeline
Signup and view all the flashcards
Intensification Process
Intensification Process
Signup and view all the flashcards
Study Notes
- Project time management includes the processes required to ensure timely project completion.
Time Management Processes
- Definition of Activities: Identify specific schedule activities that need to be performed to produce various project deliverables.
- Establishment of the Sequence of Activities: Identify and document dependencies between schedule activities.
- Estimation of Activity Resources: Estimate the types and quantities of resources required to perform each schedule activity.
- Estimation of Activity Duration: Estimate the number of working periods required to complete each schedule activity.
- Schedule Development: Analyze activity sequences, activity durations, resource requirements, and schedule constraints to create the project schedule.
- Schedule Control: Control changes to the project schedule.
- These processes interact with each other and with processes in other Knowledge Areas.
- Each process may involve the effort of one or more individuals or groups, depending on the project needs.
- Each process takes place at least once in each project and occurs in one or more phases of the project.
- In practice, the processes overlap and interact in ways not detailed in this guide, even though they are presented here as discrete components with well-defined interfaces.
- Interactions between processes are detailed in Chapter 3.
Activity Sequencing, Resource Allocation, and Scheduling
- For projects of smaller scope, establishing the sequence of activities, estimating activity resources, estimating activity duration, and developing the schedule are closely linked and considered as one process completed by one person in a short amount of time.
- These processes are presented here as distinct processes because the tools and techniques for each one are different.
Project Schedule Execution
- Is preceded by a planning effort by the project management team separate from all six project management activities
- This planning effort is part of the Develop Project Management Plan process (Section 4.3) and produces a schedule management plan.
- The schedule management plan determines the format and establishes the criteria for developing and controlling the project schedule.
- Project time management processes and related tools and techniques vary by application area and are generally defined as part of the project life cycle, and documented in the schedule management plan.
- The schedule management plan is either in the project management plan or a subsidiary plan, and can be formal or informal, very detailed or broadly outlined, depending on the project's needs.
Activity Definition
- This involves identifying and documenting the work required to be done
- Defines deliverables at the lowest level of the Work Breakdown Structure (WBS), known as work packages.
- Work packages are then broken down into smaller components called schedule activities, to provide a basis for estimating, scheduling, executing, and controlling project work
- Activity definition and schedule planning are implied in this process to meet project objectives.
Inputs of Activity Definition
- Environmental factors of the company
- Organizational process assets, such as policies, procedures, and guidelines
- Project scope statement, outlining deliverables, constraints, and assumptions
- Work Breakdown Structure (WBS), which provides a hierarchical decomposition of the project scope
- WBS dictionary, providing detailed information about each element in the WBS
- Project management plan, which includes guidance on how the project will be executed, monitored, and controlled
Tools and Techniques
- Decomposition, breaking down work packages into smaller, more manageable components
- Templates, using standardized lists of activities or parts of activity lists from previous projects
- Rolling wave planning, elaborating on the project scope and WBS as the project progresses
- Expert judgment, relying on the expertise of project team members or other experts
- Planning component
Outputs of Activity Definition
- Activity list, a comprehensive list of all schedule activities to be performed on the project
- Activity attributes, extending the activity list with multiple attributes related to each schedule activity
- Milestone list, identifying all project milestones
- Requested changes, which may affect the project scope statement and WBS
- These changes undergo review and disposition through the Integrated Change Control process.
Factors
- Environmental factors include project management information systems and software tools for schedule development.
- Organizational assets encompass activity planning policies, procedures, guidelines, and lessons learned database with historical information on used activity lists in similar past projects.
- The project scope statement includes deliverables, constraints, and assumptions, which limiting options or are considered to be true for planning (work hours per week or construction timing)
- WBS (Work Breakdown Structure) is used for defining schedule activities, and the WBS dictionary provides detailed information for each element.
- Decomposition is subdividing project work packages into smaller schedule activities, and the list of activities, WBS, and WBS dictionary can be developed sequentially or concurrently.
- Standard activity lists or parts of activity lists from previous projects can be used as templates, and related information about activity attributes (resource skills needed, risk identification, expected deliverables) can be taken into account.
- The EDT can provide an overview of the project.
Activity Sequencing
- Involves identifying and documenting logical relationships between schedule activities.
- Activities can be arranged logically with appropriate precedence relationships, leads, and lags, supporting a realistic and achievable project schedule.
- Sequencing can be done manually or with project management software and manual and automated techniques can be combined.
Establishment of the Sequence of the Activities: Inputs
- Project scope statement contains product scope description affecting activity sequencing.
- Activity list described in Section 6.1.3.1
- Activity attributes described in Section 6.1.3.2 include identified, coded activities
- Milestone list described in Section 6.1.3.3.
- Approved Change Requests, described in Section 4.4.1.4.
Tools and Techniques used in Activity Sequencing
- Precedence Diagramming Method (PDM) uses boxes or rectangles/nodes, to represent activities connected with arrows showing dependencies. Has four dependency types:
- Finish to Start—successor activity depends on predecessor activity finishing
- Finish to Finish—successor activity depends on predecessor activity finishing
- Start to Start—successor activity depends on predecessor activity starting
- Start to Finish—successor activity relies on starting predecessor
- Arrow Diagramming Method (ADM) creates a project schedule network diagram connecting activities with nodes/arrows
- Schedule network templates can be used to expedite preparation of the project schedule network activity
- Dependencies consist of mandatory dependencies when the project team determines dependencies inherent in the nature of the work being done.
- Discretionary dependencies are determined by the project team, but should be fully documented since they produce arbitrary total slack values- "soft logic".
- External dependencies refer to relationships between project activities and non-project activities
Applying Advances and Delays
- Project teams determine dependency requirements (6.2.2.4) or use leads and lags to define relationship logic.
- Leads accelerate the successor activity
- Lags delay successor activities
Establishing the Sequence of the Activities: Exits
- Project Schedule Network Diagrams provide the network
- Activity List Updates occur when change requests come as a result of Sequence of Activities analysis
- Activity Attributes are updated to include the established logical relationships and any related advances and delays- update those related to Activity if those change.
- Change Requests prepare logical project relations, advances, lags might reveal instances that create a change request on activity (add/remove activity).
Estimating Activity Resources
- Involves determining the resources (people, equipment, material) and amounts needed, and resource availability
- Coordinated with the cost estimating process (Section 7.1).
Inputs to Estimating Activity Resources
- Environmental factors, including availability of project management information systems
- Organizational process assets with personnel policies and supply purchasing. Past project review shows required resources for similar work
- Activity list identifying activities for the resources
- Activity attributes providing key inputs, defining activities for estimating resources
- Resource availability potential is evaluated
- Project Management Plan provides schedule for estimating activity resources
Resource Estimation Tools and Techniques
- Project team may require expert judgment for entries in a process. A planning or resource estimation group can provide experience
- Many activities have alternative methods, with a range of values and information (Different skill ability and machines)
- Industry-produced unit costs and resource periodicals
- Resource breakdown structures defined with complexities software help organize resources and developing resource estimation.
Increase confidence
- When there is very little confidence with an activity schedule
- Activities with inter-dependencies affect scheduling documented if there are dependencies
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.