Which project document should you compare the scope change requests to?
Which project document should you compare the scope change requests to?
- Communications Management Plan
- Risk Register
- Project Charter
- Work Breakdown Structure (WBS) (correct)
When assessing the degree to which the project scope will change, which document is most relevant?
When assessing the degree to which the project scope will change, which document is most relevant?
- Project Schedule
- Scope Management Plan (correct)
- Change Control Plan
- Stakeholder Register
Which project document provides an initial description of the project scope?
Which project document provides an initial description of the project scope?
- Project Charter (correct)
- Quality Management Plan
- Risk Register
- Work Breakdown Structure (WBS)