Podcast
Questions and Answers
What type of relationship arises when one activity cannot begin until another is partially or wholly completed?
What type of relationship arises when one activity cannot begin until another is partially or wholly completed?
During which month is the Diversion Stage activity scheduled to take place?
During which month is the Diversion Stage activity scheduled to take place?
Which relationship type should be considered when two activities pose a safety hazard if performed simultaneously?
Which relationship type should be considered when two activities pose a safety hazard if performed simultaneously?
What is the total duration for the installation of Outlet Gates?
What is the total duration for the installation of Outlet Gates?
Signup and view all the answers
What method can be employed to estimate the duration of an activity in construction?
What method can be employed to estimate the duration of an activity in construction?
Signup and view all the answers
What does the resource relationship in project sequencing primarily focus on?
What does the resource relationship in project sequencing primarily focus on?
Signup and view all the answers
Which activity is completed immediately before the Curtain Grout?
Which activity is completed immediately before the Curtain Grout?
Signup and view all the answers
What is the cumulative Work Progress Ratio after the installation of Trash Racks?
What is the cumulative Work Progress Ratio after the installation of Trash Racks?
Signup and view all the answers
Which of the following is NOT a recommended approach to estimate activity duration?
Which of the following is NOT a recommended approach to estimate activity duration?
Signup and view all the answers
How much of the total cost is allocated to Activity D?
How much of the total cost is allocated to Activity D?
Signup and view all the answers
What is the formula for calculating the early finish date of an activity?
What is the formula for calculating the early finish date of an activity?
Signup and view all the answers
During the backward pass, what does the late finish date of an activity depend on?
During the backward pass, what does the late finish date of an activity depend on?
Signup and view all the answers
Which definition best describes 'total float'?
Which definition best describes 'total float'?
Signup and view all the answers
What is the correct method to find the late start date of any activity in the backward pass?
What is the correct method to find the late start date of any activity in the backward pass?
Signup and view all the answers
What is free float best described as?
What is free float best described as?
Signup and view all the answers
How is link lag defined?
How is link lag defined?
Signup and view all the answers
What does Rule 4 of the forward pass state?
What does Rule 4 of the forward pass state?
Signup and view all the answers
What is the earliest time an activity can finish called?
What is the earliest time an activity can finish called?
Signup and view all the answers
What is the primary relationship utilized in the Arrow Diagram Method (ADM)?
What is the primary relationship utilized in the Arrow Diagram Method (ADM)?
Signup and view all the answers
Which of the following statements is true about dummy activities in PDM?
Which of the following statements is true about dummy activities in PDM?
Signup and view all the answers
How does the Project Duration estimation differ between ADM and PDM?
How does the Project Duration estimation differ between ADM and PDM?
Signup and view all the answers
In the context of the Arrow Diagram Method (ADM), what is the duration for activity E?
In the context of the Arrow Diagram Method (ADM), what is the duration for activity E?
Signup and view all the answers
Which option describes the total float in project management?
Which option describes the total float in project management?
Signup and view all the answers
Which of these activities is independent in the PDM provided?
Which of these activities is independent in the PDM provided?
Signup and view all the answers
Which of the following activities has the longest duration in the provided example?
Which of the following activities has the longest duration in the provided example?
Signup and view all the answers
What relationship types are identified in the PDM?
What relationship types are identified in the PDM?
Signup and view all the answers
What does an arrow represent in an arrow diagram?
What does an arrow represent in an arrow diagram?
Signup and view all the answers
Which path is identified as the critical path in the example provided?
Which path is identified as the critical path in the example provided?
Signup and view all the answers
How is the total float of an activity calculated?
How is the total float of an activity calculated?
Signup and view all the answers
What does a total float of zero indicate for an activity?
What does a total float of zero indicate for an activity?
Signup and view all the answers
What does the 'ES' in the activity table represent?
What does the 'ES' in the activity table represent?
Signup and view all the answers
If Activity E has a total float of 1 week, what does this imply?
If Activity E has a total float of 1 week, what does this imply?
Signup and view all the answers
Which activity has the longest duration in the displayed project?
Which activity has the longest duration in the displayed project?
Signup and view all the answers
In the example, what is the function of the nodes in the arrow diagram?
In the example, what is the function of the nodes in the arrow diagram?
Signup and view all the answers
Study Notes
Project Scheduling
- There are four types of relationships between activities that need to be considered when establishing the sequence of work:
- Physical: one activity must be partially or totally complete before another can start.
- Safety: simultaneous activity performance can result in safety hazards.
- Resource: limited resource availability prevents activities from using the same resource at the same time.
- Preferential: contractor preferences for sequencing activities.
Estimating Activity Duration
- Activity duration can be estimated using:
- Company historic records
- Superintendent or foreman input
- Standard estimating guides
- Labor Hour Productivity equation.
Labor-Hour Productivity Method
- This method calculates the total labor-hours required for an activity by multiplying (labor-hours/Unit) x (no. of Units).
S-Curve
- An S-curve (or progress curve) visually represents the project's planned progress over time.
- It shows the cumulative cost and work progress as a function of time.
Scheduling Computations: Forward Pass Rules
- The forward pass calculates the earliest start (ESD) and earliest finish (EFD) dates of each activity.
- Rule 1: The ESD of the first activity is 0.
- Rule 2: All activities are assumed to start as soon as possible after their predecessors are complete.
- Rule 3: EFD is calculated by adding the activity duration to the ESD: EFD₁= ESD₁ + T₁.
- Rule 4: At merge points, the ESD is the largest EFD of the preceding activities.
Scheduling Computations: Backward Pass Rules
- The backward pass calculates the latest start (LSD) and latest finish (LFD) dates of each activity.
- Rule 1: The LFD of the last activity is equal to its EFD.
- Rule 2: LSD is calculated by subtracting the activity duration from the LFD: LSD₁= LFD₁ - T₁.
- Rule 3: The LFD of an activity is the smallest LSD of the following activities.
The Float Concept
- Float (or slack) is the scheduling leeway an activity has.
- Total float (TF) is the time an activity can be delayed without delaying the project.
- Total Float Equation: TF₁ = LFD - EFD₁ = LSD, - ESD₁.
- Free float is the time an activity can be delayed without delaying a following activity or the project finish.
- Link lag is the difference between the ESD of an activity and the EFD of its preceding activity.
- Free float is determined by the minimum value of all link lags following an activity.
ADM vs. PDM
- ADM (Arrow Diagram Method) and PDM (Precedence Diagramming Method) are project scheduling methods.
- ADM: uses arrows to represent activities and nodes to represent events.
- PDM: uses boxes to represent activities and arrows to show relationships between them.
- Both methods have different ways of representing relationships between activities.
- ADM: primarily uses finish-to-start relationships.
- PDM: uses a more complex relationship system, including finish-to-start, finish-to-finish, and start-to-finish.
- ADM: is simpler in terms of total float calculation.
- PDM: offers more flexibility in estimating activity duration.
Arrow Diagram Method (ADM)
- ADM is a graphical method to represent project networks.
- It's used to:
- Estimate the total project duration.
- Calculate the total float for each activity.
- Create a bar chart to visualize the schedule.
- The critical path is the longest path in the network and determines the project's overall duration.
- Activities on the critical path have zero float.
Example 4: Arrow Diagram Method
This example demonstrates how to use ADM to calculate project duration, total float, and create a bar chart.
Example 5: Arrow Diagram Method
This example showcases how to use ADM in a project that requires more complex activity relationships.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers essential concepts in project scheduling, including the types of relationships between activities and methods for estimating activity duration. Key topics include the Labor-Hour Productivity Method and the S-Curve, providing insights into effective project management practices.