Questions and Answers
What is the primary factor that determines the method used to establish the duration of an activity?
What is the primary factor that determines the method used to establish the duration of an activity?
- The complexity of the activity
- The availability of resources and budget
- The size of the activity in terms of time consumption and required accuracy (correct)
- The experience of the scheduler in similar projects
How can a scheduler estimate the duration of an activity without detailed analysis?
How can a scheduler estimate the duration of an activity without detailed analysis?
- By relying on intuition
- By consulting with experts in the field
- By analyzing past project performances (correct)
- By using a complex mathematical model
What is the effect of increasing the crew size on the duration of an activity?
What is the effect of increasing the crew size on the duration of an activity?
- It has no effect on the duration
- It results in longer durations
- It results in shorter durations (correct)
- It depends on the type of activity
What is a significant portion of time devoted to in short duration activities?
What is a significant portion of time devoted to in short duration activities?
What is the primary purpose of analyzing the S-curve in project management?
What is the primary purpose of analyzing the S-curve in project management?
What is the primary consideration in determining the duration of a hand excavation task?
What is the primary consideration in determining the duration of a hand excavation task?
What factor should be considered when determining the material inflow rate?
What factor should be considered when determining the material inflow rate?
How can a scheduler determine the duration of a drywall installation task?
How can a scheduler determine the duration of a drywall installation task?
What is the primary concern when scheduling certain activities in a construction project?
What is the primary concern when scheduling certain activities in a construction project?
What is the effect of reducing the crew size on the duration of an activity?
What is the effect of reducing the crew size on the duration of an activity?
What is the significance of selecting scheduled dates in a construction project?
What is the significance of selecting scheduled dates in a construction project?
What is the benefit of using past project performances to estimate the duration of an activity?
What is the benefit of using past project performances to estimate the duration of an activity?
What is the main benefit of developing a realistic schedule in a construction project?
What is the main benefit of developing a realistic schedule in a construction project?
What should be examined when scheduling major activities in a construction project?
What should be examined when scheduling major activities in a construction project?
What is the significance of the S-curve in project management?
What is the significance of the S-curve in project management?
What should be reflected in the initial schedule of a construction project?
What should be reflected in the initial schedule of a construction project?
What is the primary reliance of developing and using schedules in project management?
What is the primary reliance of developing and using schedules in project management?
Why is it essential to accurately determine activity durations in project planning?
Why is it essential to accurately determine activity durations in project planning?
What type of estimates are prepared by architects, engineers, or consultants to approximate project costs?
What type of estimates are prepared by architects, engineers, or consultants to approximate project costs?
What is the primary reason for preparing conceptual estimates in project planning?
What is the primary reason for preparing conceptual estimates in project planning?
What is a key factor in preparing accurate conceptual estimates?
What is a key factor in preparing accurate conceptual estimates?
Why do private owners require an estimate of project costs?
Why do private owners require an estimate of project costs?
What is the relationship between activity durations and schedule accuracy?
What is the relationship between activity durations and schedule accuracy?
When is conceptual estimating typically done in a project?
When is conceptual estimating typically done in a project?
Study Notes
Estimating Durations
- Estimating durations depends on the size and accuracy required for the activity.
- A significant activity, such as excavating 375,000 cubic yards of material, warrants considerable investigation.
- Past project performances can be used to make duration estimates without detailed analysis.
- A rough estimate can be made by visualizing the work being done at a given pace, such as installing drywall at a rate of four rooms per day.
Factors Affecting Durations
- Crew size can affect durations, with increases resulting in shorter durations and reductions resulting in longer durations.
- Mobilization allowances can take up a significant percentage of time for short-duration activities.
- The "lazy S-curve" presents the full range of options open to the project manager, including actual cost data compared to predicted.
Scheduling Considerations
- The schedule should reflect significant concerns related to materials, such as storage space and installation rates.
- Material inflow rates should be based on available storage space and installation rates.
- The schedule should anticipate the need for precautionary measures, such as guarding against rain, snow, and temperature extremes.
- Major activities should be examined to determine the time of year they are scheduled to occur.
Importance of Scheduling
- A realistic schedule is desirable despite the relative uncertainties inherent in construction projects.
- Arrangements made for materials' deliveries, subcontractor start dates, and contract-specified milestone dates suggest the initial schedule is important.
- Selecting scheduled dates may include considering the likelihood that the assumptions of the network model will not hold true.
Determining Activity Durations
- Activity durations must be developed with a certain amount of accuracy for the schedules to be valuable.
- The accuracy and usefulness of the schedule are directly related to the accuracy of individual activity durations.
- Conceptual estimates are rough approximations of anticipated costs, prepared by architects, engineers, or consultants.
- Conceptual estimates require a clear understanding of the owner's wants and a good "feel" for probable costs.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the methods used to establish the duration of an activity in project management, including using past project performances and detailed analysis.