Project Management Terminology
24 Questions
0 Views

Project Management Terminology

Created by
@WellEducatedHeliotrope6193

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the primary disadvantage of Budgeting in relation to cost or resource monitoring?

  • It shows work element interrelationships
  • It considers the probability of completion date
  • It considers the effects of delayed elements on others
  • It does not show work element interrelationships (correct)
  • What is the minimum time required to complete a project determined by?

  • Free Float
  • Total Float
  • Critical Path (correct)
  • Late Start
  • What is the term for the amount of time an activity may be delayed without delaying the completion date of the project?

  • Total Float (correct)
  • Free Float
  • Early Start
  • Late Start
  • What is the primary purpose of the Program Evaluation and Review Technique (PERT)?

    <p>To assess the risk of highly uncertain projects</p> Signup and view all the answers

    What is the term for the slack in the schedule of an activity?

    <p>Free Float</p> Signup and view all the answers

    What is represented by a dotted line on the arrow network diagram?

    <p>Dummy Activity</p> Signup and view all the answers

    What is the primary advantage of using PERT?

    <p>It provides a probabilistic approach to scheduling</p> Signup and view all the answers

    What is the term for the series of interconnected activities that determines the minimum time to complete the project?

    <p>Critical Path</p> Signup and view all the answers

    What is the purpose of project monitoring and control?

    <p>To detect and correct deviations from the desired budget, schedule, and quality</p> Signup and view all the answers

    What does the cost slope represent in the time-cost relationship?

    <p>The marginal trade-off of cost-to-time for an activity</p> Signup and view all the answers

    What happens to the duration of an activity when resources are added?

    <p>The duration decreases, but the direct cost typically increases</p> Signup and view all the answers

    What is the purpose of setting a project plan?

    <p>To communicate the plan to all participants</p> Signup and view all the answers

    What does the variance measure in the context of activity completion time?

    <p>The variability in the activity completion time</p> Signup and view all the answers

    What is the goal of project monitoring?

    <p>To detect deviations from the desired budget, schedule, and quality</p> Signup and view all the answers

    What is the purpose of control schedules for time and work?

    <p>To detect and correct deviations from the desired budget, schedule, and quality</p> Signup and view all the answers

    What is the relationship between the duration of an activity and the direct cost when resources are added?

    <p>The duration decreases, and the direct cost typically increases</p> Signup and view all the answers

    What is the purpose of Step 2 in the given PERT analysis?

    <p>To distribute the cost of an activity equally across its duration</p> Signup and view all the answers

    What is the total project cost mentioned in the example?

    <p>321k</p> Signup and view all the answers

    What is the accumulated cost on the 3rd day of the project?

    <p>65k</p> Signup and view all the answers

    What is the percentage of accomplishment on the 3rd day of the project?

    <p>14.02%</p> Signup and view all the answers

    What is the purpose of Step 3: Periodic Cash Flow in the PERT analysis?

    <p>To sum the cost per period for the entire project timeline</p> Signup and view all the answers

    How is the cost corresponding to an activity distributed in its duration?

    <p>Equally</p> Signup and view all the answers

    What is the purpose of Step 5: Fill up Table in the PERT analysis?

    <p>To fill up the table with the calculated values</p> Signup and view all the answers

    How many days are represented by the shaded green regions in the timeline for activity 1?

    <p>2 days</p> Signup and view all the answers

    Study Notes

    Project Management Concepts

    • Late Start (LS): the latest time an activity can be started without delaying the project completion date.
    • Total Float (TF): the amount of time an activity can be delayed without delaying the project completion date.
    • Free Float (FF): the amount of time an activity can be delayed without delaying the early start time of the immediately following activity.

    Critical Path Method

    • Critical Path: a series of interconnected activities with zero, free, and total float time, determining the minimum time to complete the project.
    • Dummy Activity: represented by a dotted line on the arrow network diagram, indicating that any activity following the dummy cannot be started until the preceding activities are completed.

    Program Evaluation and Review Technique (PERT)

    • Developed in 1957 by the U.S. Navy as a probabilistic approach to scheduling.
    • More commonly used in the manufacturing industry.
    • Can be used for risk assessment of highly uncertain projects.

    Network Scheduling

    • Represented by shaded green regions on the timeline.
    • Note that we draw the bar for activity D after activity A is completed, meaning at the end of day 2.

    Time-Cost Relationship

    • Represents the shortest duration and the greatest cost.
    • Cost slope: represents the time-cost relationship or the marginal trade-off of cost-to-time for the activity.

    Project Monitoring and Control

    • Goal: to detect and correct deviations from desired budget, schedule, and quality.
    • Detection: monitoring.
    • Correction: control.
    • Bring project performance back in line with plans.

    Project Monitoring

    • Set of procedures and management practices.
    • Review of performance achieved or forecasted.
    • Uses performance metrics.

    Project Plan

    • Must be developed with input from people who will be performing the work.
    • Must be communicated to all participants.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Test your understanding of project management concepts such as Late Start, Total Float, and Budgeting.

    More Like This

    Construction Project Management Fundamentals
    10 questions
    Construction Project Management
    24 questions

    Construction Project Management

    AuthenticFantasticArt avatar
    AuthenticFantasticArt
    Advanced Construction Project Management Quiz
    24 questions
    Use Quizgecko on...
    Browser
    Browser