Questions and Answers
Explain how resource leveling can mitigate potential project delays.
Explain how resource leveling can mitigate potential project delays.
Resource leveling can prevent project delays by ensuring resources are not overallocated, and by smoothing out resource demands over the project duration, this helps to avoid bottlenecks and ensure that resources are available when needed.
Describe a scenario where using the critical path method is essential for project success.
Describe a scenario where using the critical path method is essential for project success.
The critical path method is essential when tight deadlines and complex task dependencies require precise control over project duration. A scenario where the critical path method is vital is civil construction projects.
How does understanding organizational culture impact project team performance?
How does understanding organizational culture impact project team performance?
Understanding the organizational culture helps align project goals with the organization's values, fosters better communication, and improves team cohesion, leading to enhanced performance and successful project outcomes.
Why is defining the project scope crucial in construction estimation, and what potential issues arise if it's not clearly defined?
Why is defining the project scope crucial in construction estimation, and what potential issues arise if it's not clearly defined?
How can value engineering contribute to sustainable construction practices?
How can value engineering contribute to sustainable construction practices?
Explain how the process of commissioning helps ensure a building operates as intended.
Explain how the process of commissioning helps ensure a building operates as intended.
Describe how a well-structured Work Breakdown Structure (WBS) can aid in project monitoring and control.
Describe how a well-structured Work Breakdown Structure (WBS) can aid in project monitoring and control.
In what ways might market analysis influence procurement planning decisions?
In what ways might market analysis influence procurement planning decisions?
How can understanding span of control improve organizational efficiency and project outcomes?
How can understanding span of control improve organizational efficiency and project outcomes?
Explain the importance of regular cost updates in maintaining the accuracy of construction cost estimates throughout a project's lifecycle.
Explain the importance of regular cost updates in maintaining the accuracy of construction cost estimates throughout a project's lifecycle.
Flashcards
Project Description
Project Description
Includes the project's timeline and requirements.
Cubic Meter
Cubic Meter
Used to measure excavation work for payment.
Prequalification Statements
Prequalification Statements
Written records that describe a contractor's capabilities and track record.
Testing and Inspection
Testing and Inspection
Signup and view all the flashcards
Functional Organization
Functional Organization
Signup and view all the flashcards
Project Manager
Project Manager
Signup and view all the flashcards
Organizational Style
Organizational Style
Signup and view all the flashcards
Deliverables
Deliverables
Signup and view all the flashcards
Cost Estimation
Cost Estimation
Signup and view all the flashcards
Resource Leveling
Resource Leveling
Signup and view all the flashcards
Study Notes
Project Timelines
- The project's timeline and requirements are in the Project Description section of the Invitation to Bid.
Excavation Work
- The cubic meter method is commonly used to measure excavation work for payment.
Contractor Records
- Prequalification Statements are written records describing a contractor's capabilities and track record.
Material Testing
- Testing and Inspection sections in documents outline testing methods and acceptance criteria for materials and workmanship.
Functional Organization
- Functional Organizations have a structure where each employee reports to one clear supervisor.
Project Objectives
- The Project Manager is assigned by an organization to lead the team responsible for achieving project objectives.
Organizational Culture
- Organizational Style refers to the cultural norms developed within an organization over time.
Project Outputs
- Deliverables are primary outputs of a project and can be tangible or intangible.
Project Budget
- Cost Estimation refers to forecasting expenses to ensure a project stays within the budget.
Resource Management
- Adjusting task start and finish dates to balance resource demand and supply is called Resource Leveling.
Scheduling Techniques
- Activity on Node is a scheduling technique that uses nodes to represent activities and logical relationships.
Task Completion
- Duration refers to the time required to complete an activity.
Construction Standards
- Specification documents outline the works, materials, and quality standards in a construction project.
Bid Instructions
- Instruction to Bidders sets out what is expected to be returned by the contractor and by what date.
Contract Notice
- The Project Owner/Client provides a notice of award of contract.
Project Information
- Invitation to Bid provides information on the scope of work, timeline, and project requirements to potential bidders.
Contractual Conditions
- Retainage/Retention Money is a contractual condition allowing the owner to withhold a portion of payment for a set period after project completion.
Organizational Values
- Organizational Culture refers to the shared mission, values, and practices influencing how an organization conducts projects.
Structural Elements of an Organization
- Money as a structural element of an organization refers to the financial resources required to achieve objectives.
Organization
- Organization describes the systematic arrangement of people aimed at accomplishing a specific purpose.
Construction Planning
- Construction Planning involves determining activities, resources, timelines, and sequence of work to achieve project objectives.
Project Duration
- The Critical Path Method is used for estimating the minimum project duration and scheduling flexibility.
Precedence Diagramming Method
- Finish-to-Start is the most common type of dependency in the Precedence Diagramming Method (PDM).
Critical Path
- Float/Slack measures the time difference between a path and the critical path.
Contract Agreements
- Contract Agreement serves as a written agreement between a contractor and a client.
Project Completion
- Performance Security refers to the financial guarantee provided to ensure a project's completion.
Contract Conditions
- General Conditions of Contract is the general term for conditions applied to ensure compliance with project quality.
Project Costs
- Bill of Quantities lists the quantities, rates, and total cost of work activities in a project.
Project Endeavors
- Project is a temporary endeavor undertaken to create a unique product, service, or result.
Organizational Output
- Machines as a structural element in an organization includes tools necessary to produce the desired output.
Strategic Management Skills
- Strategic and Business Management Skills defines the ability to see the high-level overview of an organization and negotiate strategic decisions.
Project Management Skills
- Technical Project Management Skills defines the ability to manage project elements such as cost, schedule, and risks effectively.
Work Breakdown Structure
- Work Package is the lowest level of a WBS that can be scheduled, estimated, and monitored.
Scheduling Tools
- Gant Chart is a scheduling tool that uses horizontal bars to represent activity durations on a timeline.
Logical Relationships
- Finish-to-Finish is a logical relationship that ensures a successor activity cannot finish until a predecessor activity has finished.
Network Diagrams
- Dummy Activity is used in a network diagram to show dependency without consuming time.
Quantity Surveying
- Quantity Takeoff's primary purpose is to calculate the precise quantities of materials required for a project.
Construction Costs
- Overhead Cost covers costs such as administrative expenses, utilities, and permits.
Project Wages
- Direct Labor Cost refers to wages paid to workers directly involved in project tasks
Construction Estimates
- Contingency is an allowance for unforeseen expenses included in a construction estimate.
Project Profitability
- Profit Margin is a percentage added to ensure contractor profitability in a project.
Value Engineering
- Cost Reduction is a key objective of value engineering in construction projects.
Economic Factors
- Inflation is an economic factor affecting the cost of construction materials over time.
Project Contingencies
- 5%-10% is typically set aside for contingencies, which are funds reserved within a budget to address unforeseen expenses.
Site Preparation
- Site Preparation involves removing debris and leveling the land before construction begins.
Construction Types
- Industrial Construction includes factories, warehouses, and power plants.
Procurement Planning
- Procurement Planning involves selecting materials, suppliers, and subcontractors.
Project Execution
- Project Scheduling is the technique of dividing a project into phases to ensure smooth execution.
Construction Projects
- Cost Estimate/Estimation are the processes of predicting the costs and resources required for a construction project.
Estimation Methods
- Unit Price Estimate follows estimation method based on standardized costs for specific items or activities.
Construction Cost
- Define the Project Scope is the first step in construction estimation.
Equipment Expenses
- Equipment Cost is the term for expenses related to equipment rental, fuel, and maintenance.
Alternative Solutions
- Creative Phase is the value engineering phase involving brainstorming alternative solutions.
Cost-Saving Selection
- Evaluation Phase is where value engineering involves evaluating cost-saving options for feasibility.
Cost Estimation
- The Basis of Estimate (BOE) helps define the assumptions and methodology used in cost estimation.
Constructions
- Commercial Construction includes office buildings, malls, and hospitals.
Zoning Regulations
- Zoning Permit/Approval ensures the project complies with local land use regulations.
Building Systems
- Commissioning process involves testing plumbing, electrical, and HVAC systems before handover.
Defect Process
- Final Inspection process reviews the final structure for defects before project completion.
Project Work
- Construction Schedule & S-Curve outline the schedule of work completion, such as milestones.
Bid Details
- Addenda amends or clarifies bid documents before submission.
Employee Compensation
- Dole Compliance ensures that workers are compensated according to minimum wage laws.
Contract Bids
- Bid Form ensures contractors with the authority to bid and comply with specified requirements.
Organization Authority
- Projectized Organization allows project managers to have a high level of independence and authority.
Project Leadership
- Leadership Skills involves the ability to guide, motivate, and direct a project team.
Span of Control
- The number of people reporting to a manager within an organization is the Span of Control.
Project Process
- Work Breakdown Structure (WBS) breaks down a project into smaller, manageable components.
Risk Management
- The process identifies potential risks and develops mitigation strategies, termed Risk Management.
Network Designs
- The graphical representation of task dependencies and sequences in a project is a Network Diagram.
Critical Project
- Critical Path refers to is the sequence of activities with zero float which determines the project duration.
Network Activities
- An Event is a visual representation of start & end points for activities within a project network.
Cost Breakdown
- The detailed Estimate provides comprehensive cost breakdown.
Project Management Roles
- A job such as Project Manager/Engineer, is an example of indirect labor cost.
Information Process
- Information Phase, is the first step in the value engineering process.
Overheads
- Utility bills or "Overhead" covers administrative expenses, utilities, and permits in a project.
Value Control
- Value Engineering aims to improve project value by simultaneously reducing costs while maintaining quality.
Estimating Construction Costs
- Ensuring the accuracy of construction cost estimates is to use Regular Cost Updates.
Types of Construction
- Infrastructure (Civil Construction) involves roads, bridges, and railways.
Physical Structures
- The process of planning, designing, building infrastructure of physical structures is Construction.
Project Planning
- It determines of activities, resources, timelines, and sequence of work to achieve project objectives, labelled as Project planning.
Construction development
- Feasibility studies and design development construction is labelled as the Pre-Construction Phase.
Visual Modifications
- The document labelled As-built Drawings records design modifications made during construction.
Project Costs
- 5%-10% is typically set aside for contingencies, which are funds reserved within a budget to address unforeseen expenses.
Project Phase
- Preliminary Estimate can be used during the conceptual phase of a project.
Project Labour
- Construction Workers is an example of direct labour cost.
Construction Improvement
- Value Engineering purpose is to improve project value reducing costs while maintaining or enhancing quality.
Construction Specialists
- Subcontractor Cost is the term describes fees paid to external specialists or subcontractors for specific construction tasks?
Project Phases
- The Information Phase, also includes collecting project data and identifying cost drivers is a phase of value engineering.
Material Processes
- Multiple supplier prices to optimise material costs with Market Analysis.
Construction Buildings
- Residential Construction includes single-family homes, apartments, and condominiums.
Soil assesment
- Site Analysis assesses soil conditions, topography, and accessibility.
Occupancy
- A Certificate of Occupancy, Certifies the building is safe for occupancy.
Project Contigencies
- 5% - 10% of the project contigency is set aside.
Modular Construction
- Modular construction involves of assembling pre-manufactured building components.
Quailty Control
- Quality Control ensures of ensuring materials and work meet project standards?