What is the primary objective of fast tracking activities in a project?
What is the primary objective of fast tracking activities in a project?
- To add more resources to critical activities
- To delay non-critical activities
- To do activities in parallel or overlap them (correct)
- To reduce the project scope
What is the effect of adding more resources to critical activities in a project?
What is the effect of adding more resources to critical activities in a project?
- Decreases the project duration (correct)
- Changes the project scope
- Increases the project duration
- Has no impact on the project duration
What is the purpose of a precedence diagram in project management?
What is the purpose of a precedence diagram in project management?
- To allocate resources to activities
- To estimate the project duration
- To determine the activity dependencies (correct)
- To identify the critical path
What is the type of dependency between activities A and D in the given project?
What is the type of dependency between activities A and D in the given project?
What is the duration of activity F in the given project?
What is the duration of activity F in the given project?
Which of the following is a technique used to shorten the project schedule?
Which of the following is a technique used to shorten the project schedule?
What is the critical path method used for in project management?
What is the critical path method used for in project management?
What is the effect of changing the scope of critical activities on the project schedule?
What is the effect of changing the scope of critical activities on the project schedule?
What is the purpose of a network diagram in project management?
What is the purpose of a network diagram in project management?
What is the type of dependency between activities B and E in the given project?