During the second phase of a project, a senior stakeholder requested new features that were not in the original scope. The project manager included these features, resulting in budget overruns and schedule delays. What should the project manager have done differently to avoid this situation?

  • Added the features immediately to maintain stakeholder satisfaction.
  • Informed the stakeholder that additional features could be included in a follow-up project.
  • Revised the project plan and gained approval from all stakeholders before implementing changes. (correct)
  • Asked the team to accelerate the schedule to accommodate the changes.

A project team is using an agile approach, but one team member is consistently delivering incomplete tasks due to a misunderstanding of priorities. What should the project manager do to address the issue?

  • Increase the sprint duration to give the team member more time.
  • Replace the team member with someone more experienced.
  • Conduct a retrospective to review task prioritization and communication processes. (correct)
  • Assign a mentor to the team member to provide guidance.

A critical project milestone is approaching, and the client demands a status report detailing the remaining work. However, some team members have provided inconsistent updates on task completion. What should the project manager do?

  • Revise the project schedule to reflect the inconsistencies.
  • Conduct a sprint review to validate task completion and align the status report. (correct)
  • Ask the team members to update their tasks and delay the report.
  • Submit the status report based on the available information.

During a high-stakes software development project, the project manager notices that stakeholders have differing definitions of "project success." What is the best action to resolve this?

<p>Facilitate a session to align stakeholders on success criteria and update the project charter. (C)</p> Signup and view all the answers

A client requests frequent updates, but their availability for feedback sessions is limited. The project manager feels this is slowing progress. What should they do?

<p>Revise the communication management plan to include asynchronous updates and feedback options. (B)</p> Signup and view all the answers

The team identifies a significant defect in a prototype during a client demonstration. The client is dissatisfied and requests an explanation. How should the project manager respond?

<p>Accept responsibility, analyze the defect, and propose a corrective action plan. (C)</p> Signup and view all the answers

A project manager discovers that a critical resource has been assigned to another project, jeopardizing the project timeline. What is the best course of action?

<p>Escalate the issue to senior management for resource reallocation. (B)</p> Signup and view all the answers

Midway through a project, a key stakeholder questions the alignment of deliverables with organizational strategy. What should the project manager do?

<p>Conduct a review of project objectives, deliverables, and strategy alignment with all stakeholders. (D)</p> Signup and view all the answers

A client is dissatisfied with the pace of progress in an agile project. They demand weekly deliverables, which the team finds unreasonable. What should the project manager do?

<p>Negotiate with the client to agree on realistic delivery timelines. (A)</p> Signup and view all the answers

The project sponsor unexpectedly requests a significant reduction in budget while maintaining scope and timeline. What is the project manager's best response?

<p>Use value engineering to reduce costs while maintaining essential deliverables. (C)</p> Signup and view all the answers

A project team is transitioning to an agile framework for the first time. During the first sprint, team members struggle with collaboration and frequent miscommunications. What should the project manager do?

<p>Conduct a team workshop to discuss agile principles and improve communication processes. (B)</p> Signup and view all the answers

During a political campaign project, the project manager discovers that external conditions, such as new election regulations, have changed. What should the project manager do first?

<p>Update the risk register and initiate a change request. (D)</p> Signup and view all the answers

A project involves multiple vendors, and one vendor fails to meet their contractual obligations. This delays project deliverables. What is the best way for the project manager to handle this?

<p>Refer to the contract, enforce penalties, and activate the contingency plan. (A)</p> Signup and view all the answers

During a sprint review, the client complains about incomplete features. The team explains that the definition of "done" was unclear. What should the project manager do to prevent this in future sprints?

<p>Collaborate with the team and stakeholders to define a clear &quot;definition of done.&quot; (D)</p> Signup and view all the answers

In a project to redesign a hospital's emergency department workflow, team members frequently disagree on priorities. What should the project manager do?

<p>Facilitate a stakeholder workshop to align on objectives and prioritize tasks. (C)</p> Signup and view all the answers

A project team is working on a software system. During testing, the team identifies a critical bug, but fixing it will require delaying the project. What should the project manager do?

<p>Convene a meeting with stakeholders to assess the impact and determine the next steps. (B)</p> Signup and view all the answers

A stakeholder reports dissatisfaction with the project communication plan, stating they are not receiving sufficient updates. What should the project manager do?

<p>Review the communication management plan and adjust it to better meet stakeholder needs. (D)</p> Signup and view all the answers

The project sponsor requests a detailed report of risks impacting the project's delivery. However, the risk register has not been updated in weeks. What should the project manager do first?

<p>Schedule a risk review session with the team to update the register immediately. (A)</p> Signup and view all the answers

Midway through a project, the client requests a new feature that will require significant rework. The project manager calculates that adding the feature will delay delivery by two weeks. What should the project manager do?

<p>Present the impact analysis to the client and negotiate based on priorities. (A)</p> Signup and view all the answers

The project team is working on a marketing brochure but has not defined the quality criteria for the final deliverable. What is the best course of action for the project manager?

<p>Collaborate with stakeholders to define quality criteria and document them in the project plan. (D)</p> Signup and view all the answers

During a project, a team member consistently fails to meet deadlines, citing unclear instructions. What should the project manager do?

<p>Provide clear instructions and verify understanding through regular check-ins. (A)</p> Signup and view all the answers

A project team is experiencing scope creep due to undocumented client requests. What should the project manager do to regain control?

<p>Implement stricter controls on changes and update the change management process. (B)</p> Signup and view all the answers

A project manager notices that team members are bypassing the formal approval process for changes to accelerate work. As a result, stakeholders are unaware of these changes. What should the project manager do?

<p>Enforce the existing change management process and communicate its importance to the team. (C)</p> Signup and view all the answers

During a sprint review, the product owner insists on reprioritizing backlog items to include a last-minute request. The team is concerned this will disrupt progress. What should the project manager do?

<p>Facilitate a backlog refinement session to evaluate the request's impact and make a decision. (A)</p> Signup and view all the answers

While reviewing the project schedule, the project manager finds that several tasks have been underestimated, putting the timeline at risk. What is the best course of action?

<p>Update the schedule to reflect the revised estimates and inform stakeholders. (D)</p> Signup and view all the answers

A project manager is leading a campaign for political office but struggles to maintain team engagement due to unclear roles. What should the project manager do to resolve this issue?

<p>Assign roles based on team members' strengths and document responsibilities in a RACI chart. (B)</p> Signup and view all the answers

During a project to develop an energy-efficient vehicle, the client requests additional features that exceed the approved budget. What should the project manager do first?

<p>Perform a cost-benefit analysis and present it to the client for decision-making. (D)</p> Signup and view all the answers

In an agile project, the team is struggling to deliver work at a consistent pace. The product owner suggests extending sprint durations. What should the project manager do?

<p>Conduct a retrospective to identify underlying issues and improve team efficiency. (C)</p> Signup and view all the answers

During a hospital workflow redesign project, the project sponsor requests a detailed cost analysis midway through execution. However, the cost management plan has not been updated. What should the project manager immediately do?

<p>Update the cost management plan immediately and provide the sponsor with the requested analysis. (D)</p> Signup and view all the answers

A project team is implementing a new quality improvement process but encounters resistance from staff members. What should the project manager do to address this resistance?

<p>Organize training sessions to explain the benefits of the new process and address concerns. (A)</p> Signup and view all the answers

The project sponsor prioritizes meeting the schedule, but team members are concerned about the deliverables' quality. What is the best way for the project manager to handle this conflict?

<p>Balance schedule and quality by negotiating priorities with the sponsor and team. (D)</p> Signup and view all the answers

A key stakeholder requests to be more involved in decision-making during the project execution phase. What should the project manager do?

<p>Update the stakeholder engagement plan to reflect the new level of involvement. (D)</p> Signup and view all the answers

The project manager discovers that the team has misunderstood the project's objectives, causing misaligned deliverables. What should the project manager do?

<p>Conduct a workshop to realign the team with project objectives and adjust plans if necessary. (D)</p> Signup and view all the answers

A client in a construction project insists on reducing the use of premium materials to save costs, but this could compromise the building's safety standards. What is the project manager's best course of action?

<p>Inform the client of the safety risks and propose alternative cost-saving measures. (D)</p> Signup and view all the answers

A team member raises concerns about unrealistic deadlines during the planning phase of a software project. However, the sponsor insists on maintaining the schedule. What should the project manager do?

<p>Conduct a risk assessment and present the findings to the sponsor to revisit the schedule. (B)</p> Signup and view all the answers

During a portfolio review, it becomes evident that a project does not align with strategic business objectives. What should the project manager do?

<p>Recommend terminating the project to the portfolio manager and reallocate resources to strategic initiatives. (D)</p> Signup and view all the answers

A project to develop a marketing brochure is completed, but the client is unhappy with the result, citing poor alignment with their brand. What should the project manager have done to avoid this?

<p>Conducted regular reviews with the client to ensure alignment with branding. (B)</p> Signup and view all the answers

A key vendor informs the project manager about delays in the delivery of critical materials. What is the project manager's immediate priority?

<p>Review the risk register and activate the contingency plan for procurement delays. (A)</p> Signup and view all the answers

During a political campaign project, team members express frustration over conflicting task assignments. What tool should the project manager use to clarify roles and responsibilities?

<p>A responsibility assignment matrix (RACI chart). (B)</p> Signup and view all the answers

A project manager realizes that team members are not updating the project management information system (PMIS) with task progress. As a result, reports to stakeholders are incomplete. What should the project manager do?

<p>Enforce a policy requiring task updates in the PMIS and explain its importance to the team. (B)</p> Signup and view all the answers

During a sprint retrospective, team members identify that testing was rushed due to poor time management, leading to several defects. What should the project manager prioritize to avoid this in future sprints?

<p>Improve sprint planning to allocate adequate time for testing activities. (C)</p> Signup and view all the answers

In a project to build an office building, new government regulations mandate additional safety inspections, impacting the schedule. What should the project manager do?

<p>Update the project schedule and inform stakeholders of the regulatory changes. (C)</p> Signup and view all the answers

A project manager discovers that risks identified during the planning phase were not monitored, leading to issues during execution. What should the project manager do to address this?

<p>Update the risk register and implement a process to monitor risks regularly. (D)</p> Signup and view all the answers

A team member in a self-organizing agile team repeatedly fails to deliver on commitments. How should the project manager address this?

<p>Facilitate a team discussion to address the issue collaboratively and establish accountability. (D)</p> Signup and view all the answers

During project execution, stakeholders request updates on specific metrics not originally included in the performance measurement baseline. What should the project manager do?

<p>Evaluate the feasibility of tracking the new metrics and update the performance baseline if needed. (C)</p> Signup and view all the answers

A project team working on a prototype discovers a new technology that could significantly improve the product but requires additional funding. What is the project manager's best course of action?

<p>Present a business case to stakeholders, showing the benefits and costs of adopting the technology. (B)</p> Signup and view all the answers

The client for a marketing project requests biweekly reviews, but the project manager notices that progress updates are redundant and time-consuming. What should the project manager do?

<p>Propose a more efficient update method, such as written summaries, and seek the client's agreement. (A)</p> Signup and view all the answers

A project team is tasked with delivering a high-quality product under strict time constraints. The team suggests relaxing quality standards to meet the deadline. What should the project manager do?

<p>Discuss trade-offs with stakeholders and prioritize between quality and time. (D)</p> Signup and view all the answers

A key stakeholder is dissatisfied with the lack of communication during the project initiation phase. What should the project manager have done to avoid this issue?

<p>Developed a stakeholder engagement plan and ensured the stakeholder was appropriately informed. (B)</p> Signup and view all the answers

A project team is consistently missing milestones due to unanticipated dependencies. What should the project manager do to prevent this in the future?

<p>Develop a more detailed project schedule, identifying dependencies and critical paths. (D)</p> Signup and view all the answers

Flashcards

What should a project manager do when a stakeholder requests a feature outside the original scope?

During project planning, a new feature requested by a stakeholder is outside the original scope. It’s important to assess the impact on budget, schedule, and scope. The project manager should discuss the ramifications with the stakeholder and negotiate the best course of action, potentially adjusting the project scope, adding a new phase or task, or prioritizing the feature over existing ones.

What should a project manager do when team members provide inconsistent updates for a status report?

An agile project manager should address inconsistent task completion by conducting a sprint review. This involves validating task completion and aligning the status report with the team's progress. This ensures accurate information for stakeholders.

What should a project manager do when stakeholders have differing definitions of "project success"?

In high-stakes projects, differing definitions of "project success" among stakeholders require proactive communication and alignment. The project manager should hold a session to clarify everyone's expectations, establishing shared goals to prevent confusion and ensure everyone is working towards the same objective.

What should a project manager do when a client requests frequent updates, but their availability for feedback is limited?

When clients need frequent updates but have limited availability for feedback, the project manager should revise the communication management plan. This could involve using asynchronous methods like email, instant messaging, or online project management tools for client feedback.

Signup and view all the flashcards

How should a project manager handle a significant defect discovered during a client demonstration?

When a project team faces a significant defect during a client demonstration, the project manager should take responsibility, analyze the defect, and propose a corrective action plan. This shows accountability and proactive problem-solving to regain client trust.

Signup and view all the flashcards

What should a project manager do when a critical resource is assigned to another project?

When a critical resource is assigned to another project, jeopardizing the project timeline, the project manager should escalate the issue to senior management. They need to secure resource reallocation for the current project to ensure timely delivery.

Signup and view all the flashcards

What should a project manager do when a stakeholder questions the alignment of deliverables with organizational strategy?

When a stakeholder questions the alignment of deliverables with organizational strategy, the project manager should conduct a review of the project objectives, deliverables, and strategy alignment with all stakeholders. This ensures alignment that the project serves the organization's overarching goals.

Signup and view all the flashcards

What should a project manager do when a client demands unreasonable weekly deliverables in an agile project?

A client demanding unreasonable weekly deliverables in an agile project requires negotiation. The project manager should discuss realistic delivery timelines, considering the agile framework's iterative and incremental nature.

Signup and view all the flashcards

What should a project manager do when facing an unexpected budget reduction while maintaining scope and timeline?

When facing an unexpected budget reduction while maintaining scope and timeline, the project manager should use value engineering techniques. Value engineering focuses on minimizing costs while maintaining essential deliverables and project success.

Signup and view all the flashcards

What should a project manager do when a team transitioning to an agile framework struggles with collaboration and communication?

When a team transitioning to agile struggles with collaboration and communication, the project manager should conduct a team workshop. This workshop should focus on agile principles and improve communication processes, promoting understanding and effective teamwork within the new framework.

Signup and view all the flashcards

What should a project manager do when external conditions change during a political campaign project?

When external conditions, such as election regulations, change during a political campaign project, the project manager should update the risk register. They should also initiate a change request, outlining the impact of the regulation change and proposed adjustments to the project plan.

Signup and view all the flashcards

What should a project manager do when a vendor fails to meet contractual obligations?

When a vendor fails to meet contractual obligations, delaying project deliverables, the project manager should refer to the contract. They should enforce penalties, activate the contingency plan, and take corrective action.

Signup and view all the flashcards

What should a project manager do when a client complains about incomplete features due to an unclear definition of "done"?

When a client complains about incomplete features during a sprint review due to an unclear definition of "done," the project manager should collaborate with the team and stakeholders. This includes defining a clear definition of "done" to ensure consistent understanding and prevent reoccurring issues.

Signup and view all the flashcards

What should a project manager do when team members frequently disagree on priorities in a hospital workflow redesign project?

When a team in a hospital's workflow redesign project frequently disagrees on priorities, the project manager should facilitate a stakeholder workshop. This workshop helps align everyone on objectives, prioritize tasks, and increase consensus.

Signup and view all the flashcards

What should a project manager do when a critical bug is found during testing, but fixing it will require delaying the project?

When a critical bug is found during testing and fixing it would delay the project, the project manager should convene a meeting with stakeholders. This allows for risk assessment and determining the next steps, considering the impact of delaying the project versus the risk of deploying with the bug.

Signup and view all the flashcards

What should a project manager do when a stakeholder reports dissatisfaction with the project communication plan?

When a stakeholder reports dissatisfaction with the project communication plan, the project manager should review the communication management plan and adjust it. The plan should be tailored to meet stakeholder needs, ensuring an effective communication strategy.

Signup and view all the flashcards

What should a project manager do when a project sponsor requests a detailed risk report, but the risk register has not been updated?

When a project sponsor requests a detailed report on risks, but the risk register has not been updated, the project manager should immediately schedule a risk review session with the team. This allows for a prompt update to the risk register and ensures accurate information for the sponsor.

Signup and view all the flashcards

What should a project manager do when a client requests a new feature during project execution?

When a client requests a new feature during execution, the project manager should perform an impact analysis. They should present this analysis to the client, outlining the effects of the feature on schedule, budget, and scope, allowing for a informed decision and potential negotiation.

Signup and view all the flashcards

What should a project manager do when a marketing brochure project begins without defined quality criteria?

Before a project team begins work on a marketing brochure, the project manager must collaborate with stakeholders to define quality criteria. These criteria should be documented in the project plan, ensuring a shared understanding of the desired outcome and preventing potential misunderstandings later.

Signup and view all the flashcards

What should a project manager do when a team member consistently misses deadlines due to unclear instructions?

When a team member consistently misses deadlines due to unclear instructions, the project manager should provide clear instructions. Verification of understanding through regular check-ins and open communication helps address the root cause of the problem and ensures that everyone is on the same page.

Signup and view all the flashcards

What should a project manager do when experiencing scope creep due to undocumented client requests?

To regain control of scope creep due to undocumented client requests, the project manager should implement stricter controls on changes. They should update the change management process, ensuring a transparent and controlled system for additions or modifications to the project scope.

Signup and view all the flashcards

What should a project manager do when team members bypass the formal change management process?

When team members bypass the formal approval process for changes, the project manager should enforce the existing change management process. They should communicate itsimportance to the team and stress transparency and accountability. This ensures that stakeholders are aware of all changes and can provide valuable feedback.

Signup and view all the flashcards

What should a project manager do when a product owner insists on reprioritizing backlog items during a sprint review?

When a product owner insists on reprioritizing backlog items during a sprint review, the project manager should facilitate a backlog refinement session. This session allows for evaluation of the request's impact on the current sprint goals and the overall project timeline.

Signup and view all the flashcards

What should a project manager do when they find several tasks have been underestimated, putting the timeline at risk?

When task underestimation puts the project timeline at risk, the project manager should update the project schedule to reflect the revised estimates. They should then inform stakeholders about the changes and potential impact on the original timeline.

Signup and view all the flashcards

What should a project manager use to clarify roles and responsibilities during a political campaign project?

When team members express frustration due to unclear roles in a political campaign project, the project manager should use a Responsibility Assignment Matrix (RACI chart). This tool outlines responsibilities for each task, clarifying roles, and ensuring clear ownership.

Signup and view all the flashcards

What should a project manager do when team members are not updating the project management information system (PMIS) with task progress?

When team members aren't updating the project management information system (PMIS) with task progress, the project manager should enforce a policy requiring updates. They should communicate its importance to the team and ensure accurate information is captured for reporting and decision-making.

Signup and view all the flashcards

What should a project manager prioritize to avoid testing issues due to poor time management in future sprints?

When a sprint retrospective identifies testing issues due to poor time management, the project manager should prioritize improving sprint planning. This involves allocating adequate time for testing activities within each sprint, ensuring thorough testing and preventing future defects.

Signup and view all the flashcards

What should a project manager do when new government regulations mandate additional safety inspections, impacting the project schedule?

When new government regulations mandate additional safety inspections, impacting the schedule of an office building project, the project manager should update the project schedule. They should inform stakeholders of the regulatory changes and the impact on the project timeline.

Signup and view all the flashcards

What should a project manager do when risks identified during planning are not monitored, leading to issues during execution?

When risks identified during planning are not monitored, the project manager should update the risk register. They should implement a process to monitor risks regularly, proactively mitigating potential issues and keeping stakeholders informed.

Signup and view all the flashcards

How should a project manager address a team member who repeatedly fails to deliver on commitments in a self-organizing agile team?

When a team member in a self-organizing agile team repeatedly fails to deliver on commitments, the project manager should facilitate a team discussion. This allows for addressing the issue collaboratively and establishing accountability within the team.

Signup and view all the flashcards

What should a project manager do when stakeholders request updates on specific metrics not originally included in the performance measurement baseline?

When stakeholders request updates on metrics not included in the performance measurement baseline, the project manager should evaluate the feasibility of tracking the new metrics. They should update the performance baseline if needed, ensuring the project is measured against relevant data for informed decision-making.

Signup and view all the flashcards

What should a project manager do when a team discovers a new technology that could significantly improve the product but requires additional funding?

When a team discovers a new technology that could improve the product but requires additional funding, the project manager should present a business case to stakeholders. This case should demonstrate the benefits and costs of adopting the technology, enabling informed decision-making and securing support for the investment.

Signup and view all the flashcards

What should a project manager do when a client requests frequent reviews, but the project manager finds the updates redundant and time-consuming?

When a client requests frequent reviews but updates are redundant, the project manager should propose a more efficient update method. This could involve written summaries or online tools, seeking the client's agreement to a more productive communication strategy.

Signup and view all the flashcards

What should a project manager do when a team suggests relaxing quality standards to meet a deadline?

When a project team suggests relaxing quality standards to meet a deadline, the project manager should discuss the trade-off between quality and time with stakeholders. Prioritizing between the two is a joint decision based on project requirements and risk tolerance.

Signup and view all the flashcards

What should a project manager have done to avoid a stakeholder's dissatisfaction with project communication during the initiation phase?

When a key stakeholder is dissatisfied with the lack of communication during the project initiation phase, the project manager should have developed a stakeholder engagement plan. This plan should ensure the appropriate involvement of all stakeholders, including regular communication and information sharing.

Signup and view all the flashcards

What should a project manager do to prevent missing milestones due to unanticipated dependencies?

To prevent missing milestones due to unanticipated dependencies, the project manager should develop a more detailed project schedule. This schedule should identify dependencies and critical paths, ensuring a comprehensive understanding of task interactions and potential risks.

Signup and view all the flashcards

What should a project manager do when a project does not align with strategic business objectives?

When it is discovered that a project does not align with strategic business objectives, the project manager should recommend terminating the project to the portfolio manager. They should also reallocate resources to strategic initiatives that align with the organization's goals.

Signup and view all the flashcards

What should a project manager have done to avoid a client's dissatisfaction with a marketing brochure due to poor alignment with their brand?

To avoid a client's dissatisfaction with a marketing brochure due to poor alignment with their brand, the project manager should have conducted regular reviews with the client. This ensures that the project is aligned with the brand's vision, preventing misinterpretations and ensuring the desired outcome.

Signup and view all the flashcards

What should a project manager do when a key vendor informs the project manager about delays in the delivery of critical materials?

When a key vendor informs the project manager of delays in the delivery of critical materials, the project manager should review the risk register and activate the contingency plan for procurement delays. This ensures that alternative solutions are in place to mitigate the impact of the delay and maintain the project's momentum.

Signup and view all the flashcards

What tool should a project manager use to clarify roles and responsibilities in a political campaign project?

To address conflicting task assignments during a political campaign project, the project manager should use a responsibility assignment matrix (RACI chart). This tool outlines roles and responsibilities for each task, ensuring clarity and preventing duplication of effort.

Signup and view all the flashcards

What should a project manager do when team members are not updating the project management information system (PMIS) with task progress?

When team members aren’t updating the PMIS, the project manager should enforce a policy requiring task updates. They should communicate its importance and the benefits of using the PMIS for effective tracking, reporting, and decision-making.

Signup and view all the flashcards

Study Notes

Project Management Scenarios

  • Budget Overruns and Schedule Delays: A senior stakeholder requested new project features, leading to budget overruns and schedule delays.

    • The project manager should have informed the stakeholder that the features could be included in a follow-up project.
    • Revising the project plan and gaining stakeholder approval before implementing changes would prevent this.
  • Incomplete Tasks in Agile: A project team using agile is experiencing issues with incomplete tasks, due to a team member misunderstanding priorities.

    • The project manager should assign a mentor to the team member to provide guidance.
    • Conduct a retrospective to review task prioritization and communication processes.
  • Inconsistent Status Reports: The client demands a status report, but team members provided inconsistent updates on task completion.

    • The project manager should conduct a sprint review to validate task completion and align status reports.
  • Differing Stakeholder Definitions of Success: Stakeholders have differing definitions for "project success".

    • The best action to resolve this is to facilitate a session to align stakeholders on success criteria and update the project charter.
  • Client Requests Frequent Updates: A client requests frequent updates, availability is limited, and the project manager feels this is slowing progress

    • The project manager should revise the communication management plan to include asynchronous updates and feedback options.
  • Significant Defect Identified in Prototype: A significant defect was found in a prototype during a client demonstration.

    • The project manager should accept responsibility, analyze the defect, and propose a corrective action plan.
  • Critical Resource Assigned to Another Project: A critical resource was assigned to another project, jeopardizing the project timeline.

    • Escalate the issue to senior management for resource reallocation.
  • Stakeholder Questions Alignment of Deliverables: A stakeholder questions the alignment of deliverables with organizational strategy mid-project.

    • The project manager should conduct a review of project objectives, deliverables, and strategy alignment with all stakeholders.
  • Client Dissatisfied with Agile Project Pace: A client is dissatisfied with the pace of progress in an agile project and demands weekly deliverables.

    • The project manager should negotiate with the client to agree on realistic delivery timelines.
  • Budget Reduction During Project Execution: A project sponsor requests a significant budget reduction while maintaining scope and timeline.

    • The project manager should use value engineering to reduce costs while maintaining essential deliverables.
  • Team Struggles with Agile Framework: Team members struggle with collaboration and communication during the first sprint of transitioning to an agile framework.

    • Conduct a team workshop to discuss agile principles and improve communication processes.
  • External Conditions Affecting Project: External conditions, such as new election regulations, impact a political campaign project.

    • The project manager should update the risk register and initiate a change request.
  • Vendor Failure to Meet Contractual Obligations: A vendor fails to meet their contractual obligations delaying project deliverables.

    • The project manager should refer to the contract, enforce penalties, and activate the contingency plan.
  • Unclear Definition of "Done": Team members complain about incomplete features in a sprint review citing unclear instructions.

    • The project manager and stakeholders should collaborate to define a clear "definition of done".
  • Team Disagrees on Priorities: Team members frequently disagree on priorities in a complex project.

    • Facilitate a stakeholder workshop to align on objectives and priorities.
  • Quality Issues: Team misses deadlines because of unclear instructions

    • Provide clear instructions and verify understanding through regular check-ins.
  • Scope Creep: Team experiences scope creep due to undocumented client requests

    • Implement stricter controls on changes and update the change management process.
  • Bypassing Formal Approval Process: Team members bypass formal approval processes for changes to accelerate work

    • Enforce the existing change management process and communicate its importance to the team
  • Unforeseen DependenciesTeam frequently misses milestones due to unanticipated dependencies

    • Develop a detailed project schedule, identifying dependencies and critical paths.
  • Risk Monitoring: Project manager discovers that risks identified during planning phase were not monitored

    • Update the risk register and implement a process to regularly monitor risks.
  • Stakeholder Communication: A key stakeholder requests to have more involvement.

    • Update the stakeholder engagement plan to reflect the new levels of involvement and explain that to the stakeholder.
  • Client Requests Additional Features that are Outside the Budget: A client wants more features that exceed the budget.

    • Use a cost benefit analysis to present the options to the client.
  • Quality Criteria Undefined:The team did not define quality criteria for the final deliverable.

    • The team should collaborate with stakeholders to define quality criteria and document these in the project plan.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

Module 1 - ChatGBT.docx PDF

Description

Test your knowledge on common project management scenarios. This quiz covers challenges such as budget overruns, incomplete tasks in Agile, and inconsistent status reports. Evaluate your understanding of best practices and solutions for effective project management.