FPM WEEK 2 - Scenarios
50 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

A project team is tasked with selecting a project to align with the organization's strategic goals. After collecting several options, stakeholders are struggling to prioritize. What is the most effective approach?

  • Perform a SWOT analysis to evaluate each project.
  • Choose the project that aligns with the highest revenue potential.
  • Use weighted scoring to objectively evaluate criteria. (correct)
  • Select the project with the shortest timeline.
  • A business case identifies a critical opportunity to implement a new quality improvement system. During project selection, the organization is unsure if resources will be sufficient. What should the team focus on during resource allocation?

  • Allocating resources equally across all potential projects.
  • Selecting another project to avoid risks.
  • Prioritizing the quality improvement project based on financial measures.
  • Aligning resource allocation with the strategic objectives and capacity. (correct)
  • An organization is considering two projects: one with a higher ROI but longer payback period and another with lower ROI but immediate payback. What should the project selection decision prioritize?

  • Selecting the project with the lowest initial cost.
  • Conducting a sensitivity analysis to identify risks.
  • The project with the higher ROI for long-term benefits. (correct)
  • The project with immediate payback for quicker returns.
  • A virtual conference project is under consideration. The weighted scoring method shows the "pre-recorded" option scoring higher, but the NPV of the "live streaming" option is better. What should the team do next?

    <p>Perform a decision tree analysis to evaluate risks and EMV.</p> Signup and view all the answers

    A team uses SWOT analysis to evaluate a project. They identify strong internal capabilities but significant external threats. How should the team address this during project initiation?

    <p>Develop a risk mitigation plan to address external threats.</p> Signup and view all the answers

    During a project kickoff meeting, a stakeholder argues that project objectives are unclear. What document should the project manager present to clarify the objectives?

    <p>The project charter.</p> Signup and view all the answers

    A project's business case outlines benefits that will be realized over four years. However, the payback period is longer than the organization's acceptable threshold. What should the project manager do?

    <p>Perform a sensitivity analysis to explore reducing initial costs.</p> Signup and view all the answers

    A stakeholder suggests including a feature in a project that will improve customer satisfaction but requires additional funding. The project manager identifies this as a possible constraint. What is the best course of action?

    <p>Update the project charter to reflect the new constraint and seek approval.</p> Signup and view all the answers

    A project manager is tasked with creating a benefits management plan. One of the stakeholders argues that benefits realization should not be monitored after project closure. How should the project manager respond?

    <p>Explain that benefits realization often extends beyond project closure and must be monitored.</p> Signup and view all the answers

    A project charter lists a constraint that bandwidth issues may affect the virtual conference platform. During planning, the team identifies new tools that could mitigate this constraint. What should the project manager do?

    <p>Update the risk register with the mitigation plan.</p> Signup and view all the answers

    A product roadmap outlines high-level goals but lacks specific features or timelines. How should the project manager proceed to ensure alignment with strategic objectives?

    <p>Break down goals into detailed features and prioritize them with stakeholders.</p> Signup and view all the answers

    The organization is hesitant to approve a project charter because the development approach is unclear. What should the project manager do?

    <p>Propose a hybrid approach and document it in the project charter.</p> Signup and view all the answers

    A project manager is using a decision tree to evaluate two project options. One project has higher monetary outcomes but significant risks, while the other has lower outcomes but minimal risks. How should the project manager proceed?

    <p>Use expected monetary value (EMV) analysis to quantify the risks and make an informed decision.</p> Signup and view all the answers

    During project selection, one initiative has a positive NPV but a payback period exceeding the acceptable threshold. What should the project team prioritize in their analysis?

    <p>Conduct a weighted scoring analysis to incorporate additional criteria.</p> Signup and view all the answers

    The product vision for a new website project includes reaching a global audience. During the product roadmap phase, the team identifies limited resources for translation services. How should the project manager address this?

    <p>Include resource constraints in the roadmap and prioritize translation services.</p> Signup and view all the answers

    A project charter specifies a tight schedule for delivering a virtual conference platform. During execution, the team realizes the constraints are impacting quality. What should the project manager do?

    <p>Communicate the trade-offs to stakeholders and seek guidance on priorities.</p> Signup and view all the answers

    A project kickoff meeting reveals that stakeholders have conflicting expectations about project deliverables. What should the project manager do?

    <p>Revisit the project charter to align stakeholder expectations.</p> Signup and view all the answers

    A benefits management plan identifies metrics for measuring success but lacks specific timeframes. What should the project manager do to strengthen the plan?

    <p>Use historical data to estimate timeframes for realizing benefits.</p> Signup and view all the answers

    A project manager uses a weighted scoring model to evaluate two options for a project. One option scores higher on member benefits but lower on risk. What should the project manager prioritize in the final decision?

    <p>Select the option with the higher overall score.</p> Signup and view all the answers

    A project sponsor requests an ROI calculation for a proposed project. The team has calculated total discounted benefits and costs. What should the project manager do next?

    <p>Use the ROI formula to calculate the return percentage.</p> Signup and view all the answers

    A stakeholder argues that including a specific milestone in the project charter is unnecessary. What is the project manager's best course of action?

    <p>Keep the milestone and explain its importance in tracking progress.</p> Signup and view all the answers

    During project initiation, a stakeholder identifies a constraint that may limit the team's ability to meet the budget. What document should the project manager update to reflect this?

    <p>The project charter.</p> Signup and view all the answers

    A team is developing a virtual conference platform but discovers potential bandwidth issues during project initiation. How should the project manager address this?

    <p>Document the issue as a risk and develop a mitigation strategy.</p> Signup and view all the answers

    A project manager is tasked with justifying an initiative to senior management. What document should they develop to provide a high-level overview of the project's objectives and potential benefits?

    <p>A business case.</p> Signup and view all the answers

    A decision tree analysis shows that a pre-recorded conference option has a lower expected monetary value than a live streaming option. What should the team do?

    <p>Recommend the live streaming option based on the higher EMV.</p> Signup and view all the answers

    A project manager is creating a product roadmap for a new website. The team has identified multiple business goals, but there are disagreements on prioritization. What should the project manager do?

    <p>Conduct a workshop with stakeholders to align on prioritization criteria.</p> Signup and view all the answers

    During the payback analysis of a virtual conference project, the team finds the cumulative benefits exceed costs in year three. What is the payback period?

    <p>Three years.</p> Signup and view all the answers

    The product vision for a project includes leveraging a new platform to enhance global reach. During initiation, the project manager identifies risks in adopting this technology. What should they do?

    <p>Document the risks in the risk register and propose mitigation strategies.</p> Signup and view all the answers

    A stakeholder expresses concern that the project charter does not sufficiently address resource constraints. How should the project manager respond?

    <p>Add resource constraints to the assumptions and constraints section of the project charter.</p> Signup and view all the answers

    During project initiation, a team is asked to justify why the project aligns with the organization's strategic objectives. Which document should they prepare?

    <p>A business case.</p> Signup and view all the answers

    A project charter specifies milestones and success criteria, but the development approach is unclear. What should the project manager do?

    <p>Propose an adaptive approach and gain stakeholder approval.</p> Signup and view all the answers

    The organization has identified several potential projects. One project has a positive ROI but lower benefits compared to others. How should the project manager justify this project?

    <p>Emphasize the positive ROI during selection discussions.</p> Signup and view all the answers

    A project team is using weighted scoring to select between two options. The higher-scoring option has a higher risk. How should the project manager address this?

    <p>Use sensitivity analysis to understand the impact of the risk on overall outcomes.</p> Signup and view all the answers

    During project selection, stakeholders argue over whether financial measures or customer benefits should take priority. What should the project manager do?

    <p>Create a weighted scoring model that includes both criteria.</p> Signup and view all the answers

    A virtual conference project has two options: live streaming and pre-recorded sessions. The pre-recorded option has a longer payback period. What should the project team do?

    <p>Perform a comprehensive NPV analysis to evaluate long-term benefits.</p> Signup and view all the answers

    During project initiation, the team identifies several assumptions in the project charter. What should the project manager do to ensure these assumptions are managed?

    <p>Document the assumptions in the assumption log and regularly validate them.</p> Signup and view all the answers

    A project charter specifies a critical milestone of completing technology selection by a specific date. During execution, the team realizes they need more time. What should the project manager do?

    <p>Conduct an impact analysis and propose a revised milestone.</p> Signup and view all the answers

    The project sponsor wants a virtual conference to have a low-cost solution. However, the team finds that the low-cost option may not meet quality standards. What should the project manager do?

    <p>Present a cost-benefit analysis comparing quality and cost options.</p> Signup and view all the answers

    During project charter approval, the client requests additional success criteria not initially agreed upon. What should the project manager do?

    <p>Incorporate the success criteria and seek updated approval.</p> Signup and view all the answers

    A project manager is tasked with preparing a kickoff meeting for a predictive project. What is the primary objective of this meeting?

    <p>To review the project charter, introduce roles, and align on objectives.</p> Signup and view all the answers

    The team has proposed a hybrid development approach for a website project. What is the primary advantage of using a hybrid approach?

    <p>Increased flexibility and adaptation to project requirements.</p> Signup and view all the answers

    A project manager is tasked with justifying a project with an NPV of $5,000 and a payback period of three years. Stakeholders are concerned the financial returns are low. What should the project manager emphasize?

    <p>The project's alignment with strategic objectives and additional non-financial benefits.</p> Signup and view all the answers

    During a decision tree analysis for two project options, a stakeholder questions the probabilities assigned to outcomes. What should the project manager do?

    <p>Conduct sensitivity analysis to evaluate the impact of changes in probabilities.</p> Signup and view all the answers

    A project brief for an adaptive project specifies acceptance criteria but lacks clear benefits. What should the project manager do?

    <p>Include specific and measurable benefits in the project brief.</p> Signup and view all the answers

    A product roadmap prioritizes a registration feature for a website project. During development, a team member suggests prioritizing the promotion page instead. What should the project manager do?

    <p>Discuss the proposed change with stakeholders and update the roadmap if needed.</p> Signup and view all the answers

    A stakeholder is concerned that the project charter lacks detailed timelines for execution. What is the project manager's best response?

    <p>Explain that detailed timelines will be part of the project schedule, not the charter.</p> Signup and view all the answers

    A project charter for a virtual conference lists “high attendee satisfaction” as a success criterion. During execution, the team struggles to define metrics for satisfaction. What should the project manager do?

    <p>Develop measurable metrics for attendee satisfaction and communicate them to the team.</p> Signup and view all the answers

    During the product vision phase, a stakeholder argues that the vision is too broad and lacks focus. What should the project manager do?

    <p>Collaborate with stakeholders to refine the vision into a more specific and achievable goal.</p> Signup and view all the answers

    A project manager uses ROI to justify a project, but stakeholders prioritize shorter payback periods. What is the best way to address this during the selection process?

    <p>Highlight other financial metrics, such as NPV, to provide a comprehensive analysis.</p> Signup and view all the answers

    During a kickoff meeting, team members express confusion about their roles. What should the project manager provide to resolve this?

    <p>A responsibility assignment matrix (RACI chart).</p> Signup and view all the answers

    Study Notes

    Project Management

    • Effective project selection prioritization involves using weighted scoring methods for objective evaluation of project criteria.
    • Aligning resource allocation with strategic objectives and capacity is crucial for project success.
    • Prioritizing a project with a higher ROI despite a longer payback period is often a better long-term strategy than selecting a project with a quick payback but lower ROI.
    • Decision making regarding a project should account for both the higher weighted score of a project and the better financial value of another project. The best approach may be the application of decision tree analysis to evaluate both risks and expected monetary value.
    • Addressing external threats as part of project initiation is critical to successful project management. Developing a risk mitigation plan is essential.
    • Using the project charter as the primary document clarifying project objectives is essential during a project kickoff meeting.
    • Performing sensitivity analysis when a project’s payback period exceeds acceptable thresholds is a key part of project management.
    • Stakeholder needs and constraints surrounding project features and funding should be factored into project constraints, which should be reflected in a project charter or similar documents.
    • Benefits that may occur outside the project timeframe should be monitored following project closure.
    • Project charters should account for bandwidth constraints when planning project implementations.
    • Product roadmaps should explicitly consider resource limitations and prioritize translation services for international projects.
    • Project managers should address discrepancies in stakeholders’ expectations to avoid delays.
    • Timeframes for realized benefits should be included in benefits management plans.
    • Using weighted scoring models, project managers should evaluate projects by considering both the higher scores and risks.
    • Conducting sensitivity analysis to explore risk-related impacts can enhance decision making process.
    • A project team should present total discounted benefits and costs when responding to a project sponsor seeking an ROI calculation.
    • Ensure a stakeholder’s concerns regarding the sufficiency of milestone inclusion are addressed. This can be reflected by adding specifics to the project charter.
    • Managing project assumptions is critical for ensuring that project plans efficiently reflect operational needs.
    • Project managers should document and regularly validate project assumptions.
    • Addressing project milestones and deadlines should be carried out during project execution, not initiation. This requires updating milestones, if necessary or creating impact analyses to reassess project objectives as needed.
    • Stakeholders should be involved to identify potential solutions to any concerns or disagreements. Project managers should accommodate stakeholders' concerns to minimize potential project delays.
    • Project initiation should account for all identified risks and address them appropriately; potential solutions should be documented.
    • Project managers can appropriately align stakeholders' expectations by creating a clear project plan.
    • The payback period of a project will depend on when financial benefits meet costs incurred, so the project manager should use detailed data to calculate the payback period.
    • Stakeholder concerns should be addressed through proactive communication, with a focus on addressing concerns rather than delaying or excluding feedback.
    • Project charters are used to justify initiatives by presenting project objectives and benefits.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Module 2 - ChatGBT PDF

    Description

    This quiz explores essential concepts in project management, including effective project selection, resource allocation, and decision-making strategies. It emphasizes the importance of aligning projects with strategic objectives and developing risk mitigation plans. Gain a deeper understanding of tools like weighted scoring methods and decision tree analysis to enhance your project management skills.

    More Like This

    Project Selection and Evaluation Quiz
    5 questions
    Project Selection Techniques
    16 questions
    Project Selection Methods Quiz
    34 questions
    Use Quizgecko on...
    Browser
    Browser