Project Management Chapter 6

BoundlessDeStijl avatar
BoundlessDeStijl
·
·
Download

Start Quiz

Study Flashcards

Questions and Answers

What is the Project Network defined as?

A flow chart showing project activities, their sequences, interdependencies, and timelines

Define Critical Path.

The Critical Path is the path with the longest duration through the network and determines the shortest possible project completion time.

Total Slack is the difference between __ and __.

LS and ES (Late Start and Early Start)

Conditional statements are allowed in developing project networks.

<p>False</p> Signup and view all the answers

Study Notes

Developing a Project Schedule

  • A project network is a graphic flow chart that depicts project activities, their logical sequences, and interdependencies, and provides the basis for scheduling labor and equipment, enhancing communication among project stakeholders.
  • It estimates project duration, provides the basis for budgeting cash flow, identifies critical activities, and helps managers get and stay on the project plan.

The Project Network Defined

  • A project network is a graphic representation of project activities, their sequences, and interdependencies.
  • It provides the basis for scheduling labor and equipment, enhances communication among project stakeholders, and estimates project duration.

Terminology

  • Activity: an element of the project that requires time but may not require resources.
  • Parallel activities: activities that can take place at the same time, if desired.
  • Burst activity: an activity that has more than one activity immediately following it.
  • Merge activity: an activity that has more than one activity immediately preceding it.
  • Path: a sequence of connected, dependent activities.
  • Critical path: the path with the longest duration through the network.

Basic Rules to Follow in Developing Project Networks

  • Networks flow typically from left to right.
  • An activity cannot begin until all preceding connected activities have been completed.
  • Arrows on networks indicate precedent and flow and can cross over each other.
  • Each activity should have a unique identification number.
  • An activity identification number must be greater than that of any activities that precede it.
  • Looping is not allowed.
  • Conditional statements are not allowed.
  • Where there are multiple starts, a common start node can be used to indicate a clear project beginning on the network.
  • Similarly, a single project end node can be used to indicate a clear ending.

Network Computation Process

  • Forward Pass: calculates early start and finish times for each activity.
  • Backward Pass: calculates late start and finish times for each activity.
  • Earliest times: how soon can the activity start (ES) and finish (EF).
  • Latest times: how late can the activity start (LS) and finish (LF).
  • Critical path: the longest path through the network, which determines the project duration.

Network Information

  • Early start (ES) and finish (EF) times are calculated using the forward pass.
  • Late start (LS) and finish (LF) times are calculated using the backward pass.
  • Critical path is determined by finding the path with the least slack.
  • Slack (or float) times: the amount of time an activity can be delayed without affecting the project end date.

Determining Slack (or Float) Times

  • Total slack: the amount of time an activity can be delayed without affecting the project end date.
  • Free slack: the amount of time an activity can be delayed without affecting any immediately following activity.

The Critical Path

  • The critical path is the network path(s) that has the least slack in common.
  • It is the longest path through the activity network, which determines the project duration.
  • It is important because it impacts the project completion time.
  • Activities on the critical path should be prioritized and closely monitored.

Sensitivity

  • Network sensitivity is the likelihood the original critical path(s) will change once the project is initiated.
  • A network schedule that has only one critical path and noncritical activities that enjoy significant slack would be labeled ‘insensitive’.

Practical Considerations

  • Network logic errors, such as illogical loops, can occur.
  • Activity numbering should be unique and consecutive.
  • Computers can be used to develop networks and create Gantt charts.
  • Calendar dates should be considered when developing project schedules.
  • Multiple starts and multiple projects can be accommodated using network techniques.

Extended Network Techniques

  • Laddering: breaking down activities into segments to reduce project duration.
  • Lags: the minimum amount of time a dependent activity must be delayed to begin or end.
  • Hammock activity: spans over a segment of a project and has a duration determined after the network plan is drawn.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

More Quizzes Like This

Use Quizgecko on...
Browser
Browser