What is developed first to create a detailed schedule for complex projects?

  • Work Breakdown Structure (WBS) (correct)
  • Project Plan
  • Project Logic Diagram
  • Activity Duration Estimation
  • What is the primary document used to develop the Work Breakdown Structure (WBS)?

  • Project Schedule
  • Project Charter
  • Project Scope (correct)
  • Project Budget
  • What is the purpose of sequencing activities in the planning process?

  • To identify project risks
  • To estimate activity duration
  • To develop a project schedule (correct)
  • To allocate resources
  • What is represented by the project logic diagram?

    <p>The logical sequence of activities</p> Signup and view all the answers

    What is the critical path in a project?

    <p>The longest path to complete the project</p> Signup and view all the answers

    What occurs when the client's project completion date precedes the calculated critical path end date?

    <p>The project has a negative float</p> Signup and view all the answers

    What is the purpose of estimating activity duration?

    <p>To develop a project schedule</p> Signup and view all the answers

    What is a milestone schedule used for?

    <p>Tracking progress in less complex projects</p> Signup and view all the answers

    What is the project scope used for?

    <p>To develop the Work Breakdown Structure (WBS)</p> Signup and view all the answers

    What is the result of the planning process in project management?

    <p>A project schedule</p> Signup and view all the answers