Project Delivery Methods in Construction
19 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the first phase of the architect's project life cycle in a traditional design-bid-build project?

  • Design development
  • Schematic design
  • Pre-design (correct)
  • Construction documents
  • Which project delivery method includes a construction management approach with multiple tendering phases?

  • Design-bid-build
  • Construction management (correct)
  • Design-build
  • Integrated project delivery
  • In the design-bid-build project delivery method, who administers the construction contract?

  • The owner
  • The architect (correct)
  • Engineering consultants
  • The constructor
  • In an integrated project delivery method, how do the project life cycles differ compared to design-bid-build?

    <p>They have different stakeholders' relationships</p> Signup and view all the answers

    What typically marks the end of the constructor's project life cycle?

    <p>Warranty period</p> Signup and view all the answers

    What has prompted the evolution of project delivery methods in the construction industry?

    <p>Economic pressures and increased owner requirements.</p> Signup and view all the answers

    What does the term 'design-construction project delivery' encompass?

    <p>The integration of design activities and construction processes.</p> Signup and view all the answers

    Which of the following is NOT a characteristic of modern project delivery methods?

    <p>Adversarial relationships among project teams.</p> Signup and view all the answers

    Which innovation has significantly influenced project delivery methods in recent years?

    <p>Building Information Modeling (BIM).</p> Signup and view all the answers

    Who is legally allowed to undertake the practice of architecture in project delivery?

    <p>An architect, with some noted exemptions.</p> Signup and view all the answers

    What is the primary feature of CCDC 5B in construction management?

    <p>Combines fee for construction management services with a guaranteed price for construction work.</p> Signup and view all the answers

    What role does a construction manager typically assume once bid packages are received?

    <p>They provide financial assurances and assume liability.</p> Signup and view all the answers

    Which of the following responsibilities is NOT typical for a construction manager?

    <p>Managing the marketing strategy for client acquisition.</p> Signup and view all the answers

    Which aspect typically influences architects and engineers in declining to provide construction management services?

    <p>Lack of expertise and appropriate insurance.</p> Signup and view all the answers

    In construction management, what does GMP stand for?

    <p>Guaranteed Maximum Price.</p> Signup and view all the answers

    What is a key difference between CCDC 5A and CCDC 5B?

    <p>CCDC 5B combines fee for management services with guaranteed pricing.</p> Signup and view all the answers

    Which of the following is NOT a responsibility of a construction manager?

    <p>Building design and drafting.</p> Signup and view all the answers

    What is the role of the Canadian Construction Association with regards to construction management?

    <p>It offers resources and guidelines for construction management contracts.</p> Signup and view all the answers

    What does CCDC stand for in construction management contracts?

    <p>Construction Contract Documentation Committee.</p> Signup and view all the answers

    Study Notes

    Project delivery methods

    • The construction industry has evolved to include multiple project delivery options.
    • Project delivery methods have adapted to increased owner requirements, risk transfer, shorter timeframes, and demands for higher performance.
    • The traditional term "construction project delivery" is being replaced with "design-construction project delivery" due to the increasing integration of design and construction activities.
    • Building Information Modeling (BIM) and integrated project delivery (IPD) have led to significant innovation in project delivery methods.
    • Design activities undertaken by a team as part of the design-construction process are the protected scope of work of architects.

    Design-Bid-Build

    • This is a traditional project delivery where the owner engages an architect to design the project, followed by procuring a contractor through competitive bidding under a stipulated price construction contract.
    • The architect administers the construction contract, reviews construction works, certifies payments, and has responsibilities at project completion and during the warranty period.
    • CCDC 2 is commonly used for stipulated price construction contracts.

    Construction Management

    • A construction manager assists in planning, provides cost estimates, manages the project schedule, and coordinates trades.
    • Construction management can offer improved constructability, reduced rework, and enhanced transparency, leading to higher efficiency and effectiveness.

    Integrated Project Delivery (IPD)

    • IPD utilizes a collaborative approach where teams work together from the beginning, sharing risks and rewards.
    • The goal is to achieve higher-quality outcomes and reduce adversarial relationships.
    • Requires strong communication and a shift from a competitive to a collaborative culture.
    • CCDC 30 is the Canadian standard form of agreement for integrated project delivery.

    Project Management

    • A project manager oversees the entire project, engaging all disciplines, including architects, engineers, and contractors.
    • The project manager may employ a traditional design-bid-build approach or utilize sequential tendering to achieve earlier completion.
    • Project management can offer risk transfer from the owner to the project management firm and provide constructability input during design.

    Just-in-Time

    • This method breaks down large projects into smaller work packages that are planned, demolished, and constructed on an hourly basis, emphasizing schedule optimization.

    Turnkey Development

    • This method encompasses various real estate functions, including site acquisition, entitlements, construction, financing, and long-term management.
    • It can be carried out under design-build or developer proposal methods.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Explore the various project delivery methods in the construction industry, including traditional and innovative approaches. Learn how project delivery has evolved to meet owner requirements and the integration of design and construction through Building Information Modeling (BIM).