POI and POP in Telecommunication Networks

FreshestCornet avatar
FreshestCornet
·
·
Download

Start Quiz

Study Flashcards

30 Questions

What should be the timeframe for commissioning the POI after the interconnection seeker submits the application?

30 days

How often should traffic measurements be taken for augmentation of junctions at POI?

Quarterly

What should be considered while calculating the number of junctions for augmentation, according to the text?

Route busy hour traffic printouts

When was the Regulation issued by TRAI implemented?

01.02.2004

How should the number of E1s be adjusted according to the text?

Regularly reviewed based on traffic requirements

What is the role of BSNL and private operators in determining the number of junctions for augmentation?

Take traffic measurements during agreed route busy hour

What does a Point of Presence (POP) involve?

Setting up switching and transmission centers at the service area level

What is the function of a Point of Interconnection (POI)?

To interconnect the GMSC of fully mobile network and a local exchange of BSNL

Who is responsible for handling applications for Point of Interconnection (POI)?

Circle office as a nodal point

What is the key requirement for issuing an advice note to an interconnection seeker?

Payment as per the demand note for E1s and infrastructure requirements

Why is it important for the nodal officer to review pending feasibility reports regularly?

To ensure that the response to interconnection seekers is timely

What is the recommended time limit for completing the infrastructure and necessary power requirements after the advice note is issued?

3-5 days

Which entity should expedite the process of feasibility report according to the text?

SSA Heads

What type of database should circle offices maintain regarding the E1 ports capacity available in switches designated for POI?

Database of spare capacity of E1 ports

Why is it suggested to designate a tandem exchange in each SDCC in advance for providing connectivity to NLDOs/ BSOs?

To help BSOs/NLDOs plan their transmission links

What should be nominated in advance to potentially save time according to the text?

Representatives for SSA testing team

Who should be part of the testing team for each SSA as per the text?

Representatives from SSA and Inspection(T&D) Circle

What should Inspection(T&D) Circle do, according to the text, regarding the testing team for each SSA?

Work out necessary arrangements in advance

What is the maximum timeframe within which POI should be commissioned with live traffic after payment by the interconnection seeker?

12 months

In case it is not immediately feasible to provide ports, what action should be taken by the interconnection seeker?

Be informed in writing with an expected time frame of feasibility

What is one of the main reasons for delays in commissioning of POIs as complained by BSOs, NLDOs, and ILDOs?

Delay in nomination of a local exchange as SDCC tandem

What does the text suggest SSA Heads should do to speed up the process of feasibility report?

Speed up the process of feasibility report

What should be done if other party agrees with the delay in provision of infrastructure and power after payment of demand note?

Inform the interconnection seeker in writing with expected timeframe for provision

What role does the circle office play in handling applications for POI?

Handles applications and issues demand note/advice note

What is the consequence of minor pending points that do not affect the quality of service, measurements, and integrity of the network?

Delay in the flow of commercial traffic

What is the timeframe within which private operators are expected to clear pending points as per the text?

15 days

What is the upper limit for commissioning the POI, as mentioned in the Interconnection Agreement?

30 days

What activity involves the submission of an application by a Private Operator to the CGM Office?

Activity 1

What is expected to happen after the Private Operator pays the demand note in Activity 4?

Issue of an advice note & availability of infrastructure

What should occur when there are no pending points in the A/T report as per the text?

Prompt clearance of commercial traffic

Study Notes

Point of Interconnection (POI)

  • The POI is the point at which the GMSC of a fully mobile network and the gateway switch of BSNL or local/tandem/TAX exchange of the basic service network are interconnected.
  • The POI should be commissioned within 30 days from the date of application submission, excluding time taken by the interconnection seeker for completing concerned activities.

Augmentation of POI

  • Traffic measurements are taken by BSNL and private operators during the agreed route busy hour for seven days on a quarterly basis.
  • The number of junctions is calculated as per Erlang Table for the Grade of Service (0.005) as per the interconnection agreement, including 25% additional junctions for future traffic requirements.
  • The POI capacity should be reviewed regularly, and the number of E1s may be reduced if not justified as per traffic requirement.

Provisioning of POI

  • The Circle office handles applications submitted by various operators for POI and issues demand notes/advice notes.
  • The SSA Heads should speed up the process of feasibility reports, and the nodal officer for POI should review pending feasibility reports regularly.
  • Once payment is made, the advice note should be issued immediately, and POI should be commissioned with live traffic within 12 months.

Reasons for Delay in POI Provisioning

  • Delay in issuing demand notes due to non-receipt of feasibility reports from SSAs.
  • Delay in nomination/declaration of a local exchange as SDCC tandem for providing connectivity to NLDOs/BSOs.
  • Delay in provision of infrastructure and power after payment of demand note.
  • Delay in constitution of a testing team or nomination of a representative on behalf of BSNL for acceptance testing.

Approval of A/T Report by Circle Office

  • The Circle office should maintain a database of spare capacity of E1 ports available in switches designated for POI.
  • Efforts should be made to observe a time limit of 3-5 days for completing infrastructure and necessary power requirements.
  • A tandem exchange should be designated in each SDCC well in advance for providing connectivity to NLDOs/BSOs.
  • The testing team for each SSA should be nominated in advance to save time.

Learn about the Point of Interconnection (POI) and Point of Presence (POP) in telecommunication networks. Understand how different networks are interconnected and the standards applicable at these points.