PERT / CPM Quiz

SuccessfulTuba avatar
SuccessfulTuba
·
·
Download

Start Quiz

Study Flashcards

17 Questions

Slack = ___

0

Critical Activity ___ PATH

CRITICAL

PERT | TIME ___ OPTIMISTIC TIME PESSIMISTIC TIME MOST PROBABLE TIME

VARIABILITY

Time it takes for an activity to be completed considering very minimal problems and ___

delays

ACTIVITY 1.Create a ___ Network

PERT

______ is an acronym for Program Evaluation Review Technique / Critical Path Method.

PERT / CPM

______ stands for Program Evaluation and Review Technique, where a network of nodes and arrows determine the critical activities, improve the schedule, if necessary, and review progress once the project is undertaken. ______ was developed in the late 1950’s by the U.S. Navy Polaris Nuclear Submarine Project by Booz, Allen, and Hamilton with 250 prime contractors and 4000 subcontractors with approximately 300,000 tasks and with a development time of two (2) years.

PERT

PERT involves the following steps: 1.Breaking down the project into specific activities or tasks. 2.Estimating the time required to complete each activity. 3.Identifying the precedence relationships between activities. 4._______ the critical path and slack times for each activity.

Calculating

An ______ is a job to be completed as a part of the project, signified by a branch in a PERT network.

Activity

The completion of all activities leading into a node in a PERT network is called an ______.

Event

A circle in a PERT network indicating the completion of certain activities and the initiation of others is known as a ______.

Node

A sequence of activities that determines a longest path through the network which yields the minimum time in which an entire project can be completed is known as the Critical ________

Path

______ Activity: An imaginary activity that requires no time.

Dummy

Earliest Start (ES): The earliest time an activity can be started after the completion of its ________.

Predecessor

Line connecting crucial events, any of which, if delayed, affects subsequent events, and ultimately, the completion of the project is called the ________ Path.

Critical

Network Diagram: A graphical method of representing a project with nodes and ________.

Arcs

Activity List: A list of jobs in a project with their immediate predecessors, expected times, and ________ required.

Resources

Study Notes

PERT/CPM Overview

  • PERT/CPM stands for Program Evaluation Review Technique/Critical Path Method
  • It is a method for scheduling and controlling projects
  • Developed in the 1950s, with PERT being used in the US Navy's Polaris Nuclear Submarine Project

PERT Network

  • A network of nodes and arrows that determine the critical activities
  • Determines the critical path and slack times for each activity
  • Consists of nodes, branches, and arcs

Key Terms

  • Activity: a job to be completed as part of the project, signified by a branch in a PERT network
  • Event: the completion of all activities leading into a node in a PERT network
  • Node: a circle in a PERT network indicating the completion of certain activities and the initiation of others
  • Branch: a line in a PERT network indicating an activity
  • Path: a sequence of activities leading from one node to another
  • Critical Path: a sequence of activities that determines the longest path through the network, yielding the minimum time in which an entire project can be completed

Key Concepts

  • Slack: the amount of time an activity can be delayed without affecting the overall project timeline
  • Expected Time (ET): calculated as (a + 4m + b) / 6, where a is the optimistic time, m is the most probable time, and b is the pessimistic time
  • Earliest Start (ES): the earliest time an activity can be started after the completion of its predecessor
  • Earliest Finish (EF): the earliest time that an activity can be completed
  • Latest Start (LS): the latest time that an activity can be started without delaying the start of any of its successors
  • Latest Finish (LF): the latest time that an activity can be completed without delaying the start of any of its successors

Test your knowledge on Program Evaluation Review Technique (PERT) and Critical Path Method (CPM), methods used for scheduling and controlling projects. Learn about the network of nodes and arrows, critical activities, project progress review, and their origin in the U.S. Navy Polaris Nuclear Submarine Project.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free

More Quizzes Like This

Mastering CPM and PERT
5 questions
Project Scheduling
36 questions

Project Scheduling

AudibleRhinoceros avatar
AudibleRhinoceros
CPM and PERT in Project Management
10 questions

CPM and PERT in Project Management

SelfSufficiencyConflict avatar
SelfSufficiencyConflict
Use Quizgecko on...
Browser
Browser