What is the Cost Performance Index (CPI) for work package C?

  • $1.13
  • $1.25
  • $0.78 (correct)
  • $0.89

What is the estimate to complete (ETC) for work package B?

  • $2,000,000
  • $1,000,000
  • $1,250,000
  • $1,500,000 (correct)

What is the Estimate at Completion (EAC) for work package A?

  • $8,000,000
  • $6,400,000
  • $10,666,667 (correct)
  • $7,200,000

What is the Schedule Performance Index (SPI) for the project as a whole?

<p>1.03 (B)</p> Signup and view all the answers

What is the estimated completion time (ECT) for the project as a whole?

<p>2.2 years (C)</p> Signup and view all the answers

Flashcards are hidden until you start studying

More Like This

Cuestionario 3-Unidad 6
23 questions
Software Project Management Basics
8 questions

Software Project Management Basics

BestKnownCynicalRealism avatar
BestKnownCynicalRealism
Project Management: Planning Performance Domain
44 questions
Use Quizgecko on...
Browser
Browser