What is the Cost Performance Index (CPI) for work package C?

  • $1.13
  • $1.25
  • $0.78 (correct)
  • $0.89
  • What is the estimate to complete (ETC) for work package B?

  • $2,000,000
  • $1,000,000
  • $1,250,000
  • $1,500,000 (correct)
  • What is the Estimate at Completion (EAC) for work package A?

  • $8,000,000
  • $6,400,000
  • $10,666,667 (correct)
  • $7,200,000
  • What is the Schedule Performance Index (SPI) for the project as a whole?

    <p>1.03</p> Signup and view all the answers

    What is the estimated completion time (ECT) for the project as a whole?

    <p>2.2 years</p> Signup and view all the answers

    More Like This

    Cuestionario 3-Unidad 6
    23 questions
    FPM Week 10 - Reporting and Metrics
    50 questions
    Software Project Management Basics
    8 questions

    Software Project Management Basics

    BestKnownCynicalRealism avatar
    BestKnownCynicalRealism
    Use Quizgecko on...
    Browser
    Browser