Podcast
Questions and Answers
What is the Cost Performance Index (CPI) for work package C?
What is the Cost Performance Index (CPI) for work package C?
- $1.13
- $1.25
- $0.78 (correct)
- $0.89
What is the estimate to complete (ETC) for work package B?
What is the estimate to complete (ETC) for work package B?
- $2,000,000
- $1,000,000
- $1,250,000
- $1,500,000 (correct)
What is the Estimate at Completion (EAC) for work package A?
What is the Estimate at Completion (EAC) for work package A?
- $8,000,000
- $6,400,000
- $10,666,667 (correct)
- $7,200,000
What is the Schedule Performance Index (SPI) for the project as a whole?
What is the Schedule Performance Index (SPI) for the project as a whole?
What is the estimated completion time (ECT) for the project as a whole?
What is the estimated completion time (ECT) for the project as a whole?
Flashcards are hidden until you start studying