Performance Data Analysis in Project Management Quiz
5 Questions
1 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the Cost Performance Index (CPI) for work package C?

  • $1.13
  • $1.25
  • $0.78 (correct)
  • $0.89
  • What is the estimate to complete (ETC) for work package B?

  • $2,000,000
  • $1,000,000
  • $1,250,000
  • $1,500,000 (correct)
  • What is the Estimate at Completion (EAC) for work package A?

  • $8,000,000
  • $6,400,000
  • $10,666,667 (correct)
  • $7,200,000
  • What is the Schedule Performance Index (SPI) for the project as a whole?

    <p>1.03 (B)</p> Signup and view all the answers

    What is the estimated completion time (ECT) for the project as a whole?

    <p>2.2 years (C)</p> Signup and view all the answers

    More Like This

    FPM Week 10 - Reporting and Metrics
    50 questions
    Software Project Management Basics
    8 questions

    Software Project Management Basics

    BestKnownCynicalRealism avatar
    BestKnownCynicalRealism
    Project Management: Planning Performance Domain
    44 questions
    Use Quizgecko on...
    Browser
    Browser