How is the total annual number of consumers power supply interruptions calculated?

  • By summating the total number of consumers affected by each power supply interruption in a given year (correct)
  • By considering only the longest power supply interruption in a given year
  • By dividing the total number of consumers by the number of power supply interruptions
  • By ignoring the number of consumers affected and focusing on duration only

What is the maximum time period (in calendar days) allowed for providing a new connection under OS3?

  • 53 days
  • 30 days
  • 106 days
  • 73 days (correct)

How is the aggregate sum of all consumer power supply interruption durations in minutes calculated?

  • By multiplying the total number of consumers affected by the duration of each power supply interruption (correct)
  • By averaging the duration of all power supply interruptions
  • By taking the square root of the duration of each interruption
  • By summing the total consumer load during interruptions

In the given data, how many eligible consumers applied for a new connection but were not connected within the maximum permitted time period of OS3?

<p>73 (B)</p> Signup and view all the answers

What is the unit of voltage mentioned in the document for consumers' supply, specifically in the Urban areas?

<p>400/230 V (C)</p> Signup and view all the answers

For which voltage level are eligible consumer's new power supply connection requirements specified in the text?

<p>Up to 400 V (C)</p> Signup and view all the answers

Which consumer supply voltage level has the highest number of remedial deviations according to the document?

<p>33 kV (C)</p> Signup and view all the answers

What load level is considered for rural areas when determining eligible consumer's new power supply connection requirements?

<p>Up to 15 kW (C)</p> Signup and view all the answers

Which voltage level is considered for loads above 500 kW but not exceeding 5000 kW?

<p>11 kV or 33 kV (B)</p> Signup and view all the answers

What is the frequency mentioned for consumers in hertz according to Annexure-I of the document?

<p>50 Hertz (D)</p> Signup and view all the answers

What is used to compute the System Average Interruption Duration Index (SAIDI)?

<p>Product of number of consumers affected and duration for each interruption (A)</p> Signup and view all the answers

What is the time limit specified for provision of a new connection after payment of the demand notice for supply at voltage level 66 kV and above for all loads?

<p>76 days (A)</p> Signup and view all the answers

If a distribution company fails to take the required action within the stipulated time, what is it required to do?

<p>Give reasons for each day of delay in writing to the consumer with a copy to the Authority (B)</p> Signup and view all the answers

What is the minimum percentage of new connections that a distribution company should provide electric power service to?

<p>95% (B)</p> Signup and view all the answers

For supply at voltage level up to 400 V and load above 15 kW but not exceeding 70 kW, what is the time limit for issuance of a demand notice after receipt of application?

<p>15 days (D)</p> Signup and view all the answers

What should the distribution company do if it does not meet the required actions within the specified time limits?

<p>Give reasons in writing to the consumer with a copy to the Authority (A)</p> Signup and view all the answers

What is the time limit for issuance of a demand notice after receipt of application for supply at voltage level 11 or 33 kV and load above 500 kW but not exceeding 5000 kW?

<p>76 days (C)</p> Signup and view all the answers