Podcast
Questions and Answers
How is the total annual number of consumers power supply interruptions calculated?
How is the total annual number of consumers power supply interruptions calculated?
- By summating the total number of consumers affected by each power supply interruption in a given year (correct)
- By considering only the longest power supply interruption in a given year
- By dividing the total number of consumers by the number of power supply interruptions
- By ignoring the number of consumers affected and focusing on duration only
What is the maximum time period (in calendar days) allowed for providing a new connection under OS3?
What is the maximum time period (in calendar days) allowed for providing a new connection under OS3?
- 53 days
- 30 days
- 106 days
- 73 days (correct)
How is the aggregate sum of all consumer power supply interruption durations in minutes calculated?
How is the aggregate sum of all consumer power supply interruption durations in minutes calculated?
- By multiplying the total number of consumers affected by the duration of each power supply interruption (correct)
- By averaging the duration of all power supply interruptions
- By taking the square root of the duration of each interruption
- By summing the total consumer load during interruptions
In the given data, how many eligible consumers applied for a new connection but were not connected within the maximum permitted time period of OS3?
In the given data, how many eligible consumers applied for a new connection but were not connected within the maximum permitted time period of OS3?
What is the unit of voltage mentioned in the document for consumers' supply, specifically in the Urban areas?
What is the unit of voltage mentioned in the document for consumers' supply, specifically in the Urban areas?
For which voltage level are eligible consumer's new power supply connection requirements specified in the text?
For which voltage level are eligible consumer's new power supply connection requirements specified in the text?
Which consumer supply voltage level has the highest number of remedial deviations according to the document?
Which consumer supply voltage level has the highest number of remedial deviations according to the document?
What load level is considered for rural areas when determining eligible consumer's new power supply connection requirements?
What load level is considered for rural areas when determining eligible consumer's new power supply connection requirements?
Which voltage level is considered for loads above 500 kW but not exceeding 5000 kW?
Which voltage level is considered for loads above 500 kW but not exceeding 5000 kW?
What is the frequency mentioned for consumers in hertz according to Annexure-I of the document?
What is the frequency mentioned for consumers in hertz according to Annexure-I of the document?
What is used to compute the System Average Interruption Duration Index (SAIDI)?
What is used to compute the System Average Interruption Duration Index (SAIDI)?
What is the time limit specified for provision of a new connection after payment of the demand notice for supply at voltage level 66 kV and above for all loads?
What is the time limit specified for provision of a new connection after payment of the demand notice for supply at voltage level 66 kV and above for all loads?
If a distribution company fails to take the required action within the stipulated time, what is it required to do?
If a distribution company fails to take the required action within the stipulated time, what is it required to do?
What is the minimum percentage of new connections that a distribution company should provide electric power service to?
What is the minimum percentage of new connections that a distribution company should provide electric power service to?
For supply at voltage level up to 400 V and load above 15 kW but not exceeding 70 kW, what is the time limit for issuance of a demand notice after receipt of application?
For supply at voltage level up to 400 V and load above 15 kW but not exceeding 70 kW, what is the time limit for issuance of a demand notice after receipt of application?
What should the distribution company do if it does not meet the required actions within the specified time limits?
What should the distribution company do if it does not meet the required actions within the specified time limits?
What is the time limit for issuance of a demand notice after receipt of application for supply at voltage level 11 or 33 kV and load above 500 kW but not exceeding 5000 kW?
What is the time limit for issuance of a demand notice after receipt of application for supply at voltage level 11 or 33 kV and load above 500 kW but not exceeding 5000 kW?