New Connection Provision Time Period Quiz

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson
Download our mobile app to listen on the go
Get App

Questions and Answers

How is the total annual number of consumers power supply interruptions calculated?

  • By summating the total number of consumers affected by each power supply interruption in a given year (correct)
  • By considering only the longest power supply interruption in a given year
  • By dividing the total number of consumers by the number of power supply interruptions
  • By ignoring the number of consumers affected and focusing on duration only

What is the maximum time period (in calendar days) allowed for providing a new connection under OS3?

  • 53 days
  • 30 days
  • 106 days
  • 73 days (correct)

How is the aggregate sum of all consumer power supply interruption durations in minutes calculated?

  • By multiplying the total number of consumers affected by the duration of each power supply interruption (correct)
  • By averaging the duration of all power supply interruptions
  • By taking the square root of the duration of each interruption
  • By summing the total consumer load during interruptions

In the given data, how many eligible consumers applied for a new connection but were not connected within the maximum permitted time period of OS3?

<p>73 (B)</p> Signup and view all the answers

What is the unit of voltage mentioned in the document for consumers' supply, specifically in the Urban areas?

<p>400/230 V (C)</p> Signup and view all the answers

For which voltage level are eligible consumer's new power supply connection requirements specified in the text?

<p>Up to 400 V (C)</p> Signup and view all the answers

Which consumer supply voltage level has the highest number of remedial deviations according to the document?

<p>33 kV (C)</p> Signup and view all the answers

What load level is considered for rural areas when determining eligible consumer's new power supply connection requirements?

<p>Up to 15 kW (C)</p> Signup and view all the answers

Which voltage level is considered for loads above 500 kW but not exceeding 5000 kW?

<p>11 kV or 33 kV (B)</p> Signup and view all the answers

What is the frequency mentioned for consumers in hertz according to Annexure-I of the document?

<p>50 Hertz (D)</p> Signup and view all the answers

What is used to compute the System Average Interruption Duration Index (SAIDI)?

<p>Product of number of consumers affected and duration for each interruption (A)</p> Signup and view all the answers

What is the time limit specified for provision of a new connection after payment of the demand notice for supply at voltage level 66 kV and above for all loads?

<p>76 days (A)</p> Signup and view all the answers

If a distribution company fails to take the required action within the stipulated time, what is it required to do?

<p>Give reasons for each day of delay in writing to the consumer with a copy to the Authority (B)</p> Signup and view all the answers

What is the minimum percentage of new connections that a distribution company should provide electric power service to?

<p>95% (B)</p> Signup and view all the answers

For supply at voltage level up to 400 V and load above 15 kW but not exceeding 70 kW, what is the time limit for issuance of a demand notice after receipt of application?

<p>15 days (D)</p> Signup and view all the answers

What should the distribution company do if it does not meet the required actions within the specified time limits?

<p>Give reasons in writing to the consumer with a copy to the Authority (A)</p> Signup and view all the answers

What is the time limit for issuance of a demand notice after receipt of application for supply at voltage level 11 or 33 kV and load above 500 kW but not exceeding 5000 kW?

<p>76 days (C)</p> Signup and view all the answers