New Connection Provision Time Period Quiz

PreciseDrama avatar
PreciseDrama
·
·
Download

Start Quiz

Study Flashcards

17 Questions

How is the total annual number of consumers power supply interruptions calculated?

By summating the total number of consumers affected by each power supply interruption in a given year

What is the maximum time period (in calendar days) allowed for providing a new connection under OS3?

73 days

How is the aggregate sum of all consumer power supply interruption durations in minutes calculated?

By multiplying the total number of consumers affected by the duration of each power supply interruption

In the given data, how many eligible consumers applied for a new connection but were not connected within the maximum permitted time period of OS3?

73

What is the unit of voltage mentioned in the document for consumers' supply, specifically in the Urban areas?

400/230 V

For which voltage level are eligible consumer's new power supply connection requirements specified in the text?

Up to 400 V

Which consumer supply voltage level has the highest number of remedial deviations according to the document?

33 kV

What load level is considered for rural areas when determining eligible consumer's new power supply connection requirements?

Up to 15 kW

Which voltage level is considered for loads above 500 kW but not exceeding 5000 kW?

11 kV or 33 kV

What is the frequency mentioned for consumers in hertz according to Annexure-I of the document?

50 Hertz

What is used to compute the System Average Interruption Duration Index (SAIDI)?

Product of number of consumers affected and duration for each interruption

What is the time limit specified for provision of a new connection after payment of the demand notice for supply at voltage level 66 kV and above for all loads?

76 days

If a distribution company fails to take the required action within the stipulated time, what is it required to do?

Give reasons for each day of delay in writing to the consumer with a copy to the Authority

What is the minimum percentage of new connections that a distribution company should provide electric power service to?

95%

For supply at voltage level up to 400 V and load above 15 kW but not exceeding 70 kW, what is the time limit for issuance of a demand notice after receipt of application?

15 days

What should the distribution company do if it does not meet the required actions within the specified time limits?

Give reasons in writing to the consumer with a copy to the Authority

What is the time limit for issuance of a demand notice after receipt of application for supply at voltage level 11 or 33 kV and load above 500 kW but not exceeding 5000 kW?

76 days

Test your knowledge on the maximum time period allowed for provision of new connections, the number of eligible consumers who applied for a new connection, and the number of consumers who were connected within the permitted time frame. Challenge yourself with questions related to connection delays and time calculations.