Network Scheduling Fundamentals
54 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What does lead measure in a project activity?

  • The time that an activity is delayed after its successor starts
  • The overall duration of the entire project
  • The time that an activity precedes the start or finish of its successor (correct)
  • The total time required to complete a task
  • In a Finish to Start (FS) relationship, when can activity B start?

  • Regardless of whether activity A is finished
  • Immediately after activity A starts
  • Simultaneously with activity A
  • Only after activity A has finished (correct)
  • What is the effect if activity C must not start until activity A has started in a Start to Start (SS) relationship?

  • C must begin immediately as A has started
  • C will start at least a specified duration after A has started (correct)
  • C can start at any time regardless of A's status
  • C must wait until A finishes before starting
  • In a Finish to Finish (FF) relationship, when can activity A finish?

    <p>After a defined time delay post completion of activity B</p> Signup and view all the answers

    What is the purpose of resource allocation and leveling in project management?

    <p>To ensure resources are brought in an organized manner</p> Signup and view all the answers

    In the Start to Finish (SF) relationship, how is the completion of activity B influenced?

    <p>It can only finish once activity A has started</p> Signup and view all the answers

    Which of the following statements about lag is true?

    <p>Lag is a period when an activity is delayed after its predecessor finishes</p> Signup and view all the answers

    How does a Start to Start (SS) relationship affect scheduling between two activities?

    <p>The second activity cannot start until the first has started</p> Signup and view all the answers

    Which of the following best defines the concept of lead in project management?

    <p>The time an activity can be advanced before its successor</p> Signup and view all the answers

    What happens during a Finish to Start (FS) activity link with 2 days of lead?

    <p>Activity B can start 2 days before activity A finishes</p> Signup and view all the answers

    What shape should resource curves ideally take during a project?

    <p>Positively sloping, peaking, then negatively sloping</p> Signup and view all the answers

    What is the worst-case scenario regarding resource distribution in a project?

    <p>Erratic curves requiring repetitive resource allocation</p> Signup and view all the answers

    Which strategy is necessary to improve resource allocation when faced with inefficiencies?

    <p>Move start dates of activities with float to maximize resource use</p> Signup and view all the answers

    What is the primary purpose of resource distribution in project management?

    <p>To determine the best time to start specific activities</p> Signup and view all the answers

    How does resource leveling contribute to project management?

    <p>By ensuring efficiency in the use of necessary resources</p> Signup and view all the answers

    What is the purpose of dummy activities in network scheduling?

    <p>They help ensure unique activity designations.</p> Signup and view all the answers

    Which step comes immediately after establishing activity relationships in network scheduling?

    <p>Draw a network diagram.</p> Signup and view all the answers

    What does a node represent in an arrow diagram?

    <p>A point in time when activities start and finish.</p> Signup and view all the answers

    What will result from calculating float values in scheduling?

    <p>Identifying the critical path.</p> Signup and view all the answers

    Which of the following is a characteristic of arrows in an arrow diagram?

    <p>They should point right, up, or down.</p> Signup and view all the answers

    What does the term 'Early Finish' refer to in project management?

    <p>The sum of the Early Start and Duration of an activity</p> Signup and view all the answers

    What does the term 'critical path' refer to in project scheduling?

    <p>The longest sequence of dependent tasks that determines project duration.</p> Signup and view all the answers

    During which step would you determine productivities and assign durations?

    <p>Before drawing a network diagram.</p> Signup and view all the answers

    Which of the following best defines the 'Critical Path' in project management?

    <p>A path where any delay will impact the overall project duration</p> Signup and view all the answers

    Which of the following is NOT a correct application of an arrow diagram convention?

    <p>Arrows pointing leftward.</p> Signup and view all the answers

    What does 'Total Float' represent in the context of critical activities?

    <p>The maximum time an activity can be delayed without affecting the project end date</p> Signup and view all the answers

    Which of the following statements is true regarding 'Late Start'?

    <p>Late Start equals Late Finish minus Duration</p> Signup and view all the answers

    What role do dummy activities play in project management?

    <p>They serve as logical constraints within the project network</p> Signup and view all the answers

    In the context of the Critical Path Method, what does the term 'Activity Duration' refer to?

    <p>An estimate of the time required to complete an activity</p> Signup and view all the answers

    What is meant by 'Early Start' in project scheduling?

    <p>The earliest possible start time based on preceding activities completion</p> Signup and view all the answers

    Why is determining the 'Project Duration' crucial in project management?

    <p>It helps in establishing deadlines for all project activities</p> Signup and view all the answers

    What is the early start (ES) for the task 'Move in'?

    <p>3</p> Signup and view all the answers

    What is the duration of the task 'Excavate Abutment'?

    <p>3</p> Signup and view all the answers

    What is the earliest finish (EF) for the task 'Order & Deliver Piles'?

    <p>15</p> Signup and view all the answers

    What value does the earliest start (ES) of 'Prefabricate abutment forms' depend on?

    <p>The earliest finish of 'Move in'</p> Signup and view all the answers

    What is the latest finish (LF) value for the last task in the project?

    <p>18</p> Signup and view all the answers

    What does the term 'Contract Date' refer to in relation to the project?

    <p>The last possible date for project completion</p> Signup and view all the answers

    What do the calculations of early start (ES) and early finish (EF) help to determine?

    <p>The critical path and scheduling of tasks</p> Signup and view all the answers

    How is the early finish (EF) for the task 'Drive Piles abutment' calculated?

    <p>By adding the early start (ES) to the duration</p> Signup and view all the answers

    What is the relationship between 'Drive Piles abutment' and its predecessor tasks?

    <p>It relies on the finish dates of its predecessors</p> Signup and view all the answers

    What is the primary purpose of performing a forward pass in project management?

    <p>To determine the earliest completion time of the project</p> Signup and view all the answers

    What is the formula for calculating Total Float (TF)?

    <p>TF = LF – EF = LS – ES</p> Signup and view all the answers

    What is the correct calculation for Free Float (FF) if ES of B is 54 and EF of A is 43?

    <p>FF = 8</p> Signup and view all the answers

    In a project network, what does the term 'Critical Path' refer to?

    <p>The sequence of activities that determines the project's minimum completion time.</p> Signup and view all the answers

    How is the relationship 'Finish to Start' (FS) depicted in a project schedule?

    <p>The successor activity begins after the predecessor activity finishes.</p> Signup and view all the answers

    What is the purpose of calculating 'Float' in project management?

    <p>To assess the flexibility in scheduling activities.</p> Signup and view all the answers

    If Activity A has an EF of 35 and Activity B has an ES of 36, what is the Free Float for Activity A?

    <p>0</p> Signup and view all the answers

    Which of the following defines 'Lag' in project management?

    <p>The time a task is delayed after its predecessor has finished.</p> Signup and view all the answers

    In Example #2, how many days does Activity D take?

    <p>12</p> Signup and view all the answers

    If the Total Float for Activity H is calculated as TF = 0, what does this imply?

    <p>Activity H is critical and cannot be delayed.</p> Signup and view all the answers

    What is the outcome of the Forward Pass process in project scheduling?

    <p>Determination of the earliest start and finish times for each activity.</p> Signup and view all the answers

    Which activity has the latest finish time in Example #2?

    <p>Activity N</p> Signup and view all the answers

    If a project activity is described as having a 'Finish to Finish' relationship with its predecessor, what does this mean?

    <p>The successor must finish before the predecessor can finish.</p> Signup and view all the answers

    What is the significance of the Backward Pass in project management?

    <p>To calculate the latest start and finish times for tasks.</p> Signup and view all the answers

    Study Notes

    Network Scheduling

    • Network scheduling is a process for planning and managing projects.
    • Key steps in the network model include defining activities, determining physical constraints, establishing activity relationships, drawing a network diagram, determining productivities and assigning durations, assigning resources and costs, calculating early and late start and finish times, and computing float values and identifying the critical path.

    Steps in the Network Model

    • Define activities: Clearly outline all tasks in the project.
    • Determine physical constraints: Identify any limitations on the project, such as location, materials, or time.
    • Establish activity relationships: Figure out which tasks depend on others. This determines the order of tasks and prevents work from happening prematurely.
    • Draw a network diagram: Visually represent the tasks and their relationships. A network diagram (or arrow diagram) uses arrows and nodes. The arrows represent the activity, and the nodes represent the event, when the activity starts and ends.
    • Determine productivities and assign durations: Estimate how long each task will take. Productivities involve the output per unit of time and are essential in determining task durations.
    • Assign resources and costs: Identify the resources needed for each task and their associated costs. These costs can be labor cost, material cost, etc.
    • Calculate early and late start & finish times: Determine the earliest and latest possible completion times for each activity. Early times define the quickest project completion, and late times consider buffer time for potential delays.
    • Compute float values and identify critical path: Calculate the amount of time an activity can be delayed without affecting the project completion time. The critical path is the longest path through the network, and delays anywhere on it will affect the project deadline.

    Arrow Diagram

    • Arrow diagrams use arrows and nodes to represent project activities and events, respectively.
    • Arrows show activities, while nodes represent the point in time when activities begin or end.
    • This method is often called I-J Diagram or CPM.

    Formats

    • Different formats can be used in arrow diagrams for projects, including arc format, staff format, and sloping format. Example formats are displayed in the document.

    Arrow Diagram Example

    • The diagram outlines specific tasks with durations and dependencies.
    • A table provides activities, descriptions, and durations.

    Arrow Diagram Conventions

    • The diagrams conform to various conventions—nonconsecutive node and arrow numbers, J-node numbers greater than I-node numbers.
    • The diagrams follow arrow direction (right, up or down) rules for proper connections and ordering. Number ordering conventions are illustrated.
    • Activities and precedence relationships are represented.

    Dummy Activities

    • Dummy activities are activities with zero duration.
    • They are used to represent relationships between activities when necessary for unique activity designations, for clearer logical constraints, and to create starting or ending activities. Diagrams of dummy activities, as activity splitters, for logical constraints, and for starting/ending tasks are illustrated.

    Critical Path Method (CPM)

    • CPM is a method for scheduling and controlling project activities.
    • Key terms include early start (ES), early finish (EF), late start (LS), late finish (LF), and activity duration.
    • Diagrams and tables define these terms in relation to the project timeline.

    Activity Times

    • Early Start (ES): The point in time when all preceding activities are completed.
    • Early Finish (EF): Earliest time activity can be completed. Calculated as ES + Duration.
    • Late Finish (LF): The latest time where all work involved in an activity can be completed to avoid delaying others activities.
    • Late Start (LS): Latest time to begin an activity without delaying subsequent activities. Calculated as LF - Duration.

    CPM - Definitions

    • Duration (D): Average time for an activity.
    • Early Start (ES): Earliest start time, following forward pass calculation.
    • Early Finish (EF): Earliest possible finish time (ES + Duration)
    • Late Start (LS): Latest possible start time for an activity, supporting project finish date (backward pass).
    • Late Finish (LF): Latest possible finish time for an activity, supporting project finish date

    Critical Path

    • The critical path is the sequence of dependent activities in a network diagram that determines the minimum time needed to complete the project. Delays on the critical path affect the project's total completion time.
    • The aggregate duration of activities along the critical path determines the project duration.
    • Critical activities are those activities on the critical path having no total float. Total Float is the amount of time an activity on the critical path can be delayed without affecting the entire project completion time.

    Precedence Diagram (PDM) - AoN

    • PDM (Precedence Diagram) is a project management diagram that outlines project activities and their dependencies with boxes (representing activities) and arrows connecting them.
    • Predecessors are activities that must be completed before another activity can begin.
    • Successors are activities that depend on the completion of another activity.

    Forward Pass

    • Project starts at day 0 (equivalent to beginning of day 1)
    • Early Start (ES): Calculated as the maximum of the early finishes of all preceding activities
    • Early Finish (EF) = ES + duration

    Backward Pass

    • Calculations for late start and finish times are derived using the backward pass method.
    • Late Finish (LF): Calculated by working backward from the final activity.
    • Late Start (LS) = LF - Duration

    Float (Slack)

    • Total Float (TF) is the time an activity can be delayed without delaying the entire project.
    • Calculated as LS - ES or LF - EF.
    • Free float (FF) is the amount of time an activity can be delayed without affecting the start of any subsequent activities.
    • Calculated as ESj - EFi; where ESj is the early start of an activity, and EFi the early finish of the previous activity.

    Activity Lead and Lag

    • Lag represents the time an activity is delayed from the preceding activity's start or finish.
    • Lead represents the time an activity precedes the start or finish of its successor.

    Special Relationships

    • Start-to-Start (SS): The start of activity B depends upon the start of activity A.
    • Finish-to-Start (FS): The start of activity B depends on the finish of activity A.
    • Start-to-Finish (SF): The finish of activity B depends on the start of activity A.
    • Finish-to-Finish (FF): The finish of activity B depends on the finish of activity A by a given delay.

    Importance of Allocating and Leveling Resources

    • Resources must be allocated to complete the project. Resource allocation involves bringing resources to the project in an organized manner. Resource leveling smooths out resource usage across the project. The resource curve should rise during the project then fall till the project completes.
    • Incorrect allocation of resources in cases of "ups and downs" will be inefficient, costly, and negatively affect staff morale.
    • When resources are limited, task start times are adjusted to optimize the use of resources while meeting the project deadline.

    Resource Allocation and Leveling

    • Resource Allocation deals with the efficient distribution of resources for project activities.
    • Resource leveling adjusts activities to better use resources when the project duration isn't adjustable.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Week 7-8 Scheduling PDF

    Description

    This quiz covers the essential processes involved in network scheduling for project management. Key steps include defining activities, determining constraints, and establishing relationships between tasks. Test your knowledge on creating network diagrams and understanding critical paths in project planning.

    More Like This

    Project Scheduling and Network Diagram
    5 questions
    Activity Network Diagram
    10 questions
    PMGT3623 Scheduling - Week 3 Quiz
    54 questions

    PMGT3623 Scheduling - Week 3 Quiz

    SweetheartMandelbrot1035 avatar
    SweetheartMandelbrot1035
    Use Quizgecko on...
    Browser
    Browser