Mastering Time Estimates

FierySard avatar
FierySard
·
·
Download

Start Quiz

Study Flashcards

3 Questions

Which time estimate assumes that everything proceeds better than expected?

Optimistic time (O)

Which time estimate assumes that everything goes wrong, excluding major catastrophes?

Pessimistic time (P)

Which time estimate represents the best estimate of the time required to accomplish a task, assuming everything proceeds as normal?

Most likely time (M)

Test your knowledge of project management with this quiz on optimistic, pessimistic, and most likely time estimates. Learn how to calculate the minimum and maximum possible time required for a task, as well as the best estimate. Perfect for those looking to improve their project planning skills.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free

More Quizzes Like This

Mastering Time Management
3 questions

Mastering Time Management

ReasonableUnderstanding avatar
ReasonableUnderstanding
Mastering Time Management
5 questions

Mastering Time Management

GoldenEnlightenment avatar
GoldenEnlightenment
Mastering CPM and PERT
5 questions
Use Quizgecko on...
Browser
Browser