Mastering the Bid Process in Construction

WorthwhilePyrite5473 avatar
WorthwhilePyrite5473
·
·
Download

Start Quiz

Study Flashcards

26 Questions

Which term refers to a change to the bid package issued during the bid period and before execution of the contract?

Definitions Addendum

Which term refers to the stipulated sum of money without any adjustment because of alternative prices or substitutions, etc., for which the bidder offers to perform the work called for in the bid documents?

Base Bid

Which term refers to a promise to answer for payment of a debt or performance of an obligation if the person liable in the first instance fails to make payment or perform the obligation?

Bond

Which of the following is NOT a purpose of addenda in bid documents?

To issue new information orally

When should the last opportunity for issuing an addendum be?

Four working days before bid closing

What is the recommended time for closing bids?

Late afternoon

What should be done with bids received after the designated bid closing time?

They should be returned unopened to the bidder

Which type of tender call is frequently used when the project involves public funds?

Open Competitive Bids

What is the purpose of pre-qualification in the bidding process?

To eliminate candidates who do not demonstrate necessary financial capacity and experience

What is the purpose of a bond in the construction industry?

To indemnify the owner against loss arising from contractor's failure

When are negotiated contracts mostly used in construction procurement?

When time is of the essence or when an owner values long-term relationships

Which bond guarantees that if the bid is accepted, the contractor will enter into a formal contract with the owner?

Bid Bond

What is the usual range for the amount of bid bonds?

Between 5% and 10% of the estimated construction cost

Which bond indemnifies the owner up to the amount of the bond in the event of default on the part of the contractor?

Performance Bond

Which bond guarantees that claimants will be paid for labor and materials provided to the contractor for use on the project?

Labour and Material Payment Bond

Which of the following is NOT a characteristic of the design-bid-build method of procurement?

The architect is retained by a design-builder

What is the purpose of a surety in construction contracts?

To guarantee the performance of the contractor

Which book is recommended for a detailed explanation of the procedures and case law for bidding and tendering in Canada?

Paul Sandori and William Pigott's Bidding and Tendering: What Is the Law. 5th Edition

When should the planning of how to procure the construction contractor start in a project?

Early in the project

According to CCDC 23, if a bidder notifies the architect or client of a serious mistake in their bid after the bid closing, what should be done?

The bid should not be accepted and the bidder penalized.

What happens if a bidder submits a bid and then wants to withdraw it during the period of irrevocability?

The bidder can withdraw the bid but forfeits the bid deposit or bond.

What should the architect advise the client to do if only one bid is submitted?

Return the bid unopened.

Architects may need to provide bidders with information on the details of pre-awards, pre-purchased materials, and the responsibilities which the successful bidder must assume. What are some examples of documents that architects may need to provide bidders with?

The Bid Package

According to the text, what is the purpose of a privilege clause in the bid package?

To justify awarding the contract to someone other than the lowest bidder

According to the text, what is considered a breach of the duty of fairness to all other bidders?

Accepting a non-conforming bid

When determining how to distribute bid documents, what should architects consider?

The availability of electronic tendering services

Study Notes

Bid Package Changes

  • An addendum is a change to the bid package issued during the bid period and before execution of the contract.

Types of Bids

  • A lump sum bid is a stipulated sum of money without any adjustment because of alternative prices or substitutions, etc., for which the bidder offers to perform the work called for in the bid documents.

Guarantee and Performance

  • A surety is a promise to answer for payment of a debt or performance of an obligation if the person liable in the first instance fails to make payment or perform the obligation.
  • The purpose of a bond in the construction industry is to provide a guarantee or assurance of performance or payment.

Addenda and Bid Closing

  • The last opportunity for issuing an addendum should be a reasonable time before the bid closing time.
  • The recommended time for closing bids is when all bids are received and the bid closing time has expired.
  • Bids received after the designated bid closing time should be rejected.

Tender Calls and Pre-qualification

  • A tender call that is frequently used when the project involves public funds is an open tender call.
  • The purpose of pre-qualification in the bidding process is to ensure that bidders have the necessary skills, experience, and resources to perform the work.

Negotiated Contracts

  • Negotiated contracts are mostly used in construction procurement when the project is complex, urgent, or has unique requirements.

Types of Bonds

  • A bid bond guarantees that if the bid is accepted, the contractor will enter into a formal contract with the owner.
  • The usual range for the amount of bid bonds is 5% to 10% of the bid price.
  • A performance bond indemnifies the owner up to the amount of the bond in the event of default on the part of the contractor.
  • A labour and material payment bond guarantees that claimants will be paid for labor and materials provided to the contractor for use on the project.

Design-Bid-Build Method

  • The design-bid-build method of procurement is characterized by a clear separation between the design and construction phases.
  • The design-bid-build method of procurement is not characterized by a single entity providing both design and construction services.

Surety and Construction Contracts

  • The purpose of a surety in construction contracts is to provide a guarantee or assurance of performance or payment.

Bidding and Tendering in Canada

  • The book "Canadian Construction Documents Committee (CCDC) 23" is recommended for a detailed explanation of the procedures and case law for bidding and tendering in Canada.

Procurement Planning

  • The planning of how to procure the construction contractor should start in a project as early as possible, ideally during the project initiation phase.

Bid Errors and Withdrawals

  • If a bidder notifies the architect or client of a serious mistake in their bid after the bid closing, the bidder should be allowed to withdraw their bid.
  • If a bidder submits a bid and then wants to withdraw it during the period of irrevocability, the bidder is not permitted to withdraw their bid.
  • If only one bid is submitted, the architect should advise the client to reject the bid and re-tender the project.

Bid Documents and Information

  • Architects may need to provide bidders with information on the details of pre-awards, pre-purchased materials, and the responsibilities which the successful bidder must assume.
  • Examples of documents that architects may need to provide bidders with include project schedules, site plans, and technical specifications.

Privilege Clauses and Duty of Fairness

  • The purpose of a privilege clause in the bid package is to allow the owner to reject any or all bids.
  • A breach of the duty of fairness to all other bidders occurs when an owner favors one bidder over others.

Distributing Bid Documents

  • When determining how to distribute bid documents, architects should consider the need for confidentiality, the security of the bid process, and the potential for bid shopping.

"How Well Do You Know the Bid Process in the Construction Industry?" Test your knowledge on the rules and deadlines for submitting quotations as a general contractor. Learn about the role of bid depositories and the importance of analyzing documents in the bid preparation process.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free

More Quizzes Like This

Mastering Bid Depositories
26 questions

Mastering Bid Depositories

WorthwhilePyrite5473 avatar
WorthwhilePyrite5473
CCDC 23 Bidding Guidelines
90 questions

CCDC 23 Bidding Guidelines

WorthwhilePyrite5473 avatar
WorthwhilePyrite5473
Bid Corrections and Provisional Sums Quiz
10 questions
Use Quizgecko on...
Browser
Browser