Chapter 12 - Managing Disruptions to the Plan - Issues and Change
14 Questions
6 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is a common first step in the Change Control Process?

  • Assess the impact of the change
  • Submit a Change Request form (correct)
  • Reject the change request
  • Update planning documents
  • What benefit was identified for changing the trade show giveaways to picture frames?

  • Lower production costs
  • Increased engagement with users
  • Better fit with the project theme
  • More memorable representation of the software (correct)
  • Which of the following is NOT a step in the Change Control Process?

  • Approve or reject the change request
  • Update planning documents
  • Evaluate the change's benefits (correct)
  • Assess the impact of the requested change
  • Which category received the highest weight in the decision criteria evaluation?

    <p>Effectiveness</p> Signup and view all the answers

    What is the purpose of an Issue Log in project management?

    <p>To document issues that may reduce project effectiveness.</p> Signup and view all the answers

    Which phase of the project life cycle involves addressing unexpected issues?

    <p>Executing Phase</p> Signup and view all the answers

    Which of the following is NOT a step in the problem-solving approach for resolving issues?

    <p>Prioritize all project tasks</p> Signup and view all the answers

    Why is it important to sort or filter the Issue Log?

    <p>To prioritize issues and manage them effectively.</p> Signup and view all the answers

    What call to action is indicated after documenting an issue in the Issue Log?

    <p>Review and prioritize the documented issues.</p> Signup and view all the answers

    What can happen if project issues are left unresolved?

    <p>They can lead to reduced effectiveness of the project.</p> Signup and view all the answers

    Which of the following reflects the nature of changes in project management?

    <p>Requests for changes often arise during project execution.</p> Signup and view all the answers

    During which project life cycle phase is change management particularly crucial?

    <p>Executing Phase</p> Signup and view all the answers

    What aspect of project management is indicated by the need to adapt to unexpected problems?

    <p>Project uncertainties</p> Signup and view all the answers

    Which statement best describes the concept of project effectiveness in the context of issues?

    <p>Unresolved issues can compromise project effectiveness.</p> Signup and view all the answers

    Study Notes

    Managing Project Issues

    • A project issue is a problem that has the potential of negatively impacting the project
    • Issues should be documented in an Issue Log
    • The Issue Log allows issues to be reviewed and prioritized
    • The Issue Log could be sorted by Priority or filtered by Status
    • Sorting and filtering an Issue Log allows for easier management and prioritization of issues

    Resolving Project Issues

    • Issues should be resolved by using a problem-solving approach
    • The approach used could be informal for smaller issues
    • For larger more complex issues, the approach should be more formal
    • Steps in the problem-solving approach
      • Fully Describe the issue
      • Develop alternative solutions
      • Select the optimal solution
      • Implement the selected solution
    • Selecting the optimal solution
      • Decision criteria and weighted averages may be used for complex issues
      • Alternative solutions should be assessed by cost, time, and effectiveness

    Managing Project Change

    • Project changes are different from issues because they can be considered and implemented
    • Changes require a Change Control Process
    • This process is used to determine whether or not a change should be made

    Change Control Process

    • The Change Control Process requires the following steps:
      • Submit a Change Request form
      • Assess the impact of the requested change
      • Approve or Reject the change request
      • Update planning documents if the change is approved
      • Carry out the change
    • Change Request Form
      • Contains information about the proposed change
      • Benefits of the change
      • Impacts to the project
      • Approved or Rejected decision

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz covers essential strategies for managing and resolving project issues effectively. It focuses on the use of an Issue Log for documentation, prioritization, and the problem-solving approaches needed for both small and complex issues. Test your knowledge on the steps and methods to ensure project success.