What is the purpose of subjecting construction methods and material alternatives to value analysis during the design phase?
To decrease the cost and time of the construction process
Why are design changes or procurement initiated if long delivery periods for materials are involved?
To avoid delays in the construction process
What does the project manager in field construction projects typically oversee?
All aspects of the construction project
Why is having a good working relationship with various outside persons and organizations crucial in guiding a construction project to its conclusion?
To promote collaboration and smooth project progress
What is a key factor considered when choosing construction methods during the design phase?
Material availability
When are preliminary project time schedules usually prepared during a construction project?
During the design phase progress
What is the purpose of project management?
To ensure all aspects of project delivery are executed for the owner
Which responsibility does program management focus on?
Integrating and coordinating a set of projects to achieve organizational objectives
What is a typical responsibility of construction management?
Cost Management
Which phase of project delivery does project management oversee?
Design, construction, procurement, and closeout/turnover
What does project management aim to achieve for the owner?
Safe, on-time, on-budget project delivery meeting all standards
What is the purpose of program management?
Top-down planning, management, and coordination of projects to meet overarching goals
What does procurement refer to in the context of project stages?
Ordering, expediting, and delivering key project equipment and materials
Which function may or may not be handled separately from the construction process itself?
Procurement
When does the project stage move toward conclusion?
When the owner gains beneficial use of the facility
What is the purpose of Construction Management?
Ensure all aspects of construction are executed for the owner safely on time
What is the primary focus of Project Stages - Procurement and Construction?
Ordering, expediting, and delivering key project equipment and materials
Which stage involves putting the materials and equipment into place?
Construction stage
Explore the management practices during the design phase of construction projects, including value analysis, cost budget preparations, and procurement considerations. Test your knowledge on optimizing construction processes in terms of cost and time.
Make Your Own Quizzes and Flashcards
Convert your notes into interactive study material.
Get started for free