API 653 Covers which of the following activities?

  • Tank design
  • tank fabrication
  • tank operation
  • tank reconstruction (correct)
  • Corroded roof plates on a fixed roof tank shall not be less than

  • designers recomendation
  • 0.090" in any 100 inch squared area (correct)
  • 0.050" at any point
  • tmin averaged over the critical length
  • A new nameplate should be added to a tank after

  • either major repairs or major alterations
  • either major alterations or tank reconstruction
  • it has been relocated
  • it has been reconstructed (correct)
  • for a reconstructed tank, the shell thickness readings used to determine the allowable shell height must have been taken within the last:

    <p>180 days</p> Signup and view all the answers

    the impressed current sources of a cathodic protection system should be checked (to see if still operating) every

    <p>two months</p> Signup and view all the answers

    which of the following is part of the critical zone

    <p>the bottom within 3&quot; of the shell</p> Signup and view all the answers

    a tank is 20 years old and has a bottom thickness of 0.170". Original bottom thickness was 0.250". Determine the interval for the next internal inspections

    <p>17.5 years</p> Signup and view all the answers

    Widely scattered pitting in a tank shell can be ignored if the extent of the pitting does not exceed

    <p>2 inch in any vertical 8 inches</p> Signup and view all the answers

    Which of the following is an advantage of the galvanic cathodic protection systems

    <p>annual maintenance costs are generally low</p> Signup and view all the answers

    Hot taps are permitted:

    <p>only in the liquid section of the tank</p> Signup and view all the answers

    An API 653 hydro test shall be held for at least

    <p>24 hours</p> Signup and view all the answers

    Which of the following activities is considered an alteration in API 653

    <p>the addition of a 16 NPS nozzle</p> Signup and view all the answers

    repaired or replaced bottom welds shall be examined with either a vacuum box or by using

    <p>a tracer gas test</p> Signup and view all the answers

    welding procedures for tank repairs to the shell should be qualified in accordance with

    <p>ASME Section IX</p> Signup and view all the answers

    A lap patch is installed on a tank bottom and the patch plate crosses a tank bottom weld. what is the minimum dimension for this patch plate

    <p>12&quot;</p> Signup and view all the answers

    API 653 is intended to be used by Owner/Operator organizations that

    <p>have access to engineers and inspectors</p> Signup and view all the answers

    Which of the following tests are required when qualifying a weld procedure

    <p>a minimum of 2 tension tests</p> Signup and view all the answers

    calcining of a tanks concrete ringwall can occur when the concrete is

    <p>exposed to a high temperature</p> Signup and view all the answers

    Which of the following does not increase the risk of brittle fracture

    <p>change to a product with increased viscosity</p> Signup and view all the answers

    Which external floating roof is most susceptible to sinking

    <p>pan</p> Signup and view all the answers

    All new materials used for repairs must conform to

    <p>current applicable standard</p> Signup and view all the answers

    which of the following is not considered one of the major types of inspection records

    <p>operation history</p> Signup and view all the answers

    Which tank component in a reconstructed tank must be identified by material type

    <p>bottom plates welded to the shell</p> Signup and view all the answers

    an F on the radiograph indicates

    <p>the IQI is placed on the film side</p> Signup and view all the answers

    if an atmospheric tank is air tested, the pressure should not exceed

    <p>2 inches of water</p> Signup and view all the answers

    the welding position 4G is a(n)

    <p>overhead plate groove weld</p> Signup and view all the answers

    A new tank bottom was installed above the existing tank bottom. Now the spacing between a nozzle and the new bottom is below the minimum requirements of API 650. Which of the following is not an acceptable method of repair

    <p>remove the existing reinforcement pad</p> Signup and view all the answers

    During a tank repair, if API 653 conflicts with the design standard, which standard governs?

    <p>API 653</p> Signup and view all the answers

    All reconstruction work must be authorized by the

    <p>either the engineer or inspector</p> Signup and view all the answers

    More Like This

    API 650 Closed Book Test
    25 questions

    API 650 Closed Book Test

    UserReplaceableSmokyQuartz avatar
    UserReplaceableSmokyQuartz
    Master the Art of Book Cover Design
    5 questions
    Student's Book 01: Close to You
    10 questions
    Use Quizgecko on...
    Browser
    Browser