Which activity is LEAST likely to occur during the closing phase of a project?
Which activity is LEAST likely to occur during the closing phase of a project?
- Documenting lessons learned for future projects.
- Developing a detailed work breakdown structure (WBS). (correct)
- Delivering final products to the client.
- Conducting a post-project review to evaluate successes and failures.
A project manager is transitioning from the construction industry to the software development industry. Which factor will MOST likely pose a challenge?
A project manager is transitioning from the construction industry to the software development industry. Which factor will MOST likely pose a challenge?
- The project manager's familiarity with project management standards.
- The project manager's understanding of general project management principles.
- The project manager's knowledge of the specific body of knowledge related to software development. (correct)
- The project manager's certifications from professional organizations.
Which knowledge area in project management PRIMARILY focuses on ensuring that project outputs satisfy specific performance criteria?
Which knowledge area in project management PRIMARILY focuses on ensuring that project outputs satisfy specific performance criteria?
- Managing Scope
- Managing Human Resources
- Managing Communication
- Managing Quality (correct)
A project team is struggling with internal conflicts. Which project management knowledge area should the project manager prioritize to address this issue?
A project team is struggling with internal conflicts. Which project management knowledge area should the project manager prioritize to address this issue?
Which of the following BEST describes the purpose of 'Managing Integration' in the PMBOK?
Which of the following BEST describes the purpose of 'Managing Integration' in the PMBOK?
A project manager notices that a key stakeholder is misinformed about the project's progress. Which action should the project manager take FIRST?
A project manager notices that a key stakeholder is misinformed about the project's progress. Which action should the project manager take FIRST?
What is the PRIMARY purpose of a 'work breakdown structure (WBS)' in project management?
What is the PRIMARY purpose of a 'work breakdown structure (WBS)' in project management?
A project is consistently exceeding its allocated budget. Which project management process should the project manager focus on improving?
A project is consistently exceeding its allocated budget. Which project management process should the project manager focus on improving?
How do projects differ from operations in terms of their nature and objectives?
How do projects differ from operations in terms of their nature and objectives?
Which of the following is the MOST effective measure of project success in contemporary project management?
Which of the following is the MOST effective measure of project success in contemporary project management?
In the project management process, which process group involves defining the project objectives and securing the necessary approvals to proceed?
In the project management process, which process group involves defining the project objectives and securing the necessary approvals to proceed?
A project manager is facing a situation where the available resources have been significantly reduced. According to the Project Constraints, how would this impact the project?
A project manager is facing a situation where the available resources have been significantly reduced. According to the Project Constraints, how would this impact the project?
What is the primary relationship defined by the triple constraint in project management?
What is the primary relationship defined by the triple constraint in project management?
Which stakeholder typically provides the financial resources for a project and serves as the ultimate escalation point for major issues?
Which stakeholder typically provides the financial resources for a project and serves as the ultimate escalation point for major issues?
A project is underway to develop a new software application. Which stakeholder group would be MOST concerned with the usability and performance of the final application?
A project is underway to develop a new software application. Which stakeholder group would be MOST concerned with the usability and performance of the final application?
A project team is struggling to meet a critical deadline due to unforeseen technical challenges. What role should the project sponsor take in this situation?
A project team is struggling to meet a critical deadline due to unforeseen technical challenges. What role should the project sponsor take in this situation?
Which of the following activities is most crucial during the initiating phase of a project, according to the PMI process groups?
Which of the following activities is most crucial during the initiating phase of a project, according to the PMI process groups?
In project management, which of the following best describes the role of a 'Process Manager' within a project team?
In project management, which of the following best describes the role of a 'Process Manager' within a project team?
Which of the following is the primary purpose of a Project Management Office (PMO) within an organization?
Which of the following is the primary purpose of a Project Management Office (PMO) within an organization?
What is the most important characteristic of the 'sprints' used in Scrum development?
What is the most important characteristic of the 'sprints' used in Scrum development?
Which aspect of project management does the Work Breakdown Structure (WBS) primarily support?
Which aspect of project management does the Work Breakdown Structure (WBS) primarily support?
Why is maintaining a stakeholder register considered crucial in project management?
Why is maintaining a stakeholder register considered crucial in project management?
A project manager notices a significant scope change request from a client. What should be the FIRST step the project manager takes?
A project manager notices a significant scope change request from a client. What should be the FIRST step the project manager takes?
Which communication method is most suitable for conveying complex, detailed information that requires careful review?
Which communication method is most suitable for conveying complex, detailed information that requires careful review?
What is the key objective of project risk management?
What is the key objective of project risk management?
In the context of project procurement, what does 'contract administration' primarily involve?
In the context of project procurement, what does 'contract administration' primarily involve?
Flashcards
What is a Project?
What is a Project?
A unique and temporary endeavor with a defined objective.
What is an Operation?
What is an Operation?
Ongoing, repetitive work with continuous processes and no defined end date.
What is Project Success?
What is Project Success?
Meeting scope, budget and timeline while satisfying the customer.
What is Project Management?
What is Project Management?
Signup and view all the flashcards
What are the 5 Project Management Process Groups?
What are the 5 Project Management Process Groups?
Signup and view all the flashcards
What are Project Constraints?
What are Project Constraints?
Signup and view all the flashcards
What is the Triple Constraint?
What is the Triple Constraint?
Signup and view all the flashcards
Who are Project Stakeholders?
Who are Project Stakeholders?
Signup and view all the flashcards
Resource Management
Resource Management
Signup and view all the flashcards
Quality Assurance
Quality Assurance
Signup and view all the flashcards
Stakeholder Communication
Stakeholder Communication
Signup and view all the flashcards
Closing Phase
Closing Phase
Signup and view all the flashcards
Managing Integration
Managing Integration
Signup and view all the flashcards
Managing Scope
Managing Scope
Signup and view all the flashcards
Managing Time/Schedule
Managing Time/Schedule
Signup and view all the flashcards
Managing Costs
Managing Costs
Signup and view all the flashcards
Risk Management
Risk Management
Signup and view all the flashcards
Procurement Management
Procurement Management
Signup and view all the flashcards
Stakeholder Management
Stakeholder Management
Signup and view all the flashcards
Project Scope Definition
Project Scope Definition
Signup and view all the flashcards
Project Schedule/Time Management
Project Schedule/Time Management
Signup and view all the flashcards
Project Costs
Project Costs
Signup and view all the flashcards
Project Quality
Project Quality
Signup and view all the flashcards
Project Stakeholders
Project Stakeholders
Signup and view all the flashcards
Scrum Development
Scrum Development
Signup and view all the flashcards
Project Management Office (PMO)
Project Management Office (PMO)
Signup and view all the flashcards
Study Notes
- Project management applies knowledge, skills, tools, and techniques to meet project requirements.
Defining a Project
- Projects produce a unique product or service
- Success is determined when a particular objective is achieved
- Projects are temporary
- Projects have definite start and end dates
- Projects end when objectives are achieved or abandoned
Operation
- Operation is ongoing and repetitive
- It involves continuous work without an end date
- Processes are repeated to produce the same results
Project Success
- Traditionally success is measured by being on time, within budget, and delivering the promised scope
- A more effective measure is satisfied customers
Project Management Process Groups
- Initiating involves defining the project and getting approval
- Planning involves setting goals, budgets, schedules, and risks
- Executing involves doing the work and managing the team
- Monitoring & Controlling tracks progress and making adjustments
- Closing completes and evaluates the project
Project Constraints
- Cost constitutes the budget and resources
- Scope defines what needs to be done
- Quality meets standards and expectations
- Risk includes uncertainties that impact success
- Resources constitute the availability of people, equipment, and materials
- Time involves the project deadline
Triple Constraint
- All constraints are grouped into: cost, scope, and time
Project Stakeholders
- Stakeholders are individuals or groups affected by the project
- Key stakeholders include:
- Project Sponsor who provides funding and overall support
- Project Manager who leads the project and ensures goals are met
- Project Team Members perform tasks and contribute expertise
- Customers/Clients use the final product or service
- Suppliers/Vendors provide materials or services needed
- End Users are people who directly use the product/service
- Any individual, group, or organization can be a stakeholder
Stakeholder Roles
- Functional Managers manages the work related to the functional areas of the business
- Sponsors provides resources and support for the project, is accountable for the project success, and serves as an escalation point
- The Project Team carries out the project work
Project Success Criteria
- A project is considered successful if it:
- Achieves its goals and objectives
- Stays within budget and meets the deadline
- Delivers the expected quality and value
- Satisfies stakeholders
Importance of Project Management
- Project management improves efficiency by setting clear goals and deadlines
- It reduces risks through planning and monitoring
- It ensures better resource management (money, time, people)
- By being organized project management increases chances of project success
Project Management Expertise
- PM's need application knowledge, understanding of the project environment, management knowledge & skills, and interpersonal skills
- Project environment includes cultural, social, political, international, and physical elements
- Management knowledge and skills include communication, influence, leadership, motivation, negotiation and problem solving
Project Management Standards
- Organisations like PMI (Project Management Institute) and IPMA (International Project Management Association) set standards
- Standards organisations offers certifications: CAPM, and PMP
Project Life Cycle
- The project life cycle outlines the stages a project undergoes from start to finish, ensuring systematic progress toward objectives
- It consists of four primary phases: Initiation, Planning, Implementation, and Closure
Initiation Phase
- The project's purpose or need is identified, often addressing a business problem or opportunity
- Key activities within the initiation phase include:
- Developing a Business Case which documents the need and proposes solution option
- Conducting a Feasibility Study which assesses whether the proposed solutions are practical and beneficial
- Appointing a Project Manager to oversee the projec
- Identifying Stakeholders which recognizes all parties affected by the project
- This phase concludes with a decision to proceed to detailed planning
Planning Phase
- The project is planned in detail to achieve its objectives
- Key activities include:
- Defining scope, outlining all work required
- Setting objectives that is establishing clear, measurable goals
- Developing a Project Plan that creates schedules, budgets, and resource allocations
- Risk Management Planning that identifies potential risks and mitigation strategies
Project Roadmap
- Risk management planning ensures a comprehensive roadmap is in place
Implementation (Execution) Phase
- Plans are put into action during the execution phase
- Key activities include:
- Executing Project Plan performs tasks as scheduled
- Resource Management that allocates and managing resources effectively
- Quality Assurance that ensures deliverables meet required standards
- Stakeholder Communication that keeps all parties informed of progress. Regular monitoring and adjustments are essential to stay on track
Closing Phase
- In this final phase, the project is formally completed
- Key activities include:
- Delivering Final Products that hands complete deliverables to the client
- Releasing Project Resources that frees up personnel and materials
- Conducting Post-Project Review that evaluates successes and areas for improvement
- Documenting Lessons Learned records insights for future projects, ensuring a smooth transition and valuable feedback for future endeavors
Project Management as a Profession
- Key aspects include:
- Body of knowledge
- Standards
- Professional organizations
Knowledge and Skills
- Expert PMs can potentially move from one industry to another
Project Management Standards
- PMI (Project Management Institute) and IPMA (International Project Management Association) are two major organizations with worldwide impact on project management
PMBOK Knowledge Areas
- Managing Integration ensures all project activities align by developing the project charter, scope statement, and plan to direct, manage, monitor, and control changes effectively
- Managing Scope establishes clear project boundaries through a work breakdown structure (WBS), ensuring tasks are well-defined, verified, and controlled
- Managing Time/Schedule keeps projects on track by defining tasks, sequencing activities, estimating resources and durations, and maintaining schedule control
- Managing Costs optimizes resource allocation by planning, estimating, budgeting, and controlling costs to ensure value creation
- Managing Quality ensures deliverables meet performance standards through quality planning, assurance, and control
- Managing Human Resources focuses on recruiting, developing, and managing the project team to maximize efficiency and productivity
- Managing Communication facilitates clear and structured communication across project participants, managers, and stakeholders through planning, distribution, reporting, and engagement
- Managing Risks identifies, analyzes, and mitigates potential risks, ensuring proactive planning and response to uncertainties
- Managing Procurement oversees vendor selection, contract administration, and closure to ensure smooth procurement processes
- Managing Stakeholders identifies key stakeholders, assesses their influence, and maintains strong relationships to align expectations with project goals
Project Start-Up and Integration
- Project start-up is similar to starting a new organization
- The project leader develops the project infrastructure used to design and execute the project
- The project management team must develop alignment between the major stakeholders during the early phases
Project Scope
- The Project scope defines the project's objectives
- Scope comes from agreement between sponsor and team
- Changes in scope require a defined approval process
Schedule and Time Management
- WBS defines work packages
- Schedules are created based on dependencies and estimated durations
- Software tools may assist in managing schedules
Project Costs
- Develop a budget
- Estimate methods
- Plan cash flow
- Track expenditures
Project Quality
- Define quality standards
- Methods to achieve and measure standards
Human Resources and Communication
- There are two types of team members, Functional Managers who focus on the technology of the project and Process Managers who have expertise in estimating, cost tracking, planning, and scheduling
- Important to identify and manage project team
- Develop and motivate project team
Communication Methods
- Communication plan requires a definition of the audience, method, frequency, and responsible team members
- Teamwork and communication are essential for completing complex project successfully
- Two categories of Communication - Synchronous and Asynchronous
Risk Management
- Risk management requires that you identify, analyze, and manage risks
Procurement
- Contracts and procurement strategies are important
Stakeholder Management
- Stakeholder management requires you to Identify and engage stakeholders
- Maintain a stakeholder register
PMI Process Groups
- Initiating
- Planning
- Executing
- Monitoring & Controlling
- Closing
Scrum Development
- It uses Agile methodology
- It is an iterative approach using sprints (2-4 weeks)
- Key roles include Product Owner, Scrum Master, and the Development Team
The Project Management Office (PMO)
- PMO's align projects with organizational objectives
- PMO's sets project standards
- PMO's provides resources, training, and mentorship
PMO Objectives
- Some PMO objectives include:
- Ensuring projects are aligned with organizational objectives
- Providing templates and procedures for use by project managers
- Providing training and mentorship
- Providing facilitation
- Staying abreast of the latest trends in project management
- Serving as a repository for project reports and lessons learned
Stakeholder Definition
- Stakeholders are people, groups, or organizations impacted by the project
- Stakeholders are individuals who either care about or have a vested interest in your project
- Key stakeholders can make or break the success of a project
Key Stakeholders
- Top Management
- The Project Team
- Your Manager
- Peers
- Resource Manager
- Internal Customers
- External Customers
- Government
- Contractors, Subcontractors, Suppliers
Stakeholder Management
- The Project Team requires you to understand Top Management, The Project Team itself, Your Manager, Peers, Resource Managers, Internal Customers, External Customers, Government, and Contractors, Subcontractors, and Suppliers
Top Management
Important points regarding top management:
- Support from top management helps helps in recruiting the best staff and acquiring necessary resources
- High visibility can enhance the project manager's professional standing
- Failure is highly visible and costly, especially for large projects
Dealing with Top Management
- Develop in-depth plans with major milestones for approval
- Ask about their information reporting needs and frequency
- Create a scheduled status reporting methodology
- Keep them informed about project risks and potential impacts
The Project Team
- The team includes people dedicated full-time or borrowed part-time
- Project managers must provide leadership, direction, and support
- Borrowed team members have other priorities
- Juggling multiple projects may cause missed deadlines
- Personality conflicts can arise
- Missed deadlines might be discovered too late Strategies for effective management:
- Involve team members in project planning
- Meet privately and informally (e.g., lunch or coffee)
- Be available for concerns anytime
- Encourage teamwork and cooperation
- Conduct project performance reviews
Manager and Reporting
- The boss decides the project assignment and available resources
- Understand how your performance will be measured
- Ask for clarification when directions are unclear
- Develop an acceptable reporting schedule
- Communicate frequently
Peers
- Peers are Colleagues at the same organizational level that may or may not be part of the project
- There's limited control over peers
- It is possible to experience political maneuvering or sabotage
- One should be aware of potential personality or technical conflicts
- Envy of peers who wanted to lead the project can be a factor
- They can give conflicting instructions from different managers
- Secure top management's support to empower you as the project manager
- Confront dysfunctional behaviors directly
- Ask for full peer support and schedule frequent review meetings
- Set clear goals and performance standards
Resource Managers
- They control resources that project managers need
- Important to ensure access to the best staff and equipment
- Poor relationships may result in resource limitations
Internal Customers
- Individuals within the organization who are customers for projects that meet the needs of internal demands
- A challenge is the lack of clarity about precisely what the customer wants
- Lack of documentation is common
- Watch out for having insufficient knowledge of customer operations
- Avoid unrealistic deadlines, budgets, or specifications
External Customers
- These are typical customers when projects could be marketed to outside customers
Government
- In regulated industries (pharmaceutical, banking, military), project managers deal with various government levels (municipal, provincial, federal, international)
Contractors, Subcontractors, and Suppliers
- Stakeholders include external experts or vendors providing services/materials
- Watch out for work quality issues
- Avoid cost overruns and schedule delays
- Effective conflict management and negotiation skills are beneficial
- Careful monitoring of supplier and contractor performance is important
- Proactive risk management to avoid disruptions
Politics
- Project managers have direct control over very few things; therefore their ability to influence others is essential
- Steps to be a good project politician:
- Assess the Environment by identifying all the relevant stakeholders
- Identify Goals
- Define the Problems to fully understand the situation
Culture
- When project stakeholders do not share a common culture, project management must adapt its organizations and work processes to cope with cultural differences
- 3 major aspects of cultural difference that can affect a project:
- Communication is the most visible manifestation of culture
- Negotiation is the greatest barrier to communication
- Decision Making
Managing Stakeholder Process
- Management involves identifying, analyzing, and engaging all individuals or groups with a vested interest in the project
- Stakeholder management ensures alignment of interests, mitigates conflicts, and maintains project momentum by balancing diverse expectations and influences.
Relationships
- Include those impacted by the project and those who can impact the project.
- Begin building strong relationships early.
- Analyze Stakeholders to assess key participants, understand their problems, and define roles
- Assess Influence by measuring each stakeholder's influence on the project by understanding them
- Stakeholder success means you understood their Expectations
Project Initiation
- The key purpose include:
- Define business problem or opportunity
- Create a business case
- Form project team
Business Case
- Problem or opportunity definition
- Alignment with organizational objectives
- Analysis of benefits, costs, and risks
Financial Considerations
- Net Present Value (NPV)
- Rate of Return (ROI)
- Payback Analysis
Decision Making
- A weighted decision matri allows decision makers to structure and solve their problems by:
- Specifying and prioritizing their needs with a list a criteria
- Evaluating, rating, and comparing the different solutions
- Selecting the best matching solution
- A decision matrix array presents on one axis a list of alternatives which are evaluated regarding a list of criteria, weighted depending on their importance
Financial metrics
- NPV - is Net Present Value
- ROI is Return on investment, and is a performance measure to compare efficiency of an investments
Project Charter
- Provides approval to proceed to planning
SMART and project Objectives
- Projects must be Specific, Measurable, Acceptable, Realistic, and Time based
Project Content
- Typical contents include:
- Identification section
- Project purpose
- Measurable objectives
- High-level requirements
- Constraints, assumptions, risks
- Budget
- Stakeholder list
- Approvals