What is the main focus of the Perform Integrated Change Control process?
Managing project changes
Which diagram illustrates the flow of data in the Close Project or Phase process?
Figure 4-15
What is the purpose of the Requirements Traceability Matrix?
Link requirements to their origin and trace through to delivery
Which process involves creating a Data Flow Diagram in the project scope management?
Plan Scope Management
What does the Context Diagram represent in project management?
The overall scope of the project and its boundaries
Which process primarily deals with closing a project or phase?
Close Project or Phase
Which of the following is NOT a component of the Project Management Plan that should be closed during the Closing Process Group?
Project risk register
Which of the following project documents should be updated during the Closing Process Group?
Lessons learned register
Which of the following is the primary purpose of the Closing Process Group?
To complete and verify the entire project or project phase
Which of the following is NOT a typical output of the Close Project or Phase process?
Planned risk responses
Which of the following is a key consideration when closing a project or phase?
Verifying that all work is complete
What is the primary output of the Close Project or Phase process?
Final product, service, or result transition
What process involves reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents, and the project management plan?
Perform Integrated Change Control
Which part of the project management process deals with the authority to start a project?
Develop Project Charter
In which process are tools like expert judgment, data analysis, and meetings commonly used?
Direct and Manage Project Work
Which process is focused on creating, maintaining, and sharing knowledge based on both the project successes and failures?
Manage Project Knowledge
What is the primary focus of the Close Project or Phase process?
Handing over completed deliverables
Which process involves comparing actual performance against the planned performance, analyzing variances, and taking corrective actions as needed?
Monitor and Control Project Work
This quiz covers the inputs, tools & techniques, and outputs involved in the Integrated Change Control process and the Close Project or Phase process. It includes data flow diagrams for better understanding.