What is the primary objective of the joint inspections by Open Line and Construction organisation or Rly PSUs within 15 days of commissioning of Signalling work?
What is the primary objective of the joint inspections by Open Line and Construction organisation or Rly PSUs within 15 days of commissioning of Signalling work?
What is the role of Sr.DSTE of the division in the commissioning of signalling work?
What is the role of Sr.DSTE of the division in the commissioning of signalling work?
What is included in the completion documents and maintenance accessories handed over to the division?
What is included in the completion documents and maintenance accessories handed over to the division?
Why is it essential to have a sighting committee certificate?
Why is it essential to have a sighting committee certificate?
Signup and view all the answers
What is the primary purpose of the 'As Laid' Cable route plan?
What is the primary purpose of the 'As Laid' Cable route plan?
Signup and view all the answers
What is the significance of the wire counts details in case of RRI?
What is the significance of the wire counts details in case of RRI?
Signup and view all the answers
What is the purpose of the cable insulation test record?
What is the purpose of the cable insulation test record?
Signup and view all the answers
Why is it essential to have a track circuit bonding plan?
Why is it essential to have a track circuit bonding plan?
Signup and view all the answers
What is the primary purpose of FORM VIII, as stated in rule 5(1)(h)?
What is the primary purpose of FORM VIII, as stated in rule 5(1)(h)?
Signup and view all the answers
Who is responsible for forwarding the commissioning information to the Commissioner of Railway Safety?
Who is responsible for forwarding the commissioning information to the Commissioner of Railway Safety?
Signup and view all the answers
What is the purpose of obtaining approval from the Commissioner of Railway Safety?
What is the purpose of obtaining approval from the Commissioner of Railway Safety?
Signup and view all the answers
What is the primary purpose of the Rules laid down in the Indian Railway Act?
What is the primary purpose of the Rules laid down in the Indian Railway Act?
Signup and view all the answers
Who is responsible for issuing a circular to notify railway officials before opening works?
Who is responsible for issuing a circular to notify railway officials before opening works?
Signup and view all the answers
What is required to be obtained before starting any work that affects the running line?
What is required to be obtained before starting any work that affects the running line?
Signup and view all the answers
What is the purpose of notifying the Operating Department about the commencement of signalling work?
What is the purpose of notifying the Operating Department about the commencement of signalling work?
Signup and view all the answers
What is the consequence of deviating from approved plans, drawings, and specifications?
What is the consequence of deviating from approved plans, drawings, and specifications?
Signup and view all the answers
What is the purpose of the General Rules and Subsidiary Rules for all Open Line Railways?
What is the purpose of the General Rules and Subsidiary Rules for all Open Line Railways?
Signup and view all the answers
What is the significance of the Rules for Opening of a Railway or section of a Railway for the public carriage of passengers?
What is the significance of the Rules for Opening of a Railway or section of a Railway for the public carriage of passengers?
Signup and view all the answers
What is the purpose of the Indian Railway Schedule of Dimensions?
What is the purpose of the Indian Railway Schedule of Dimensions?
Signup and view all the answers
What is the primary responsibility of the Signal Engineer incharge before commencing work?
What is the primary responsibility of the Signal Engineer incharge before commencing work?
Signup and view all the answers
What is the purpose of the Signal Engineer incharge's frequent inspections?
What is the purpose of the Signal Engineer incharge's frequent inspections?
Signup and view all the answers
What is the significance of the sanction of the Commissioner of Railway Safety or Principal Chief Signal and Telecom Engineer?
What is the significance of the sanction of the Commissioner of Railway Safety or Principal Chief Signal and Telecom Engineer?
Signup and view all the answers
What is the purpose of the Signal Engineer incharge's progress reports?
What is the purpose of the Signal Engineer incharge's progress reports?
Signup and view all the answers
Why is the sighting committee certificate essential?
Why is the sighting committee certificate essential?
Signup and view all the answers
What is the responsibility of the Engineer incharge regarding expenditure?
What is the responsibility of the Engineer incharge regarding expenditure?
Signup and view all the answers
What is the purpose of the Engineer incharge's involvement in the preparation of the Station working Rules?
What is the purpose of the Engineer incharge's involvement in the preparation of the Station working Rules?
Signup and view all the answers
What is the significance of the detailed estimate for the work?
What is the significance of the detailed estimate for the work?
Signup and view all the answers
What is the primary purpose of the Railway Safety Certificate?
What is the primary purpose of the Railway Safety Certificate?
Signup and view all the answers
Under what circumstances is the Railway Safety Certificate required to be signed?
Under what circumstances is the Railway Safety Certificate required to be signed?
Signup and view all the answers
What is the purpose of the description of work in the Railway Safety Certificate?
What is the purpose of the description of work in the Railway Safety Certificate?
Signup and view all the answers
Who signs the Railway Safety Certificate on behalf of the Railway?
Who signs the Railway Safety Certificate on behalf of the Railway?
Signup and view all the answers
What is the significance of the Plan No. in the Railway Safety Certificate?
What is the significance of the Plan No. in the Railway Safety Certificate?
Signup and view all the answers
What is the purpose of the Signal Engineering Manual in the Railway Safety Certificate?
What is the purpose of the Signal Engineering Manual in the Railway Safety Certificate?
Signup and view all the answers
What is the significance of the letter number and date in the Railway Safety Certificate?
What is the significance of the letter number and date in the Railway Safety Certificate?
Signup and view all the answers
What is the purpose of the certification in the Railway Safety Certificate?
What is the purpose of the certification in the Railway Safety Certificate?
Signup and view all the answers
What is the primary purpose of the Commissioner of Railway Safety's certificate?
What is the primary purpose of the Commissioner of Railway Safety's certificate?
Signup and view all the answers
What is the validity of the sanction accorded by the Commissioner of Railway Safety?
What is the validity of the sanction accorded by the Commissioner of Railway Safety?
Signup and view all the answers
What is the purpose of the communication 'Reference Sanction No………………….dated ………………'?
What is the purpose of the communication 'Reference Sanction No………………….dated ………………'?
Signup and view all the answers
Who is responsible for submitting the safety certificate to the Commissioner of Railway Safety?
Who is responsible for submitting the safety certificate to the Commissioner of Railway Safety?
Signup and view all the answers
What is the consequence of deviating from the approved plans, drawings, and specifications?
What is the consequence of deviating from the approved plans, drawings, and specifications?
Signup and view all the answers
What is the primary purpose of the inspection by the Commissioner of Railway Safety?
What is the primary purpose of the inspection by the Commissioner of Railway Safety?
Signup and view all the answers
What is the significance of the date of sanction in the certificate?
What is the significance of the date of sanction in the certificate?
Signup and view all the answers
What is the purpose of the 'Certificate signed' statement in the communication?
What is the purpose of the 'Certificate signed' statement in the communication?
Signup and view all the answers
What is the primary requirement for the General Manager of a Government railway to sanction the use of a new locomotive or rolling stock?
What is the primary requirement for the General Manager of a Government railway to sanction the use of a new locomotive or rolling stock?
Signup and view all the answers
What is the primary purpose of FORM VIII, as stated in rule 5(1)(h)?
What is the primary purpose of FORM VIII, as stated in rule 5(1)(h)?
Signup and view all the answers
What information is required in the section 'Names of Station' in FORM VIII?
What information is required in the section 'Names of Station' in FORM VIII?
Signup and view all the answers
What is the purpose of the calculations and stress sheets in the proposal for sanction of a new locomotive or rolling stock?
What is the purpose of the calculations and stress sheets in the proposal for sanction of a new locomotive or rolling stock?
Signup and view all the answers
What is the primary purpose of the PCSTE sanction?
What is the primary purpose of the PCSTE sanction?
Signup and view all the answers
What is the significance of the 'LENGTH: 9.19 km' in FORM VIII?
What is the significance of the 'LENGTH: 9.19 km' in FORM VIII?
Signup and view all the answers
Who signs the certificate on Form Annexure: 9-A6 in the proposal for sanction of a new locomotive or rolling stock?
Who signs the certificate on Form Annexure: 9-A6 in the proposal for sanction of a new locomotive or rolling stock?
Signup and view all the answers
Who is responsible for forwarding the commissioning information to the Commissioner of Railway Safety?
Who is responsible for forwarding the commissioning information to the Commissioner of Railway Safety?
Signup and view all the answers
What is the purpose of the certificate referred to in clause (vii) of Para 9.4.2(b)?
What is the purpose of the certificate referred to in clause (vii) of Para 9.4.2(b)?
Signup and view all the answers
Who is responsible for issuing the communication to the designated address after the work has been opened and the safety certificate has been signed?
Who is responsible for issuing the communication to the designated address after the work has been opened and the safety certificate has been signed?
Signup and view all the answers
What is the primary requirement for the railway administration other than the Government railway to use a new locomotive or rolling stock?
What is the primary requirement for the railway administration other than the Government railway to use a new locomotive or rolling stock?
Signup and view all the answers
What is the purpose of the gauge specified in FORM VIII?
What is the purpose of the gauge specified in FORM VIII?
Signup and view all the answers
What is the duration of the validity of the PCSTE sanction?
What is the duration of the validity of the PCSTE sanction?
Signup and view all the answers
What is the purpose of the safety certificate?
What is the purpose of the safety certificate?
Signup and view all the answers
What is the purpose of the provisional speed certificate or final speed certificate in the proposal for sanction of a new locomotive or rolling stock?
What is the purpose of the provisional speed certificate or final speed certificate in the proposal for sanction of a new locomotive or rolling stock?
Signup and view all the answers
What is the role of the 'SECTION: LAKSHMIKANTPUR-KULPI' in FORM VIII?
What is the role of the 'SECTION: LAKSHMIKANTPUR-KULPI' in FORM VIII?
Signup and view all the answers
Who is responsible for submitting the safety certificate to the Principal Chief Signal & Telecommunication Engineer?
Who is responsible for submitting the safety certificate to the Principal Chief Signal & Telecommunication Engineer?
Signup and view all the answers
What is the significance of the 'Non-Interlocked' column in FORM VIII?
What is the significance of the 'Non-Interlocked' column in FORM VIII?
Signup and view all the answers
What is the purpose of the cost of modification to signaling and telecommunication installations in the proposal for sanction of a new locomotive or rolling stock?
What is the purpose of the cost of modification to signaling and telecommunication installations in the proposal for sanction of a new locomotive or rolling stock?
Signup and view all the answers
Who is responsible for completing FORM VIII?
Who is responsible for completing FORM VIII?
Signup and view all the answers
What is the purpose of the letter from the Principal Chief Signal & Telecommunication Engineer to the designated person?
What is the purpose of the letter from the Principal Chief Signal & Telecommunication Engineer to the designated person?
Signup and view all the answers
What is the primary purpose of the sanction of the Central Government for introduction of the locomotives or rolling stock?
What is the primary purpose of the sanction of the Central Government for introduction of the locomotives or rolling stock?
Signup and view all the answers
What is the consequence of not submitting the safety certificate to the Principal Chief Signal & Telecommunication Engineer?
What is the consequence of not submitting the safety certificate to the Principal Chief Signal & Telecommunication Engineer?
Signup and view all the answers
Who is responsible for issuing the reconnection memo after the completion of the work?
Who is responsible for issuing the reconnection memo after the completion of the work?
Signup and view all the answers
What is the primary responsibility of the Dy.CSTE Concerned?
What is the primary responsibility of the Dy.CSTE Concerned?
Signup and view all the answers
Who is required to associate themselves during the work execution stage of new/alteration works?
Who is required to associate themselves during the work execution stage of new/alteration works?
Signup and view all the answers
What is the requirement for undertaking the work of trenching and cable laying?
What is the requirement for undertaking the work of trenching and cable laying?
Signup and view all the answers
What is the requirement for power supply equipment installed by construction organisation or Rly PSUs?
What is the requirement for power supply equipment installed by construction organisation or Rly PSUs?
Signup and view all the answers
What tests are required to be carried out by the Open Line organisation before permitting the Executing agency to commence work?
What tests are required to be carried out by the Open Line organisation before permitting the Executing agency to commence work?
Signup and view all the answers
What is the significance of the Site Inspection Register?
What is the significance of the Site Inspection Register?
Signup and view all the answers
What is the requirement for working in existing location boxes?
What is the requirement for working in existing location boxes?
Signup and view all the answers
What is the purpose of obtaining approval from the PCSTE/OL for power supply equipment?
What is the purpose of obtaining approval from the PCSTE/OL for power supply equipment?
Signup and view all the answers
When is the prior approval of the Commissioner of Railway Safety/PCSTE required?
When is the prior approval of the Commissioner of Railway Safety/PCSTE required?
Signup and view all the answers
Who submits the Safety Certificate on the prescribed form (Annexure: 9-A2)?
Who submits the Safety Certificate on the prescribed form (Annexure: 9-A2)?
Signup and view all the answers
What does the Engineer-incharge do before signing the Safety Certificate?
What does the Engineer-incharge do before signing the Safety Certificate?
Signup and view all the answers
What happens if the Commissioner of Railway Safety decides not to inspect the work prior to opening?
What happens if the Commissioner of Railway Safety decides not to inspect the work prior to opening?
Signup and view all the answers
Who may propose to inspect the works in accordance with the application made initially?
Who may propose to inspect the works in accordance with the application made initially?
Signup and view all the answers
What is required before obtaining the prior approval of the Commissioner of Railway Safety/PCSTE?
What is required before obtaining the prior approval of the Commissioner of Railway Safety/PCSTE?
Signup and view all the answers
Who should be associated when the increase in speed of a locomotive or rolling stock is contemplated over the maximum sanctioned speed?
Who should be associated when the increase in speed of a locomotive or rolling stock is contemplated over the maximum sanctioned speed?
Signup and view all the answers
What is the purpose of the Joint Safety Certificate?
What is the purpose of the Joint Safety Certificate?
Signup and view all the answers
Who signs the Joint Safety Certificate on behalf of the Railway?
Who signs the Joint Safety Certificate on behalf of the Railway?
Signup and view all the answers
What is the purpose of the speed restrictions and conditions mentioned in the Joint Safety Certificate?
What is the purpose of the speed restrictions and conditions mentioned in the Joint Safety Certificate?
Signup and view all the answers
Why is the Chief Electrical Engineer required to sign the Joint Safety Certificate in certain cases?
Why is the Chief Electrical Engineer required to sign the Joint Safety Certificate in certain cases?
Signup and view all the answers
What is the purpose of noting the maximum speed of the locomotive or rolling stock in the Joint Safety Certificate?
What is the purpose of noting the maximum speed of the locomotive or rolling stock in the Joint Safety Certificate?
Signup and view all the answers
What is the primary purpose of the Railway Safety Certificate?
What is the primary purpose of the Railway Safety Certificate?
Signup and view all the answers
What is the significance of the Signal Engineering Manual in the Railway Safety Certificate?
What is the significance of the Signal Engineering Manual in the Railway Safety Certificate?
Signup and view all the answers
Under what circumstances is the Railway Safety Certificate required to be signed?
Under what circumstances is the Railway Safety Certificate required to be signed?
Signup and view all the answers
What is the purpose of the description of work in the Railway Safety Certificate?
What is the purpose of the description of work in the Railway Safety Certificate?
Signup and view all the answers
Who signs the Railway Safety Certificate on behalf of the Railway?
Who signs the Railway Safety Certificate on behalf of the Railway?
Signup and view all the answers
What is the significance of the Plan No. in the Railway Safety Certificate?
What is the significance of the Plan No. in the Railway Safety Certificate?
Signup and view all the answers
What is the purpose of the certification in the Railway Safety Certificate?
What is the purpose of the certification in the Railway Safety Certificate?
Signup and view all the answers
What is the significance of the letter number and date in the Railway Safety Certificate?
What is the significance of the letter number and date in the Railway Safety Certificate?
Signup and view all the answers
Study Notes
General Instructions for Commissioning of Signalling Installations
- The safety of the travelling public is ensured by rules laid down in the Indian Railway Act, General Rules & Subsidiary rules, and Rules for Opening of a Railway or section of a Railway for public carriage of passengers.
- The rules provide for legal authorization to be obtained for any work affecting the running line before starting or bringing it into use, and before opening a new section of a line for public traffic.
Notification to Railway Officials
- No signalling work affecting the running of trains or working of traffic at a station shall be brought into use until staff of all concerned Departments have been notified.
- Timely intimation of the date of commencement of work, duration of work, arrangements for working of trains during the progress of the work, and date of opening of work shall be given to the Operating Department.
Approved Plans and Specifications
- All works shall be carried out strictly in accordance with approved plans, standard drawings, and specifications.
- Deviations, if any, shall have the prior approval of the Principal Chief Signal and Telecommunication Engineer.
Joint Inspections and Deficiencies
- Within 15 days of commissioning of Signalling work, another joint inspection shall be undertaken by Open Line and Construction organisation or Rly PSUs.
- Deficiencies noted during the inspection shall be listed in two categories: Category-A (to be complied before handing over) and Category-B (to be complied after handing over with target dates mutually agreed in writing).
Responsibilities of Sr.DSTE
- The Sr.DSTE shall ensure that Open line staff actively associate with the construction activities, particularly in the areas of site plan, cable route plan, signal locations, power supply sources, and cable testing.
Handing Over of Maintenance
- While handing over the maintenance of the works executed by the construction organisation or Rly PSUs, the following completion documents and maintenance accessories shall be handed over to the division:
- Approved SIP of the station
- Completion wiring diagrams
- Control Table/Selection Table/Locking Table/Route control chart and Dog-Chart
- Panel diagram/VDU diagrams (in case of panel or EI installations)
- Sighting Committee certificate
- Approved as well as updated ‘As Laid’ Cable route plan
- Cable termination plan/diagrams
- Wire counts details
- Power supply arrangement plan
- Cable insulation test record
- Signal infringements at the station
- Track circuit bonding plan
Responsibilities of Engineer Incharge
- The Signal Engineer incharge shall ensure that no work is commenced without:
- Proper men and materials being available
- Approved signalling plans, locking tables, and diagrams
- Sanction of Commissioner of Railway Safety or Principal Chief Signal & Telecom Engineer
- Station working Rules and temporary working instructions
- Sanction to the detailed estimate for the work with necessary allotment of Funds
- The Engineer incharge shall also be responsible for:
- Proper and efficient execution of works
- Frequent inspections and issue of detailed instructions
- Satisfactory progress of work and submission of progress reports
- Correct booking and control over expenditure within allotted funds
- Assistance in preparation of Station working Rules
- Arrangement for sighting of new Signals by sighting committee
- Fixing a date for opening jointly with other concerned officials and notifying the same to all concerned
Approval and Sanction for New Locomotives and Rolling Stock
- The General Manager of a Government railway can sanction the use of new locomotives or rolling stock already introduced by the Central Government under Para 9.4.1.
- Railway administrations other than Government railways require approval from the Central Government through the Commissioner for use of new locomotives or rolling stock.
Requirements for Sanction
- The proposal for sanction must be accompanied by:
- Diagrams showing axle loads, wheel spacing, length over buffers, and other principal dimensions of the rolling stock.
- Provisional or final speed certificate issued by the Research, Design, and Standards Organisation.
- Sanction of the Central Government for introduction of the locomotives or rolling stock or increase in sanctioned maximum speed.
- Calculations and stress sheets showing conclusions, external forces, and stresses produced on bridges and tracks.
- Cost of modifications to signaling and telecommunication installations.
- Estimate of cost of improvements in existing structures or tracks.
- Certificate signed by the Chief Engineer, Chief Mechanical Engineer, and Chief Electrical Engineer.
Conditions for Certificate
- The certificate must indicate that the speed certified does not exceed the limits laid down by the Research, Designs, and Standard Organisation.
- The certificate must specify the maximum number of motive power units proposed to be coupled together for multiple operation.
Procedure for Commissioning of Signalling Installations
- The Commissioner of Railway Safety issues a sanction for the work, which is valid for a specified period.
- The work can be opened for public carriage of passengers after inspection by the Commissioner of Railway Safety or on receipt of a safety certificate.
- The Commissioner of Railway Safety may inspect the work prior to its opening for public carriage of passengers.
Station Machinery and Interlocking
- Station machinery includes interlocking, signals, and block systems.
- The Sr.DSTE analyzes signal failures and takes corrective action.
Open Line Inspectors and Officers
- Open Line inspectors and officers associate themselves with the work execution stage to acquaint themselves with the works and point out deficiencies.
- Observations are jointly agreed and recorded in the "Site Inspection Register".
Joint Safety Certificate
- The Joint Safety Certificate is required for new types of locomotives or rolling stock.
- It certifies that it is safe to run a specific number of units on a designated section of the railway at a maximum speed.
Speed Restrictions and Conditions
- The certificate includes speed restrictions and special conditions for the operation of the locomotives or rolling stock.
- The speed restrictions include the nature of the restriction and the section of the railway where it applies.
Sign-Off Process
- The Chief Operating Manager, Chief Signalling and Telecommunications Engineer, and other designated officials must sign the certificate.
- The Commissioner of Railway Safety/PCSTE may inspect the works before opening and provide prior approval for any deviations from the approved plan.
Safety Certificate
- The Safety Certificate is submitted by the Engineer-in-charge before opening the works.
- The Engineer-in-charge must test the new works, ensure they are installed correctly, and confirm they can be opened to the public without endangering safety.
- The Safety Certificate must be signed before opening temporary or new works if the Commissioner of Railway Safety does not inspect the work prior to opening.
Requirements for Safety Certificate
- The Safety Certificate must confirm that:
- The schedule of dimensions has not been infringed.
- Engineering work has been carried out in accordance with the plan.
- The weight of rails, strength of bridges, and general structural character of the works meet prescribed requirements.
- Signalling and Interlocking have been carried out in accordance with the Signalling Plan and Signal Engineering Manual.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Learn about the rules and regulations governing the commissioning of signalling installations in Indian Railways, ensuring the safety of passengers.