4BE3.5 U4 C2 Obj2 EMH
72 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

EASY What is the purpose of maintaining an air cushion in the expansion tank?

  • To reduce noise and vibration in the system
  • To increase the pressure in the system
  • To accommodate the expanded water during warmup (correct)
  • To prevent the tank from rusting
  • When should the stop valve on the boiler outlet be opened?

  • When the system is at a high temperature
  • When the boiler is fully fired
  • When the boiler water reaches the temperature of the supply main (correct)
  • When the return line is fully open
  • What is the recommended procedure when warming up a cold boiler?

  • Crack open the outlet valve, then slowly open the inlet valve (correct)
  • Open the outlet valve fully, then crack open the inlet valve
  • Open both valves simultaneously
  • Fully open the inlet valve, then slowly open the outlet valve
  • What should be done after warming up the boiler?

    <p>Switch to low fire until sufficiently warmed up</p> Signup and view all the answers

    What is the requirement for using the alternative method of warming up a cold boiler?

    <p>The on-line boilers have sufficient capacity to heat the extra boiler</p> Signup and view all the answers

    Why is it important to plan ahead for heating loads?

    <p>To have standby boilers warmed up prior to being required</p> Signup and view all the answers

    What is the primary objective of the Power Engineer during the startup of a hot water boiler?

    <p>To monitor all aspects of startup</p> Signup and view all the answers

    What should be done before starting the boiler?

    <p>Prepare the boiler plant auxiliaries according to site-specific procedures</p> Signup and view all the answers

    Why is it necessary to wait for at least 5 minutes after shutting the pilot and main gas valves?

    <p>To allow the furnace to purge naturally</p> Signup and view all the answers

    What is the purpose of the draft fan in some boilers?

    <p>To provide a mechanical purge</p> Signup and view all the answers

    What is the recommended reference for heating boiler operating practices?

    <p>ASME VI Recommended Rules for the Care and Operation of Heating Boilers</p> Signup and view all the answers

    What should be done to the boiler control switch before starting the boiler?

    <p>Turn it to the 'off' position</p> Signup and view all the answers

    What is the purpose of closing the main disconnect switch?

    <p>To supply power to the boiler</p> Signup and view all the answers

    What should be done if the boiler is equipped with a high-low firing rate control?

    <p>Place the boiler on low fire</p> Signup and view all the answers

    What should be done with the firing rate control when starting the boiler?

    <p>Place the control in manual low fire</p> Signup and view all the answers

    What happens after the air damper goes to the low fire position in the ignition sequence?

    <p>The electrodes in the igniter spark</p> Signup and view all the answers

    Why should the water temperature be raised slowly when starting the boiler?

    <p>To avoid overheating the boiler</p> Signup and view all the answers

    What should be performed while the boiler is warming up?

    <p>Both operating and safety limit checks</p> Signup and view all the answers

    What should be checked after the burner shuts down?

    <p>Both the water pressure on the tridicator gauge and the water level in the expansion tank</p> Signup and view all the answers

    What is the purpose of the try lever and pop tests on the safety relief valve?

    <p>To check for evidence of leaking</p> Signup and view all the answers

    What is the term used to describe adding a previously non-operating boiler to a system that is already in operation?

    <p>Cutting in</p> Signup and view all the answers

    What should be done with the valve in the connecting line between the boiler and the expansion tank when cutting in a boiler?

    <p>Crack open the valve</p> Signup and view all the answers

    Why should the stop valves in the supply and return lines to the boiler be closed during warmup when cutting in a boiler?

    <p>To allow the boiler to warm up slowly</p> Signup and view all the answers

    MEDIUM What should be entered in the log book after starting the boiler?

    <p>The date and time of startup, observed irregularities and corrective actions taken, and other relevant information</p> Signup and view all the answers

    What should be performed before starting a hot water boiler?

    <p>Preparing the boiler plant auxiliaries according to site-specific procedures</p> Signup and view all the answers

    Why is it necessary to wait for at least 5 minutes after shutting the pilot and main gas valves?

    <p>To allow the furnace to purge naturally</p> Signup and view all the answers

    What should be done if the boiler is equipped with a high-low firing rate control?

    <p>Place the boiler on low fire</p> Signup and view all the answers

    What should be reviewed before starting a hot water boiler?

    <p>The manufacturer recommendations for burner and boiler startup</p> Signup and view all the answers

    What is the purpose of closing the main disconnect switch?

    <p>To supply power to the boiler</p> Signup and view all the answers

    What should be done after shutting the pilot and main gas valves?

    <p>Wait for at least 5 minutes to allow the furnace to purge naturally</p> Signup and view all the answers

    What should be done with the boiler control switch before starting the boiler?

    <p>Place it in the 'off' position</p> Signup and view all the answers

    Why should the site-specific standard operating procedures be followed?

    <p>Because they are site-specific and necessary for safe boiler operation</p> Signup and view all the answers

    What should be done first when starting a boiler?

    <p>Turn the boiler control switch to the 'on' or 'start' position</p> Signup and view all the answers

    What happens after the pilot ignition trial is over?

    <p>The main burner safety shut-off valves open</p> Signup and view all the answers

    Why is it important to raise the water temperature slowly?

    <p>To prevent leaks in the system</p> Signup and view all the answers

    What should be checked frequently while the boiler is warming up?

    <p>The burner for leaks</p> Signup and view all the answers

    What should be done with the valve in the connecting line between the boiler and the expansion tank when cutting in a boiler?

    <p>Crack it open and let the pressure equalize</p> Signup and view all the answers

    What should be done with the firing rate control if the boiler is equipped with a fully modulating firing rate control?

    <p>Place it in auto</p> Signup and view all the answers

    What should be done before increasing the fuel input?

    <p>Warming up the boiler and the heating system to normal operating temperature and pressure</p> Signup and view all the answers

    What should be performed while the boiler is warming up?

    <p>Operating and safety limit checks</p> Signup and view all the answers

    What should be entered in the log book after starting the boiler?

    <p>All of the above</p> Signup and view all the answers

    What is the term used to describe adding a previously non-operating boiler to a system that is already in operation?

    <p>Cutting in</p> Signup and view all the answers

    Why is it essential to have sufficient space in the expansion tank?

    <p>To accommodate the expanded water produced during warmup.</p> Signup and view all the answers

    What should be done when the boiler water reaches the temperature of the water in the supply main?

    <p>Open the stop valve on the boiler outlet slightly.</p> Signup and view all the answers

    What is the alternative method of warming up a cold boiler?

    <p>Crack open the outlet valve, then slowly open the inlet valve.</p> Signup and view all the answers

    What should be done with the boiler after it has been warmed up?

    <p>Switch to 'low fire' or 'automatic' as applicable.</p> Signup and view all the answers

    What is the importance of planning ahead for heating loads?

    <p>To ensure that standby boilers are warmed up prior to being required.</p> Signup and view all the answers

    What is the requirement for using the alternative method of warming up a cold boiler?

    <p>The on-line boilers must have sufficient capacity to heat the extra boiler.</p> Signup and view all the answers

    What is the primary concern when warming up a cold boiler using the alternative method?

    <p>Establishing flow through the boiler without causing shock to the system</p> Signup and view all the answers

    What is the purpose of opening the stop valve on the boiler outlet slightly when the boiler water reaches system temperature?

    <p>To establish flow through the boiler and prevent shock to the system</p> Signup and view all the answers

    Why is it necessary to have standby boilers warmed up prior to being required?

    <p>To plan ahead for heating loads and ensure sufficient capacity</p> Signup and view all the answers

    What is the primary benefit of maintaining an air cushion in the expansion tank?

    <p>To accommodate the expanded water produced during warmup</p> Signup and view all the answers

    What is the recommended procedure when the boiler reaches system temperature using the alternative method?

    <p>Opening the valve in the return line slowly</p> Signup and view all the answers

    What is the primary consideration when using the alternative method of warming up a cold boiler?

    <p>Establishing flow through the boiler without causing shock to the system</p> Signup and view all the answers

    What is the primary purpose of the 5-minute waiting period after shutting the pilot and main gas valves?

    <p>To allow the furnace to purge naturally</p> Signup and view all the answers

    Why is it essential to follow the manufacturer's recommendations for burner and boiler startup?

    <p>To ensure a safe and proper startup</p> Signup and view all the answers

    What should be done with the boiler control switch before starting the boiler?

    <p>It should be in the 'off' position</p> Signup and view all the answers

    Why is it necessary to review the site-specific standard operating procedures before starting a hot water boiler?

    <p>To ensure a safe and efficient startup</p> Signup and view all the answers

    What should be done with the main disconnect switch before starting the boiler?

    <p>It should be closed to supply power to the boiler</p> Signup and view all the answers

    What is the primary purpose of the expansion tank in a hot water boiler system?

    <p>To provide a buffer for sudden changes in pressure</p> Signup and view all the answers

    Why is it necessary to open the boiler return and supply valves before starting the boiler?

    <p>To allow for the circulation of treated water</p> Signup and view all the answers

    What should be done with the pilot flame after it has been established?

    <p>It should be used to ignition the main burner</p> Signup and view all the answers

    What is the correct sequence of events in the ignition sequence of a boiler?

    <p>The forced draft fan starts, the air damper fully opens, the boiler purges, the air damper goes to low fire, and the electrodes spark.</p> Signup and view all the answers

    What should be done with the valve in the connecting line between the boiler and the expansion tank when cutting in a boiler?

    <p>The valve should be cracked open and then fully opened once the pressures equalize.</p> Signup and view all the answers

    What should be done with the stop valves in the supply and return lines to the boiler during warmup when cutting in a boiler?

    <p>They should be closed.</p> Signup and view all the answers

    What should be done with the firing rate control if the boiler is equipped with a fully modulating firing rate control?

    <p>It should be placed in auto.</p> Signup and view all the answers

    What should be performed while the boiler is warming up?

    <p>The operating and safety limit checks should be performed.</p> Signup and view all the answers

    What should be done after the burner shuts down?

    <p>The water pressure should be checked on the tridicator gauge.</p> Signup and view all the answers

    What should be entered in the log book after starting the boiler?

    <p>All of the above.</p> Signup and view all the answers

    What is the purpose of raising the water temperature slowly when starting the boiler?

    <p>To prevent thermal shock to the boiler.</p> Signup and view all the answers

    What should be checked frequently while the boiler is warming up?

    <p>All of the above.</p> Signup and view all the answers

    What is the purpose of the try lever and pop tests on the safety relief valve?

    <p>To ensure the valve is functioning properly.</p> Signup and view all the answers

    Study Notes

    Startup Preparation

    • Prepare boiler plant auxiliaries according to site-specific procedures.
    • Review manufacturer recommendations for burner and boiler startup.

    Boiler Startup Sequence

    • Open boiler return and supply valves, if applicable.
    • Ensure boiler control switch is in the “off” position.
    • Close main disconnect switch to supply power to the boiler.

    Furnace Purge and Ignition

    • If the boiler has a gas-fired atmospheric burner, allow 5 minutes for natural purge.
    • Light the continuous pilot burner according to manufacturer's instructions.
    • Open main burner test firing valve.

    Main Burner Ignition

    • Place boiler on low fire if equipped with high-low firing rate control or manual low fire if equipped with fully modulating firing rate control.
    • Turn boiler control switch to the “on” or “start” position.
    • Ignition sequence: forced draft fan starts, air damper opens, boiler purges, air damper goes to low fire, electrodes spark, pilot fuel admitted, and main burner ignites.

    Warming Up the Boiler

    • Raise water temperature slowly, operating the boiler at low fire, until the boiler and heating system reach normal operating temperature and pressure.
    • Perform operating and safety limit checks.

    Safety Checks

    • Check the boiler frequently for leaks and ensure the burner is operating properly.
    • Check the safety relief valve for evidence of leaking and perform try lever and pop tests.

    Log Book Entry

    • Record date and time of startup, observed irregularities, corrective actions taken, time when controls shut off burner, tests performed, and results of tests.
    • Include signature of operator.

    Cutting in a Boiler

    • When adding a previously non-operating boiler to an already operating system, follow the same startup procedures, with exceptions:
      • Close the valve in the connecting line between the boiler and the common expansion tank.
      • Fill the boiler and raise pressure to at least the minimum required static pressure.
      • Crack open the valve and let the pressure equalize, then open the valve fully.

    Startup Preparation

    • Prepare boiler plant auxiliaries according to site-specific procedures.
    • Review manufacturer recommendations for burner and boiler startup.

    Boiler Startup Sequence

    • Open boiler return and supply valves, if applicable.
    • Ensure boiler control switch is in the “off” position.
    • Close main disconnect switch to supply power to the boiler.

    Furnace Purge and Ignition

    • If the boiler has a gas-fired atmospheric burner, allow 5 minutes for natural purge.
    • Light the continuous pilot burner according to manufacturer's instructions.
    • Open main burner test firing valve.

    Main Burner Ignition

    • Place boiler on low fire if equipped with high-low firing rate control or manual low fire if equipped with fully modulating firing rate control.
    • Turn boiler control switch to the “on” or “start” position.
    • Ignition sequence: forced draft fan starts, air damper opens, boiler purges, air damper goes to low fire, electrodes spark, pilot fuel admitted, and main burner ignites.

    Warming Up the Boiler

    • Raise water temperature slowly, operating the boiler at low fire, until the boiler and heating system reach normal operating temperature and pressure.
    • Perform operating and safety limit checks.

    Safety Checks

    • Check the boiler frequently for leaks and ensure the burner is operating properly.
    • Check the safety relief valve for evidence of leaking and perform try lever and pop tests.

    Log Book Entry

    • Record date and time of startup, observed irregularities, corrective actions taken, time when controls shut off burner, tests performed, and results of tests.
    • Include signature of operator.

    Cutting in a Boiler

    • When adding a previously non-operating boiler to an already operating system, follow the same startup procedures, with exceptions:
      • Close the valve in the connecting line between the boiler and the common expansion tank.
      • Fill the boiler and raise pressure to at least the minimum required static pressure.
      • Crack open the valve and let the pressure equalize, then open the valve fully.

    Startup Preparation

    • Prepare boiler plant auxiliaries according to site-specific procedures.
    • Review manufacturer recommendations for burner and boiler startup.

    Boiler Startup Sequence

    • Open boiler return and supply valves, if applicable.
    • Ensure boiler control switch is in the “off” position.
    • Close main disconnect switch to supply power to the boiler.

    Furnace Purge and Ignition

    • If the boiler has a gas-fired atmospheric burner, allow 5 minutes for natural purge.
    • Light the continuous pilot burner according to manufacturer's instructions.
    • Open main burner test firing valve.

    Main Burner Ignition

    • Place boiler on low fire if equipped with high-low firing rate control or manual low fire if equipped with fully modulating firing rate control.
    • Turn boiler control switch to the “on” or “start” position.
    • Ignition sequence: forced draft fan starts, air damper opens, boiler purges, air damper goes to low fire, electrodes spark, pilot fuel admitted, and main burner ignites.

    Warming Up the Boiler

    • Raise water temperature slowly, operating the boiler at low fire, until the boiler and heating system reach normal operating temperature and pressure.
    • Perform operating and safety limit checks.

    Safety Checks

    • Check the boiler frequently for leaks and ensure the burner is operating properly.
    • Check the safety relief valve for evidence of leaking and perform try lever and pop tests.

    Log Book Entry

    • Record date and time of startup, observed irregularities, corrective actions taken, time when controls shut off burner, tests performed, and results of tests.
    • Include signature of operator.

    Cutting in a Boiler

    • When adding a previously non-operating boiler to an already operating system, follow the same startup procedures, with exceptions:
      • Close the valve in the connecting line between the boiler and the common expansion tank.
      • Fill the boiler and raise pressure to at least the minimum required static pressure.
      • Crack open the valve and let the pressure equalize, then open the valve fully.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Learn the essential steps for safely starting a hot water boiler, including furnace purge, ignition, and main burner light-off. Understand the importance of following manufacturer operating procedures and site-specific standard operating procedures.

    Use Quizgecko on...