Gas Hot Tapping Procedures for 4" and Above
12 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the correct step for attaching the completion machine and alignment tool to the isolation valve?

  • Raise and lower the boring bar until contact is made with the pipe, then advance boring bar until pilot drill contacts the pipe
  • Attach completion machine assembled with alignment tool and completion plug to the isolation valve, then fully open isolation valve
  • Attach the proper size machine adapter to the body of the drilling machine, then attach the drilling machine with equipment and adapter onto the isolation valve
  • Advance shaft until completion plug contacts fitting threads, then rotate shaft until completion plug threads are engaged with fitting threads and securely bolt isolation valve to fitting (correct)

What is the purpose of performing a 'dry run' alignment of the completion plug?

  • To ensure the completion plug threads are aligned with the fitting threads before securing the isolation valve to the fitting (correct)
  • To check the condition of the completion plug before attaching it to the isolation valve
  • To determine the travel distance for the hot tap procedure
  • To coat the cutter and pilot bit with cutting grease before attaching the drilling machine

What is the correct step for withdrawing the shaft after completing the hot tap procedure?

  • Attach completion machine assembled with alignment tool and completion plug to the isolation valve, then fully open isolation valve
  • Rotate shaft in the opposite direction until completion plug is unscrewed from fitting and withdraw shaft to rearmost position (correct)
  • Attach the proper size machine adapter to the body of the drilling machine, then attach the drilling machine with equipment and adapter onto the isolation valve
  • Raise and lower the boring bar until contact is made with the pipe, then advance boring bar until pilot drill contacts the pipe

What should be done to the cutter and pilot bit before attaching the drilling machine to the isolation valve?

<p>Thoroughly coat the cutter and pilot bit with cutting grease (D)</p> Signup and view all the answers

What should be done if the boring bar does not advance easily during the drilling operation?

<p>Retract the boring bar and report to the supervisor (A)</p> Signup and view all the answers

What is the purpose of retracting the boring bar to its rearmost position?

<p>To ensure the cutter and pilot bit clears the isolation valve (D)</p> Signup and view all the answers

What should be done if internal corrosion is found in the examined coupon?

<p>Immediately report it to the supervisor (B)</p> Signup and view all the answers

What is the purpose of bleeding off pressure from the isolation valve?

<p>To ensure completion plug is properly seated (B)</p> Signup and view all the answers

When should the completion plug be screwed into the fitting?

<p>After attaching the completion machine assembled with inserting tool (C)</p> Signup and view all the answers

What is the purpose of operating the drilling machine until the pilot bit penetrates the pipe?

<p>To measure the travel required to complete the drilling operation (B)</p> Signup and view all the answers

What should be done if the cut is not complete during the drilling operation?

<p>Retract boring bar to its rearmost position (D)</p> Signup and view all the answers

When should the completion flange be bolted solidly to the fitting flange?

<p>After attaching the completion machine assembled with inserting tool (D)</p> Signup and view all the answers