What is the purpose of performing low water cut-off tests in heating boiler and power boiler service?
What is the purpose of performing low water cut-off tests in heating boiler and power boiler service?
- To determine the cause of the low water condition
- To test the frequency and procedures of low water cut-offs
- To check if the boiler shuts off rapidly when the float chamber is drained (correct)
- To isolate the feedwater and allow the boiler to steam off water
What are the recommended test methods for low water cut-offs in heating boiler and power boiler service?
What are the recommended test methods for low water cut-offs in heating boiler and power boiler service?
- Determining the cause of the low water condition
- Draining the float chamber rapidly to check if the boiler shuts off
- Isolating the feedwater and blowing off the boiler (correct)
- Allowing the boiler to steam off water
What is the role of the operator in addressing a low water condition in a boiler?
What is the role of the operator in addressing a low water condition in a boiler?
- Determine the cause of the low water condition and correct it before restarting the boiler (correct)
- Isolate the feedwater and allow the boiler to steam off water
- Reset the cut-off and restart the boiler immediately
- Conduct rapid draining of the float chamber
Where can one find information about low water cut-off tests and frequencies in heating boiler and power boiler service?
Where can one find information about low water cut-off tests and frequencies in heating boiler and power boiler service?
According to CSA B51 6.3.2.1, how many low-water fuel cut-off devices should steam boilers not continuously attended by a certified operator be equipped with?
According to CSA B51 6.3.2.1, how many low-water fuel cut-off devices should steam boilers not continuously attended by a certified operator be equipped with?
What does the statement 'cannot be rendered inoperative' mean in the context of low water cut-off devices?
What does the statement 'cannot be rendered inoperative' mean in the context of low water cut-off devices?
Why may momentary contact switch be installed in parallel to the low water cut-off switch for large capacity boilers?
Why may momentary contact switch be installed in parallel to the low water cut-off switch for large capacity boilers?
What takes precedence over the ASME codes in Canada regarding boilers and pressure vessels?
What takes precedence over the ASME codes in Canada regarding boilers and pressure vessels?
Why should no switches be installed that render the low water cut-off inoperable according to CSA B51 6.3.2.1?
Why should no switches be installed that render the low water cut-off inoperable according to CSA B51 6.3.2.1?
What is required for large capacity boilers according to CSA B51 6.3.2.1?
What is required for large capacity boilers according to CSA B51 6.3.2.1?
What is the minimum heat input, in Btu/hr, that requires a flow-sensing device in a coil-type boiler or a watertube boiler?
What is the minimum heat input, in Btu/hr, that requires a flow-sensing device in a coil-type boiler or a watertube boiler?
In which jurisdictional code are the flow-sensing device requirements similar to those in CSA B51?
In which jurisdictional code are the flow-sensing device requirements similar to those in CSA B51?
What is the capacity (in boiler horsepower output) for boilers that ASME CSD-1 addresses?
What is the capacity (in boiler horsepower output) for boilers that ASME CSD-1 addresses?
How many automatic low-water fuel cutoffs are required for each automatically fired, low-pressure steam boiler according to ASME CSD-1 Part CW120?
How many automatic low-water fuel cutoffs are required for each automatically fired, low-pressure steam boiler according to ASME CSD-1 Part CW120?
Where should the low-water fuel cutoff be located for hot-water boilers as per ASME CSD-1 Part CW-130?
Where should the low-water fuel cutoff be located for hot-water boilers as per ASME CSD-1 Part CW-130?
What must be avoided when connecting cut-off devices to a water column for high-pressure steam boilers according to ASME CSD-1 Part CW-140?
What must be avoided when connecting cut-off devices to a water column for high-pressure steam boilers according to ASME CSD-1 Part CW-140?
What is the main purpose of a low-water fuel cutoff for hot-water heating boilers as per ASME CSD-1 Part CW-130?
What is the main purpose of a low-water fuel cutoff for hot-water heating boilers as per ASME CSD-1 Part CW-130?
What is the requirement for a means of testing the low-water cut-offs of hot water boilers according to Part HG-614?
What is the requirement for a means of testing the low-water cut-offs of hot water boilers according to Part HG-614?
What is the minimum capacity defined for a boiler in CSA B51?
What is the minimum capacity defined for a boiler in CSA B51?
What is required to be installed at the hot water outlet according to CSA B51?
What is required to be installed at the hot water outlet according to CSA B51?
What does ASME CSD-1 address?
What does ASME CSD-1 address?
According to CSA-B51 6.3.2.2, which statement about low-water fuel cut-off devices for hot water boilers is true?
According to CSA-B51 6.3.2.2, which statement about low-water fuel cut-off devices for hot water boilers is true?
According to ASME BPVC I, what is the requirement for low water fuel cut-off devices on fuel-fired or waste heat fired boilers?
According to ASME BPVC I, what is the requirement for low water fuel cut-off devices on fuel-fired or waste heat fired boilers?
Under what conditions may some hot water boilers be exempted from low-water fuel cut-off device requirements according to CSA B51 6.2.2.3?
Under what conditions may some hot water boilers be exempted from low-water fuel cut-off device requirements according to CSA B51 6.2.2.3?
Under what circumstance does ASME BPVC I permit the use of a low water cut-off as an alternative to a secondary means of feeding water?
Under what circumstance does ASME BPVC I permit the use of a low water cut-off as an alternative to a secondary means of feeding water?
What is the requirement for electric boilers of the resistance element type according to ASME BPVC I?
What is the requirement for electric boilers of the resistance element type according to ASME BPVC I?
What is the requirement for heating surface area in ASME BPVC I regarding the number of means of feeding water?
What is the requirement for heating surface area in ASME BPVC I regarding the number of means of feeding water?
What does ASME BPVC IV prohibit regarding the installation of low-water fuel cut-off devices in the interconnecting piping?
What does ASME BPVC IV prohibit regarding the installation of low-water fuel cut-off devices in the interconnecting piping?
What does ASME BPVC IV require regarding the location of the automatic low-water fuel cutoff in steam heating boilers?
What does ASME BPVC IV require regarding the location of the automatic low-water fuel cutoff in steam heating boilers?
What is recommended by ASME VII regarding operating procedures when an automatic low water boiler trip is equipped with a water column?
What is recommended by ASME VII regarding operating procedures when an automatic low water boiler trip is equipped with a water column?