Podcast
Questions and Answers
What action can the Contractor take if the suspension under Sub-Clause 8.9 has continued for more than 84 days?
What action can the Contractor take if the suspension under Sub-Clause 8.9 has continued for more than 84 days?
Under what condition can the Contractor give a Notice of termination?
Under what condition can the Contractor give a Notice of termination?
When can the Contractor resume work after receiving a Notice from the Engineer?
When can the Contractor resume work after receiving a Notice from the Engineer?
What must the Contractor do if the suspension affects the whole of the Works?
What must the Contractor do if the suspension affects the whole of the Works?
Signup and view all the answers
Under what circumstance can the Contractor agree to a further suspension?
Under what circumstance can the Contractor agree to a further suspension?
Signup and view all the answers
What should the Contractor do if the suspension under Sub-Clause 8.9 continues for more than 28 days and the Plant and/or Materials were scheduled to have been completed and ready for delivery to the Site during the suspension period?
What should the Contractor do if the suspension under Sub-Clause 8.9 continues for more than 28 days and the Plant and/or Materials were scheduled to have been completed and ready for delivery to the Site during the suspension period?
Signup and view all the answers
What does the Contractor need to do if the suspension affects the whole of the Works?
What does the Contractor need to do if the suspension affects the whole of the Works?
Signup and view all the answers
Under what circumstance can the Contractor treat the suspension as an omission of the affected part of the Works?
Under what circumstance can the Contractor treat the suspension as an omission of the affected part of the Works?
Signup and view all the answers
When should the Contractor carry out the Tests on Completion?
When should the Contractor carry out the Tests on Completion?
Signup and view all the answers
What is the Contractor entitled to if the work on Plant, or delivery of Plant and/or Materials, has been suspended for more than 28 days?
What is the Contractor entitled to if the work on Plant, or delivery of Plant and/or Materials, has been suspended for more than 28 days?
Signup and view all the answers
What should the Contractor provide to the Employer as part of the construction contract?
What should the Contractor provide to the Employer as part of the construction contract?
Signup and view all the answers
Under what circumstances is the Contractor entitled to an extension of time for completion?
Under what circumstances is the Contractor entitled to an extension of time for completion?
Signup and view all the answers
What action can the Engineer take if the initial programme fails to comply with the contract or reflect actual progress?
What action can the Engineer take if the initial programme fails to comply with the contract or reflect actual progress?
Signup and view all the answers
When must the Contractor give notice under the contract?
When must the Contractor give notice under the contract?
Signup and view all the answers
What can the Engineer do when determining each extension of time?
What can the Engineer do when determining each extension of time?
Signup and view all the answers
Under what conditions can the Contractor submit a proposal to avoid or minimize the effects of future events or circumstances?
Under what conditions can the Contractor submit a proposal to avoid or minimize the effects of future events or circumstances?
Signup and view all the answers
What is included in the programme that the Contractor is required to provide?
What is included in the programme that the Contractor is required to provide?
Signup and view all the answers
If a delay is caused by the Employer’s responsibility and concurrent with a delay caused by the Contractor’s responsibility, how will the Contractor’s entitlement to Extension of Time (EOT) be assessed?
If a delay is caused by the Employer’s responsibility and concurrent with a delay caused by the Contractor’s responsibility, how will the Contractor’s entitlement to Extension of Time (EOT) be assessed?
Signup and view all the answers
Under what conditions will delays caused by authorities be considered as a cause of delay?
Under what conditions will delays caused by authorities be considered as a cause of delay?
Signup and view all the answers
What happens if the Contractor's progress is too slow?
What happens if the Contractor's progress is too slow?
Signup and view all the answers
Under what circumstances may the Employer be entitled to payment of additional costs?
Under what circumstances may the Employer be entitled to payment of additional costs?
Signup and view all the answers
What is the consequence if the Contractor fails to comply with the Time for Completion?
What is the consequence if the Contractor fails to comply with the Time for Completion?
Signup and view all the answers
How are Delay Damages calculated?
How are Delay Damages calculated?
Signup and view all the answers
What is the Contractor entitled to during a suspension instructed by the Engineer?
What is the Contractor entitled to during a suspension instructed by the Engineer?
Signup and view all the answers
What happens if the Engineer does not give a Notice within 21 days after receiving the initial programme?
What happens if the Engineer does not give a Notice within 21 days after receiving the initial programme?
Signup and view all the answers
Under what circumstance is the Contractor required to proceed in accordance with the Programme?
Under what circumstance is the Contractor required to proceed in accordance with the Programme?
Signup and view all the answers
What entitlement do the Employer’s Personnel have in relation to the Programme?
What entitlement do the Employer’s Personnel have in relation to the Programme?
Signup and view all the answers
What is the consequence if the Engineer gives no Notice within 14 days after receiving a revised programme?
What is the consequence if the Engineer gives no Notice within 14 days after receiving a revised programme?
Signup and view all the answers
What action can the Contractor take if the Engineer does not give a Notice within the specified timeframes?
What action can the Contractor take if the Engineer does not give a Notice within the specified timeframes?
Signup and view all the answers
What is the Engineer's responsibility regarding the initial programme and revised programmes submitted by the Contractor?
What is the Engineer's responsibility regarding the initial programme and revised programmes submitted by the Contractor?
Signup and view all the answers
What is the Contractor required to do if the Engineer gives no Notice within the specified timeframes?
What is the Contractor required to do if the Engineer gives no Notice within the specified timeframes?
Signup and view all the answers
What happens if the Engineer gives no Notice within 21 days after receiving the initial programme?
What happens if the Engineer gives no Notice within 21 days after receiving the initial programme?
Signup and view all the answers
What action can the Engineer take if a revised programme submitted by the Contractor does not comply with the Contract?
What action can the Engineer take if a revised programme submitted by the Contractor does not comply with the Contract?
Signup and view all the answers
What is the consequence if the Engineer gives no Notice within 14 days after receiving a revised programme?
What is the consequence if the Engineer gives no Notice within 14 days after receiving a revised programme?
Signup and view all the answers
What is the Contractor required to do if the Engineer gives no Notice within the specified timeframes for initial and revised programmes?
What is the Contractor required to do if the Engineer gives no Notice within the specified timeframes for initial and revised programmes?
Signup and view all the answers
Who is entitled to rely on the Programme when planning their activities?
Who is entitled to rely on the Programme when planning their activities?
Signup and view all the answers
What is the purpose of the Engineer's review of the initial and revised programmes submitted by the Contractor?
What is the purpose of the Engineer's review of the initial and revised programmes submitted by the Contractor?
Signup and view all the answers
What platform is the document restricted for distribution within?
What platform is the document restricted for distribution within?
Signup and view all the answers
Study Notes
FIDIC General Conditions Summary
- If a delay is caused by the Employer’s responsibility and concurrent with a delay caused by the Contractor’s responsibility, the Contractor’s entitlement to Extension of Time (EOT) will be assessed according to rules and procedures in the Special Provisions.
- Delays caused by authorities will be considered as a cause of delay if the Contractor diligently follows procedures laid down by relevant legally constituted public authorities or private utility entities in the country, and the delay or disruption was unforeseeable.
- If the Contractor's progress is too slow, the Engineer may instruct the Contractor to submit a revised program to expedite progress, and the Contractor shall adopt these revised methods at their own risk and cost.
- The Employer may be entitled to payment of additional costs if the revised methods cause the Employer to incur additional costs, in addition to Delay Damages.
- If the Contractor fails to comply with the Time for Completion, the Employer shall be entitled to payment of Delay Damages by the Contractor for this default.
- Delay Damages shall be the amount stated in the Contract Data and shall be paid for every day that elapses between the Time for Completion and the Date of Completion of the Works or Section, not exceeding the maximum amount stated in the Contract Data.
- The Contractor shall protect, store, and secure the Works during a suspension instructed by the Engineer, and may be entitled to EOT and/or payment of costs incurred from complying with the instruction or resuming the work.
- The Contractor shall not be entitled to EOT or payment of costs incurred in making good the consequences of the Contractor’s faulty or defective workmanship, Plant, or Materials.
- The Engineer may instruct the Contractor to suspend progress of part or all of the Works at any time, and during such suspension, the Contractor shall protect, store, and secure the Works against any deterioration, loss, or damage.
- If the cause of the suspension is the responsibility of the Contractor, certain clauses related to consequences, payment for plant and materials, and prolonged suspension shall not apply.
- The Contractor shall not be entitled to EOT or payment for costs from any deterioration, loss, or damage caused by the Contractor’s failure to protect, store, or secure the Works during a suspension.
- The Sub-Clause does not limit the Contractor’s liability for Delay Damages in cases of fraud, gross negligence, deliberate default, or reckless misconduct by the Contractor.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your understanding of the FIDIC general conditions with this summary quiz covering topics such as delays, entitlement to extension of time, payment for additional costs, protection and suspension of works, and liability for delay damages.