What was the primary cause of the gas leakage at well site #16 at Mari Field Daharki?
What was the primary cause of the gas leakage at well site #16 at Mari Field Daharki?
What action was taken to rectify the leaked Access Fitting Assembly at well site #16?
What action was taken to rectify the leaked Access Fitting Assembly at well site #16?
What were the recommendations proposed to avoid reoccurrence of gas leakage from Access Fitting Assembly at Mari Field Daharki?
What were the recommendations proposed to avoid reoccurrence of gas leakage from Access Fitting Assembly at Mari Field Daharki?
Study Notes
Gas Leakage from Access Fitting Assembly at Mari Field Daharki
- On March 7, 2023, a gas leakage was reported at well site #16 at Mari Field Daharki due to a hole in the thread protection plug of the Access Fitting Assembly.
- An investigation team was constituted to identify the root cause and propose recommendations to avoid reoccurrence.
- Production and C&I teams were mobilized to assess the extent of leakage and perform rectification.
- Line depressurization was initiated by shutting off Wells#16 and 97 and isolating the 8” line from the HRL network.
- Rectification of the leaked Access Fitting Assembly was concluded by the C&I team at 1600 hrs and pipeline loop was re-pressurized, and production resumed at 1700 hrs.
- The cellar uplifting activity at Mari Field Daharki is currently being executed by the ED&P team, and uplifting activity has been carried out at 57/87 locations.
- Gas leakage detection survey has been started at all corrosion monitoring access fittings recently installed at uplifted cellar locations.
- The primary cause of gas escape was found to be a loosened bore seal nut, which was not properly tightened during the installation of the access fitting assembly.
- Roles and responsibilities, as well as communication protocols, were not distinctly defined during the installation of access fitting assemblies.
- Recommendations include checking all corrosion monitoring access fittings assemblies at uplifted cellar locations for leakage, clearly defining roles and responsibilities for installation of access fitting assemblies, and developing or updating work instructions for QA/QC of newly installed access fittings.
- The permit shall be closed out after the punch listing has been conducted by the Maintenance (Static/C&I/E&I), E&C, and Production teams.
- All dossiers must be handed over to the Operations Team for an effective punch listing of the already uplifted cellars, as well as ongoing and upcoming cellars.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
Test your knowledge of gas leakage incidents with this quiz on the Access Fitting Assembly incident at Mari Field Daharki. Learn about the root cause of the incident, the actions taken to rectify it, and the recommendations proposed to prevent reoccurrence. Challenge yourself to understand the roles and responsibilities involved and the importance of clear communication protocols during installation. Take the quiz to strengthen your understanding of gas leakage incidents and preventative measures.