Podcast
Questions and Answers
What happens if the Engineer does not give a Notice within the period of 14 days?
What happens if the Engineer does not give a Notice within the period of 14 days?
What should the other Party do if they disagree with the deemed valid Notice of Claim?
What should the other Party do if they disagree with the deemed valid Notice of Claim?
What is required for the agreement or determination of the Claim under Sub-Clause 20.2.5 to include a review by the Engineer?
What is required for the agreement or determination of the Claim under Sub-Clause 20.2.5 to include a review by the Engineer?
What should the claiming Party do if they disagree with the Engineer or consider late submission of the Notice of Claim justified?
What should the claiming Party do if they disagree with the Engineer or consider late submission of the Notice of Claim justified?
Signup and view all the answers
What does 'contemporary records' refer to in Sub-Clause 20.2?
What does 'contemporary records' refer to in Sub-Clause 20.2?
Signup and view all the answers
What is the Engineer's role regarding the Contractor's contemporary records?
What is the Engineer's role regarding the Contractor's contemporary records?
Signup and view all the answers
What is the consequence of the claiming Party failing to keep necessary contemporary records to substantiate the Claim?
What is the consequence of the claiming Party failing to keep necessary contemporary records to substantiate the Claim?
Signup and view all the answers
If a DAAB member declines to act or is unable to act as a result of death, when should a replacement DAAB member be appointed?
If a DAAB member declines to act or is unable to act as a result of death, when should a replacement DAAB member be appointed?
Signup and view all the answers
When does the term of the DAAB expire if the Contract is terminated?
When does the term of the DAAB expire if the Contract is terminated?
Signup and view all the answers
Under what conditions would the Parties fail to agree the appointment of a replacement DAAB member?
Under what conditions would the Parties fail to agree the appointment of a replacement DAAB member?
Signup and view all the answers
When can the appointment of any DAAB member be terminated?
When can the appointment of any DAAB member be terminated?
Signup and view all the answers
If the DAAB is to comprise three persons, what happens if either Party fails to select a member by the date stated in the first paragraph of Sub-Clause 21.1?
If the DAAB is to comprise three persons, what happens if either Party fails to select a member by the date stated in the first paragraph of Sub-Clause 21.1?
Signup and view all the answers
Who appoints the member(s) of the DAAB if one Party refuses or fails to sign a DAAB Agreement with any replacement member?
Who appoints the member(s) of the DAAB if one Party refuses or fails to sign a DAAB Agreement with any replacement member?
Signup and view all the answers
When does the term of the DAAB expire if the Parties reach a final agreement on all matters in connection with the termination of the Contract?
When does the term of the DAAB expire if the Parties reach a final agreement on all matters in connection with the termination of the Contract?
Signup and view all the answers
Under what conditions can the appointment of any DAAB member be terminated?
Under what conditions can the appointment of any DAAB member be terminated?
Signup and view all the answers
If the DAAB is to comprise a sole member, what happens if the Parties fail to agree the appointment of this member by the date stated in the first paragraph of Sub-Clause 21.1?
If the DAAB is to comprise a sole member, what happens if the Parties fail to agree the appointment of this member by the date stated in the first paragraph of Sub-Clause 21.1?
Signup and view all the answers
What is the time limit for the engineer to respond to a claim, as per FIDIC 2017 General Conditions?
What is the time limit for the engineer to respond to a claim, as per FIDIC 2017 General Conditions?
Signup and view all the answers
When should the final fully detailed claim be submitted after the event's effects end?
When should the final fully detailed claim be submitted after the event's effects end?
Signup and view all the answers
Under what condition may late submissions of claims be accepted?
Under what condition may late submissions of claims be accepted?
Signup and view all the answers
How are substantiated claim amounts included in Payment Certificates until the claim is agreed or determined?
How are substantiated claim amounts included in Payment Certificates until the claim is agreed or determined?
Signup and view all the answers
How can the Employer claim payment, extend the Defects Notification Period (DNP), or make deductions?
How can the Employer claim payment, extend the Defects Notification Period (DNP), or make deductions?
Signup and view all the answers
What happens if there is a failure to comply with the claim process?
What happens if there is a failure to comply with the claim process?
Signup and view all the answers
How are disputes decided according to FIDIC 2017 General Conditions?
How are disputes decided according to FIDIC 2017 General Conditions?
Signup and view all the answers
What does a 'fully detailed Claim' include according to Sub-Clause 20.2.4?
What does a 'fully detailed Claim' include according to Sub-Clause 20.2.4?
Signup and view all the answers
What happens if the claiming Party fails to submit the statement under Sub-Clause 20.2.2(b)?
What happens if the claiming Party fails to submit the statement under Sub-Clause 20.2.2(b)?
Signup and view all the answers
What does the Engineer do if they consider that the claiming Party has failed to give the Notice of Claim within the period of 28 days?
What does the Engineer do if they consider that the claiming Party has failed to give the Notice of Claim within the period of 28 days?
Signup and view all the answers
What does the Engineer do after receiving a fully detailed Claim under Sub-Clause 20.2.4?
What does the Engineer do after receiving a fully detailed Claim under Sub-Clause 20.2.4?
Signup and view all the answers
What happens if the Engineer does not give a Notice within 14 days after the time limit for submitting the statement under Sub-Clause 20.2.2(b) has expired?
What happens if the Engineer does not give a Notice within 14 days after the time limit for submitting the statement under Sub-Clause 20.2.2(b) has expired?
Signup and view all the answers
What does the agreement or determination of the Claim include according to Sub-Clause 20.2.5?
What does the agreement or determination of the Claim include according to Sub-Clause 20.2.5?
Signup and view all the answers
What happens if the Engineer requires necessary additional particulars after receiving the fully detailed Claim?
What happens if the Engineer requires necessary additional particulars after receiving the fully detailed Claim?
Signup and view all the answers
What is the consequence of failing to submit a fully detailed Claim within the specified time limit?
What is the consequence of failing to submit a fully detailed Claim within the specified time limit?
Signup and view all the answers
What must be included in a 'fully detailed Claim' submission?
What must be included in a 'fully detailed Claim' submission?
Signup and view all the answers
What happens if the Engineer requires additional particulars after receiving the fully detailed Claim?
What happens if the Engineer requires additional particulars after receiving the fully detailed Claim?
Signup and view all the answers
What does the Engineer do after receiving a fully detailed Claim?
What does the Engineer do after receiving a fully detailed Claim?
Signup and view all the answers
In case of a continuing effect, what clause will apply to the Claims?
In case of a continuing effect, what clause will apply to the Claims?
Signup and view all the answers
If the claiming Party disagrees with the Engineer's Notice, what must they do?
If the claiming Party disagrees with the Engineer's Notice, what must they do?
Signup and view all the answers
What does the agreement or determination of the Claim include?
What does the agreement or determination of the Claim include?
Signup and view all the answers
Study Notes
FIDIC 2017 General Conditions: Claims and Disputes
- FIDIC 2017 General Conditions outline the process for handling claims in construction contracts.
- The claiming party must promptly give notice to the other party, describing the particulars and reasons for the claim.
- The engineer must respond to the claim within a specified time limit, providing the contractual or legal basis for the response.
- Interim fully detailed claims must be submitted at monthly intervals, with a final fully detailed claim due within 28 days after the event's effects end.
- Late submissions of claims may be accepted depending on the potential prejudice to the other party and their prior knowledge of the event or circumstance.
- The Engineer includes substantiated claim amounts in each Payment Certificate until the claim is agreed or determined.
- The Employer can only claim payment, extend the Defects Notification Period (DNP), or make deductions by complying with Sub-Clause 20.2.
- Failure to comply with the claim process may affect additional payment, extension of time, or extension of the DNP, taking into account any prevention or prejudice to proper investigation.
- Disputes are decided by a Dispute Adjudication/Avoidance Board (DAAB) in accordance with the contract.
- The Parties jointly appoint the DAAB members within a specified time after the Contractor's receipt of the Letter of Acceptance.
- The DAAB comprises either one suitably qualified member or three members, selected from a list in the Contract Data, with the possibility of a chairperson.
- The Parties mutually agree on the terms of remuneration for the DAAB members and any expert consulted.
FIDIC Contract Claims Procedure
- The Engineer has the right to inspect the Contractor's records during normal working hours and request copies if necessary.
- A "fully detailed Claim" submission must include a detailed description of the event, contractual/legal basis, contemporary records, and supporting particulars of the amount claimed.
- The claiming Party must submit a fully detailed Claim within 84 days of becoming aware of the event, or should have become aware.
- If the Engineer deems that the Notice of Claim was not given within 28 days, they must give a Notice to the claiming Party within 14 days with reasons.
- Failure to submit a fully detailed Claim within the specified time limit will result in the Notice of Claim being deemed invalid, unless the Engineer fails to give a Notice within 14 days.
- If the claiming Party disagrees with the Engineer's Notice, they must include details of the disagreement in the fully detailed claim.
- In case of a continuing effect, the Claims of continuing effect clause will apply.
- After receiving a fully detailed Claim, the Engineer proceeds to agree or determine the additional payment or time extension entitled to the claiming Party.
- The agreement or determination of the Claim will include whether the Notice of Claim shall be treated as valid, taking into account the details of the claiming Party’s disagreement or late submission justification.
- If the Engineer requires additional particulars after receiving the fully detailed Claim, the claiming Party must provide them.
- The Engineer will review any disagreement in the agreement or determination of the Claim.
- If there is a continuing effect, an interim or final fully detailed Claim must be submitted, and the Engineer will then proceed to agree or determine the Claim.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge of the FIDIC 2017 General Conditions related to claims and disputes in construction contracts. Explore the procedures for handling claims, the role of the Engineer, deadlines for claim submissions, and the resolution of disputes through the Dispute Adjudication/Avoidance Board (DAAB).