Podcast
Questions and Answers
What is the total plinth area of the residential building project mentioned?
What is the total plinth area of the residential building project mentioned?
1500 sq.m.
Calculate the plinth area rate in sq.m. if the rate is given as 14915 per sq.ft.
Calculate the plinth area rate in sq.m. if the rate is given as 14915 per sq.ft.
Approx. $160,000 per sq.m.$
What percentage is added for water supply and sanitary installations to the building cost?
What percentage is added for water supply and sanitary installations to the building cost?
5%
What is the total percentage of extra costs (architectural treatment, water supply, internal installations, electric & gas services) added to the initial building cost?
What is the total percentage of extra costs (architectural treatment, water supply, internal installations, electric & gas services) added to the initial building cost?
Signup and view all the answers
Define 'taking out of quantities' in the context of a detailed estimate.
Define 'taking out of quantities' in the context of a detailed estimate.
Signup and view all the answers
What documentation is usually submitted with the detailed estimate to obtain Technical Sanction?
What documentation is usually submitted with the detailed estimate to obtain Technical Sanction?
Signup and view all the answers
What is the purpose of including a contingency percentage in a detailed estimate?
What is the purpose of including a contingency percentage in a detailed estimate?
Signup and view all the answers
What is meant by 'Bill of Quantities' in the context of estimations?
What is meant by 'Bill of Quantities' in the context of estimations?
Signup and view all the answers
What is the purpose of the abstract of cost in estimation?
What is the purpose of the abstract of cost in estimation?
Signup and view all the answers
Explain the difference between a contractor estimate and an engineer's estimate.
Explain the difference between a contractor estimate and an engineer's estimate.
Signup and view all the answers
What are progress estimates and when are they typically made?
What are progress estimates and when are they typically made?
Signup and view all the answers
What is the significance of junctions and corners in detailed estimating?
What is the significance of junctions and corners in detailed estimating?
Signup and view all the answers
Define the separate or individual wall method in estimating.
Define the separate or individual wall method in estimating.
Signup and view all the answers
How does the center line method differ from the separate or individual walls method?
How does the center line method differ from the separate or individual walls method?
Signup and view all the answers
Why is accuracy in calculations important for detailed estimates?
Why is accuracy in calculations important for detailed estimates?
Signup and view all the answers
What are the typical components included in the detailed estimate calculations?
What are the typical components included in the detailed estimate calculations?
Signup and view all the answers
Study Notes
Estimation and Specifications
- Estimation involves calculating project costs.
- Specifications outline detailed project requirements.
- Rough cost estimates are initial approximations.
- Detailed estimates refine calculations after design finalization.
- Detailed estimates correct errors from rough estimates.
- Detailed estimates provide technical sanction.
- Project breakdown into work items or activities occurs.
- Quantities of each item calculated from drawings.
- Method called "taking out of quantities" used.
- Bill of Quantities document for itemized quantities.
- Itemized work units based on local practice.
- Itemized work multiplied by estimated current rate.
- Total of all items equals estimated total cost.
Example 2
- Rough cost estimate for a residential building.
- Total plinth area: 1500 sq. m.
- Plinth area rate: 14915/ sq. ft.
- Special architectural treatment: 1.5% of building cost.
- Water supply and sanitary installations: 5% of building cost.
- Internal Installations: 14% of building cost.
- Electric and gas services: 16% of building cost.
- Contingencies: 3% overall.
- Supervision charges: 8% overall.
- Design charges: 2% overall.
Detailed Estimate
- Detailed estimates calculate costs meticulously using detailed working drawings.
- Rough estimate errors are avoided.
- Detailed estimates submitted for technical sanction.
Bill of Quantities
- Document showing itemized work amounts.
- Measurements (length, breadth, height) recorded on the document.
- Corresponding quantities calculated and recorded.
- Remarks section available on the document.
Priced Bill of Quantities
- Lists quantities, unit costs, and total costs for each item.
- Itemized description of each item.
- Unit costs recorded and calculated.
- Total cost per item is determined.
- Remarks section available on the document.
Additional Information
- Rates usually match local Schedule of Rates.
- Premium allowed for rising labor/material costs.
- Additional 5% for possible contingencies (beyond unforeseen items).
- 2% for establishment charges.
- Drawings and details included in the submittal.
Types of Detailed Estimates
- Contractor Estimate: Created by contractor for bidding.
- Engineer's Estimate: Prepared by engineers for financial purposes.
- Progress Estimate: Regularly prepared to measure project completion and payments.
- Monthly estimate, a type of progress estimate.
Methods of Detailed Estimate
- Measuring dimensions (length, breath, height) from drawings.
- Special attention to wall junctions.
- Symmetrical footings: calculated using two methods.
- Separate or individual wall method.
- Center line method.
Separate or Individual Walls Method
- "Long walls" run in one direction, "short walls" run perpendicularly.
- Lengths measured according to "out-to-out" or "in-to-in."
- Wall lengths multiplied by breath and height to obtain quantities.
- Useful for calculating excavation, concrete, brickwork.
Separate or Individual Walls Method (Continued)
- Center-to-center lengths used for symmetrical footings.
- "Out-to-out" length (long walls) = center-to-center length + ½ breadth on each side.
- "In-to-in" length (short walls)= center-to-center length - 1 breadth.
Methods of quicker estimation for long walls
- Length of foundation trench measured ("out-to-out").
- Foundation concrete length the same as foundation trench.
- For each footing, preceding footing length minus two offsets.
Methods of quicker estimation for short walls
- Same as long wall method but offsets added.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the fundamental concepts of estimation and specifications in project management. It includes topics such as rough and detailed cost estimates, project breakdown, and methods for calculating quantities. Test your understanding of how to effectively estimate project costs and outline specifications.