When are hire charges applicable for the plant?
When are hire charges applicable for the plant?
- From the date of delivery to the date of return. (correct)
- For the time spent in transportation only.
- From the day of the order till delivery.
- Only when the plant is used on-site.
Who is responsible for the replacement of wear and tear parts during the hire period?
Who is responsible for the replacement of wear and tear parts during the hire period?
- The hiring department only. (correct)
- The Controller of Stores.
- The railway only.
- Both the railway and the hiring department.
What must be done to acquire spare parts during the hiring period?
What must be done to acquire spare parts during the hiring period?
- They must be sourced only from the railway ex-stores depot. (correct)
- Spares can be bought from multiple sources without restriction.
- They can be purchased from any local supplier.
- The hiring department can shop around for the best price.
How is the cost of breakage or loss of parts determined?
How is the cost of breakage or loss of parts determined?
What is the assumed life of machines when not otherwise specified?
What is the assumed life of machines when not otherwise specified?
What is the primary purpose of creating an Engineering Plant Reserve on each railway?
What is the primary purpose of creating an Engineering Plant Reserve on each railway?
Which of the following items is NOT included in the Engineering Plant Reserve list?
Which of the following items is NOT included in the Engineering Plant Reserve list?
Who has the authority to modify the items on the Engineering Plant Reserve list?
Who has the authority to modify the items on the Engineering Plant Reserve list?
Which of the following items represents a type of drilling machine included in the Engineering Plant Reserve?
Which of the following items represents a type of drilling machine included in the Engineering Plant Reserve?
What restriction is placed on the Stores Department regarding the Engineering Plant Reserve?
What restriction is placed on the Stores Department regarding the Engineering Plant Reserve?
Which item in the Engineering Plant Reserve is associated with lifting operations?
Which item in the Engineering Plant Reserve is associated with lifting operations?
What type of equipment includes items such as air compressors and steam hoists?
What type of equipment includes items such as air compressors and steam hoists?
What documentation is required when returning plant to the nearest stores depot?
What documentation is required when returning plant to the nearest stores depot?
Which of the following details is NOT required on the Advice Note when returning plant?
Which of the following details is NOT required on the Advice Note when returning plant?
Under what condition may plant be transferred directly from one work to another?
Under what condition may plant be transferred directly from one work to another?
Who is responsible for deciding what material is maintained in the Engineering Plant Reserve?
Who is responsible for deciding what material is maintained in the Engineering Plant Reserve?
What should be done when new material is sent to the Reserve?
What should be done when new material is sent to the Reserve?
What is necessary regarding the storage of materials in the Engineering Plant Reserve?
What is necessary regarding the storage of materials in the Engineering Plant Reserve?
What condition qualifies plant for a transfer value fix by the Chief Engineer?
What condition qualifies plant for a transfer value fix by the Chief Engineer?
What label should be used on the Advice Notes for returning engineering plant?
What label should be used on the Advice Notes for returning engineering plant?
Who maintains custody of materials in the Engineering Plant Reserve?
Who maintains custody of materials in the Engineering Plant Reserve?
Where should winches, dredgers, and pumps that require overhaul be kept?
Where should winches, dredgers, and pumps that require overhaul be kept?
What is the purpose of marking a plant with the letters 'E.R.'?
What is the purpose of marking a plant with the letters 'E.R.'?
What type of plant should be kept close to loco shops?
What type of plant should be kept close to loco shops?
How should pieces of plant from the same category be numbered?
How should pieces of plant from the same category be numbered?
Which information is NOT included in the Reserve Plant Register?
Which information is NOT included in the Reserve Plant Register?
What document should be referred to for entering particulars on receipt of an Engineering Plant Reserve item?
What document should be referred to for entering particulars on receipt of an Engineering Plant Reserve item?
Which of the following best describes a tip wagon’s storage requirement?
Which of the following best describes a tip wagon’s storage requirement?
What should be recorded in the Reserve Plant Register regarding the issuing of an item?
What should be recorded in the Reserve Plant Register regarding the issuing of an item?
What is the primary purpose of maintaining a Reserve Plant Register?
What is the primary purpose of maintaining a Reserve Plant Register?
What key detail is associated with the Reserve Plant Number?
What key detail is associated with the Reserve Plant Number?
What must be done before any inspection or repair work is initiated?
What must be done before any inspection or repair work is initiated?
How should the cost of inspection and repairs for returned items be allocated?
How should the cost of inspection and repairs for returned items be allocated?
What should be noted if repairs are estimated but not undertaken immediately?
What should be noted if repairs are estimated but not undertaken immediately?
In cases where plant is debited on a hire basis, what should expenditure on inspection and repairs be charged to?
In cases where plant is debited on a hire basis, what should expenditure on inspection and repairs be charged to?
What document should be utilized for each material brought on or returned to the Reserve?
What document should be utilized for each material brought on or returned to the Reserve?
What initial information should be included on the Engineering Reserve Plant Inspection Certificate?
What initial information should be included on the Engineering Reserve Plant Inspection Certificate?
What should NOT be operated upon for recording the expenditure on repairs to plants?
What should NOT be operated upon for recording the expenditure on repairs to plants?
What should be included in the remarks section of the Engineering Reserve Plant Inspection Certificate?
What should be included in the remarks section of the Engineering Reserve Plant Inspection Certificate?
What happens to the second-hand value of an article upon its return for inspection?
What happens to the second-hand value of an article upon its return for inspection?
What is essential when estimating costs for repairs that may not be undertaken immediately?
What is essential when estimating costs for repairs that may not be undertaken immediately?
What additional information must be included on the Advice Note when returning plant to the stores depot?
What additional information must be included on the Advice Note when returning plant to the stores depot?
In what condition may plant be transferred directly from one work to another without returning to the Reserve?
In what condition may plant be transferred directly from one work to another without returning to the Reserve?
Who holds the responsibility for maintaining records of receipts, issues, and balances in the Engineering Plant Reserve?
Who holds the responsibility for maintaining records of receipts, issues, and balances in the Engineering Plant Reserve?
What is the role of the Controller of Stores when new material is sent to the Reserve?
What is the role of the Controller of Stores when new material is sent to the Reserve?
What should be indicated on the Advice Notes accompanying the plant returned to the stores depot?
What should be indicated on the Advice Notes accompanying the plant returned to the stores depot?
What does the Chief Engineer determine concerning the transfer value of plant?
What does the Chief Engineer determine concerning the transfer value of plant?
What must be included in the records when material is either sent to or returned from the Engineering Plant Reserve?
What must be included in the records when material is either sent to or returned from the Engineering Plant Reserve?
What responsibility does the hirer have regarding inspection certificates while possessing the plant?
What responsibility does the hirer have regarding inspection certificates while possessing the plant?
What conditions allow the railway to recall the plant from the hirer?
What conditions allow the railway to recall the plant from the hirer?
Which of the following actions must be taken upon the return of the plant?
Which of the following actions must be taken upon the return of the plant?
How should the costs of repairs and replacements be managed if they exceed fair wear and tear?
How should the costs of repairs and replacements be managed if they exceed fair wear and tear?
What is required to assess the condition of the plant upon return?
What is required to assess the condition of the plant upon return?
What must be included in the agreement signed for hiring the plant?
What must be included in the agreement signed for hiring the plant?
Who monitors the recovery of hire and the return of the plant according to the procedures?
Who monitors the recovery of hire and the return of the plant according to the procedures?
When shall delivery of the hired plant be made?
When shall delivery of the hired plant be made?
What additional cost must be covered by the hiring department besides hire charges?
What additional cost must be covered by the hiring department besides hire charges?
What will be the supervision charges incurred by the railway during plant dispatch and receipt?
What will be the supervision charges incurred by the railway during plant dispatch and receipt?
In the event that plant material is carried by rail, what dictates the carriage charges?
In the event that plant material is carried by rail, what dictates the carriage charges?
What is the responsibility of the hirer regarding the return of the plant?
What is the responsibility of the hirer regarding the return of the plant?
What should occur before any inspection or repair work is initiated?
What should occur before any inspection or repair work is initiated?
What is a key requirement of the Engineering Reserve Plant Inspection Certificate?
What is a key requirement of the Engineering Reserve Plant Inspection Certificate?
How should the cost of repairs for items returned to the Plant Reserve be allocated?
How should the cost of repairs for items returned to the Plant Reserve be allocated?
Which authorization is needed to change items on the Engineering Plant Reserve list?
Which authorization is needed to change items on the Engineering Plant Reserve list?
When should the cost of repairs be estimated but not undertaken immediately?
When should the cost of repairs be estimated but not undertaken immediately?
Which of the following best describes the responsibility regarding costs during the inspection and repair of hired plant?
Which of the following best describes the responsibility regarding costs during the inspection and repair of hired plant?
What information should be transcribed into the Plant Reserve Register after estimating repair costs?
What information should be transcribed into the Plant Reserve Register after estimating repair costs?
What should be done with the expenditure on inspection and repairs when the work is debited on a hire basis?
What should be done with the expenditure on inspection and repairs when the work is debited on a hire basis?
What document should be obtained for all materials brought on or returned to the Reserve?
What document should be obtained for all materials brought on or returned to the Reserve?
What aspect should be indicated in the remarks section of the Engineering Reserve Plant Inspection Certificate?
What aspect should be indicated in the remarks section of the Engineering Reserve Plant Inspection Certificate?
What must accompany any requisitions placed on the Depot Officer by officials in charge of works?
What must accompany any requisitions placed on the Depot Officer by officials in charge of works?
What is the primary condition for hiring out items from the Engineering Plant Reserve to private parties?
What is the primary condition for hiring out items from the Engineering Plant Reserve to private parties?
Which detail is mandated to be marked on the issue notes for plants issued from the reserve?
Which detail is mandated to be marked on the issue notes for plants issued from the reserve?
What should be done with charges incurred from returning the plant to the stores depot?
What should be done with charges incurred from returning the plant to the stores depot?
What is indicated by the label 'Engineering Plant Reserve' on outgoing issue documents?
What is indicated by the label 'Engineering Plant Reserve' on outgoing issue documents?
What must be done when new material is added to the Engineering Plant Reserve?
What must be done when new material is added to the Engineering Plant Reserve?
What key detail must be reflected in the remarks section of the Engineering Reserve Plant Inspection Certificate?
What key detail must be reflected in the remarks section of the Engineering Reserve Plant Inspection Certificate?
Which responsibility does the Chief Engineer hold in relation to plants maintained in the Engineering Plant Reserve?
Which responsibility does the Chief Engineer hold in relation to plants maintained in the Engineering Plant Reserve?
What should be kept in mind regarding the items likely to be idle for a considerable time in the Reserve?
What should be kept in mind regarding the items likely to be idle for a considerable time in the Reserve?
What initial information is required on the Engineering Reserve Plant Inspection Certificate?
What initial information is required on the Engineering Reserve Plant Inspection Certificate?
Flashcards
Engineering Plant Reserve
Engineering Plant Reserve
A stock of construction equipment kept for future use.
Construction Plant Items
Construction Plant Items
Equipment for construction work.
Purpose of Reserve
Purpose of Reserve
Avoid losses from selling usable gear needed later.
Air Compressors
Air Compressors
Signup and view all the flashcards
Boilers
Boilers
Signup and view all the flashcards
Cranes
Cranes
Signup and view all the flashcards
Railway Board Approval
Railway Board Approval
Signup and view all the flashcards
Transfer of Plant to Reserve
Transfer of Plant to Reserve
Signup and view all the flashcards
Advice Note (S. 1539)
Advice Note (S. 1539)
Signup and view all the flashcards
Information in Advice Note
Information in Advice Note
Signup and view all the flashcards
Direct Transfer to New Project
Direct Transfer to New Project
Signup and view all the flashcards
Transfer Value
Transfer Value
Signup and view all the flashcards
Engineering Department Responsibility
Engineering Department Responsibility
Signup and view all the flashcards
Stores Department Responsibility
Stores Department Responsibility
Signup and view all the flashcards
Storage Location
Storage Location
Signup and view all the flashcards
Locating Reserve Plant
Locating Reserve Plant
Signup and view all the flashcards
Reserve Plant Number
Reserve Plant Number
Signup and view all the flashcards
Reserve Plant Register
Reserve Plant Register
Signup and view all the flashcards
Estimated Scrap Value
Estimated Scrap Value
Signup and view all the flashcards
Book Value on Receipt
Book Value on Receipt
Signup and view all the flashcards
Total Book Value
Total Book Value
Signup and view all the flashcards
Issue Notes
Issue Notes
Signup and view all the flashcards
Amount Debited on Issue
Amount Debited on Issue
Signup and view all the flashcards
Cost of Inspection and Repairs
Cost of Inspection and Repairs
Signup and view all the flashcards
Allocation of Inspection and Repair Costs
Allocation of Inspection and Repair Costs
Signup and view all the flashcards
Plant Reserve Usage in the Future
Plant Reserve Usage in the Future
Signup and view all the flashcards
Plant Hire Charges (A-2210)
Plant Hire Charges (A-2210)
Signup and view all the flashcards
Certificate of Inspection (Form S. 1919)
Certificate of Inspection (Form S. 1919)
Signup and view all the flashcards
Description of the Item
Description of the Item
Signup and view all the flashcards
Spares Included
Spares Included
Signup and view all the flashcards
Remarks
Remarks
Signup and view all the flashcards
Material Is Ready
Material Is Ready
Signup and view all the flashcards
Hire Charges
Hire Charges
Signup and view all the flashcards
Liability for Wear and Tear
Liability for Wear and Tear
Signup and view all the flashcards
Spares for Wearable Parts
Spares for Wearable Parts
Signup and view all the flashcards
Breakage or Loss of Parts (Other Than Wearable)
Breakage or Loss of Parts (Other Than Wearable)
Signup and view all the flashcards
Loss of the Entire Plant
Loss of the Entire Plant
Signup and view all the flashcards
Direct Transfer of Equipment
Direct Transfer of Equipment
Signup and view all the flashcards
Custody of the Reserve
Custody of the Reserve
Signup and view all the flashcards
Storage of Reserve Equipment
Storage of Reserve Equipment
Signup and view all the flashcards
Plant Reserve Management
Plant Reserve Management
Signup and view all the flashcards
Plant Transfer to Reserve
Plant Transfer to Reserve
Signup and view all the flashcards
Plant Reserve Issue
Plant Reserve Issue
Signup and view all the flashcards
Plant Hire Charges
Plant Hire Charges
Signup and view all the flashcards
Plant Inspection Certificate
Plant Inspection Certificate
Signup and view all the flashcards
Plant Reserve Number
Plant Reserve Number
Signup and view all the flashcards
Plant Reserve Register
Plant Reserve Register
Signup and view all the flashcards
Plant Reserve Cost Allocation
Plant Reserve Cost Allocation
Signup and view all the flashcards
Plant Reserve Disposal
Plant Reserve Disposal
Signup and view all the flashcards
What is the first step before repairing a plant reserve item?
What is the first step before repairing a plant reserve item?
Signup and view all the flashcards
Who pays for inspecting and repairing a returned plant reserve item?
Who pays for inspecting and repairing a returned plant reserve item?
Signup and view all the flashcards
What happens to inspection and repair costs when plant hire charges include all costs?
What happens to inspection and repair costs when plant hire charges include all costs?
Signup and view all the flashcards
What information should the Certificate of Inspection (Form S. 1919) include?
What information should the Certificate of Inspection (Form S. 1919) include?
Signup and view all the flashcards
What does the Certificate of Inspection (Form S. 1919) confirm?
What does the Certificate of Inspection (Form S. 1919) confirm?
Signup and view all the flashcards
What happens to the cost of spare parts for wearable items?
What happens to the cost of spare parts for wearable items?
Signup and view all the flashcards
Who is responsible for replacing worn-out parts during plant hire?
Who is responsible for replacing worn-out parts during plant hire?
Signup and view all the flashcards
Hirer's Responsibility
Hirer's Responsibility
Signup and view all the flashcards
Railway's Right of Recall
Railway's Right of Recall
Signup and view all the flashcards
Shared Repair Costs
Shared Repair Costs
Signup and view all the flashcards
What is the Engineering Plant Reserve?
What is the Engineering Plant Reserve?
Signup and view all the flashcards
Who can borrow equipment from the Reserve?
Who can borrow equipment from the Reserve?
Signup and view all the flashcards
How is equipment transferred to the Reserve?
How is equipment transferred to the Reserve?
Signup and view all the flashcards
What are the terms of delivery for borrowed equipment?
What are the terms of delivery for borrowed equipment?
Signup and view all the flashcards
What is the cost of borrowing equipment?
What is the cost of borrowing equipment?
Signup and view all the flashcards
Who manages the Engineering Plant Reserve?
Who manages the Engineering Plant Reserve?
Signup and view all the flashcards
Why is the Engineering Plant Reserve important?
Why is the Engineering Plant Reserve important?
Signup and view all the flashcards
What happens when equipment is borrowed from the Reserve?
What happens when equipment is borrowed from the Reserve?
Signup and view all the flashcards
How is the condition of equipment in the Reserve checked?
How is the condition of equipment in the Reserve checked?
Signup and view all the flashcards
What happens to equipment when it is no longer needed in the Reserve?
What happens to equipment when it is no longer needed in the Reserve?
Signup and view all the flashcards
Study Notes
Engineering Plant Reserve
- Purpose: Avoid losses from forced sales of usable plant leftover from special projects. A reserve is created to ensure needed plant is available for future use.
- Creation: Requires approval from the Railway Board, who set a maximum financial limit.
- Inventory: Includes construction plant, including:
- Air compressors
- Air receivers
- Boilers
- Boring equipment (hand or power)
- Concrete mixers
- Cranes (derrick scotch)
- Dregers
- Drilling machines (hand/power/pneumatic)
- Driving gear
- Portable steam engines
- Internal combustion engines
- Locomotive engines (2 ft gauge)
- Gantries for girder erection
- Pneumatic hammers (rock drilling)
- Hydraulic jacks
- Screw jacks
- Jolly boats
- Lathes (construction)
- Lorries (motor)
- Mortar mills (steam)
- Pumps and all types of pumping plants
- Pile driving frames
- Pile hammers (steam)
- Screwing machines
- Steam hoists
- Stone crushers
- Winches (crab/steam)
- Separate Stock: Stores departments should not keep separate stock of these items for new work (not normal railway operations).
- Transferring Plant: On completion of projects, engineers transfer unused plant to the nearest depot with additional info like type, maker, receipt date, and work allocation.
- Marked Advice Notes: Notes should be marked "Engineering Plant Reserve".
- Direct Transfer: Plant in good condition can be transferred to another project without returning to reserve, with chief engineer permission.
- Custody: Stores department is responsible for all reserve plant materials. They need to record receipts, issues and balances.
- Storage: Materials should be held near the workshop or loco shops if needed for repair, and separate records must exist.
- Plant Numbering: Each machine gets a unique "E.R." (Engineering Reserve) number, often matching the price list number, or an additional category number if multiple machines in the same category exist. A separate reserve plant register is also maintained.
- Inspection and Repairs: Plants returned to the depot need dismantling, repairs, and inspection. The Chief Engineer is responsible for arranging these.
- Cost Estimation: Before any work for inspection or repair (other than routine maintenance), cost estimates need Chief Engineer approval.
- Accounting of Hire Charges: The Controller of Stores manages recovery of hire charges and maintain records for each item.
- Priced Ledgers: Each plant has its own priced ledger, with receipt, issue, and balance info for accurate accounting.
- Posting to Ledger: Post entries related to plant reserve to the priced ledger, handling as single class for summaries.