Within how many days can a person apply for a review of an order of the Forum?

Thirty (30) days.

What is one circumstance under which a review of an order can be applied for?

If no appeal or representation has been preferred.

What must be clearly stated in the review application?

The matter or evidence not known or producible at the time of the order.

Who hears the review application?

<p>The same bench that issued the original Order.</p> Signup and view all the answers

Under what condition can a review application be heard by a different bench?

<p>If there is a retirement or demission of a member who passed the original order.</p> Signup and view all the answers

What must happen before a review application can be rejected?

<p>The applicant must be given an opportunity of being heard.</p> Signup and view all the answers

What happens if the Forum finds no sufficient ground for review?

<p>The Forum shall reject the review application.</p> Signup and view all the answers

What must the Forum provide before granting a review application?

<p>Previous notice to the opposite side or party.</p> Signup and view all the answers

What must accompany the review application?

<p>Documents, supporting data, and statements as required by the Forum.</p> Signup and view all the answers

What grounds can lead to the removal of an Electricity Ombudsman?

<p>An Electricity Ombudsman can be removed for reasons like insolvency, conviction of a moral turpitude offence, incapacity, conflict of interest, abuse of position, or misbehaviour.</p> Signup and view all the answers

What must the Commission do before removing an Electricity Ombudsman for specific reasons?

<p>The Commission must conduct an inquiry and conclude that the individual should be removed based on the grounds specified in clauses (d), (e), (f), and (g).</p> Signup and view all the answers

Which clause relates to the physical or mental capability of the Electricity Ombudsman?

<p>Clause (c) addresses the removal of an Ombudsman who has become physically or mentally incapable of performing their duties.</p> Signup and view all the answers

What is the implication of clause (b) regarding moral turpitude?

<p>Clause (b) allows for removal if the Ombudsman has been convicted of an offence involving moral turpitude, which indicates a breach of ethical conduct.</p> Signup and view all the answers

What does clause (d) refer to regarding interests of the Electricity Ombudsman?

<p>Clause (d) pertains to the Ombudsman acquiring financial or other interests that could adversely affect their functions.</p> Signup and view all the answers

What does clause (e) signify about the Ombudsman's position?

<p>Clause (e) indicates that the Ombudsman can be removed if they abuse their position to the detriment of the public interest.</p> Signup and view all the answers

What does clause (f) encompass concerning the Ombudsman's behaviour?

<p>Clause (f) encompasses removal for guilt of proved misbehaviour by the Ombudsman.</p> Signup and view all the answers

Which clause addresses the failure to perform assigned functions by the Ombudsman?

<p>Clause (g) specifically addresses the failure to deliver the assigned functions or exceeding their brief.</p> Signup and view all the answers

Why is it important for the Commission to formally record reasons for removing an Ombudsman?

<p>Recording reasons ensures transparency and accountability in the removal process, which upholds the integrity of the office.</p> Signup and view all the answers

What shall prevail in case of inconsistency between the Regulations and the Standards of Performance?

<p>The Standards of Performance shall prevail.</p> Signup and view all the answers

What does 'Act' refer to in the context of these Regulations?

<p>'Act' refers to the Electricity Act, 2003 (36 of 2003).</p> Signup and view all the answers

Who is considered a 'Complainant' under these Regulations?

<p>A Complainant is any Consumer who files a Complaint against the Distribution Licensee.</p> Signup and view all the answers

What constitutes a 'Complaint' as defined in the Regulations?

<p>A Complaint is a submission made by a consumer expressing dissatisfaction with the electricity supply service.</p> Signup and view all the answers

Define 'Grievance' in the context of these Regulations.

<p>A Grievance refers to any fault or inadequacy in the performance of services by a Distribution Licensee.</p> Signup and view all the answers

What is the 'Forum' mentioned in the Regulations?

<p>The Forum is established for the redressal of consumer Grievances against Distribution Licensees.</p> Signup and view all the answers

Who is the 'Electricity Ombudsman'?

<p>The Electricity Ombudsman is an authority appointed by the Commission to address grievances not resolved by the Forum.</p> Signup and view all the answers

What is the prerequisite for a consumer to file a 'Representation'?

<p>The consumer must be aggrieved by non-redressal of Grievances by the Forum within the specified time.</p> Signup and view all the answers

What qualifications does a 'Nodal Officer' have according to these Regulations?

<p>A Nodal Officer must have knowledge and experience in electricity distribution and cannot be below the rank of Executive Engineer.</p> Signup and view all the answers

What is required of the Distribution Licensee after an order from the Electricity Ombudsman?

<p>The Distribution Licensee must implement or comply with the order within the stipulated time frame.</p> Signup and view all the answers

What can the Complainant do if the Distribution Licensee does not comply with the Ombudsman's order?

<p>The Complainant can approach the Commission for enforcement within 30 days.</p> Signup and view all the answers

What constitutes non-compliance with the Electricity Ombudsman's orders?

<p>Non-compliance is deemed a violation of the Regulations and can incur actions by the Commission.</p> Signup and view all the answers

Who bears the expenses of the inspection undertaken by a third party as per Regulation 23.4?

<p>The Distribution Licensee bears the expenses.</p> Signup and view all the answers

Can a party appeal against the order of the Electricity Ombudsman before the Commission?

<p>No, no party can file an appeal before the Commission against the Ombudsman's order.</p> Signup and view all the answers

What is sent along with the order of the Electricity Ombudsman?

<p>Copies of the order are sent to the Complainant, the Distribution Licensee, and the concerned Forum.</p> Signup and view all the answers

What costs can a person requesting information from the Electricity Ombudsman expect to pay?

<p>They will pay no more than the cost of photocopying.</p> Signup and view all the answers

What happens if the Distribution Licensee fails to comply with an order?

<p>They may face appropriate action by the Commission under Sections 142 and 146 of the Electricity Act.</p> Signup and view all the answers

Under what circumstance can commercial confidence information be disclosed according to Regulation 24.2?

<p>If the Electricity Ombudsman believes it serves a larger public interest.</p> Signup and view all the answers

What is not required from applicants when requesting information from the Electricity Ombudsman?

<p>They are not required to provide reasons or personal details.</p> Signup and view all the answers

What time frame must the Distribution Licensee comply with the Ombudsman's order?

<p>The Compliance must be made within the time frame stipulated in the order.</p> Signup and view all the answers

Who must the Distribution Licensee inform regarding compliance with the order?

<p>The Distribution Licensee must inform the Electricity Ombudsman.</p> Signup and view all the answers

What type of information does Regulation 24.2(b) state will not be disclosed?

<p>Information that would impede investigations or prosecutions.</p> Signup and view all the answers

What actions might the Commission take against the Distribution Licensee for non-compliance?

<p>The Commission may impose fines and penalties or take other enforcement steps.</p> Signup and view all the answers

Which regulation outlines the expenses for inspections by third parties?

<p>Regulation 23.4.</p> Signup and view all the answers

What should the Electricity Ombudsman consider before disclosing sensitive information?

<p>The larger public interest.</p> Signup and view all the answers

What type of information is protected from disclosure to maintain competitive positions?

<p>Trade secrets and intellectual property.</p> Signup and view all the answers

Is the obligation to disclose information absolute according to Regulation 24?

<p>No, there are exceptions regarding sensitive information.</p> Signup and view all the answers

Study Notes

Regulations Overview

  • Regulations align harmoniously with the Standards of Performance for Distribution Licensees as well as the Electricity Supply Code.
  • In case of inconsistencies, the Standards of Performance and the Electricity Supply Code take precedence.

Key Definitions

  • Act: Refers to the Electricity Act, 2003 (36 of 2003).
  • Commission: Refers to the Maharashtra Electricity Regulatory Commission.
  • Complainant: Any consumer or prospective consumer filing a complaint against their Distribution Licensee.
  • Complaint: Expression of dissatisfaction regarding electricity supply by the Distribution Licensee.
  • Grievance: Any inadequacy or defect in services provided by a Distribution Licensee, including non-compliance with regulatory orders.

Forums and Authorities

  • Forum: A grievance redressal mechanism established by Distribution Licensees under Section 42(5) of the Act.
  • Electricity Ombudsman: An authority designated by the Commission to address non-redressal of grievances by the Forum.

Review Process

  • A review application can be filed by any aggrieved party within 30 days of the Forum's order under certain conditions:
    • Absence of prior appeal or representation.
    • Discovery of new important evidence post-order.
    • Demonstration of an obvious mistake within the order.
  • Review hearings take place with the same bench that issued the original order unless otherwise permitted.

Grounds for Removing the Electricity Ombudsman

  • Removal can occur if the Ombudsman:
    • Becomes insolvent or convicted of morally improper offenses.
    • Loses capability to fulfill duties due to physical or mental reasons.
    • Has conflicts of interest affecting impartiality.
    • Misbehaves or fails to perform assigned functions.

Compliance and Enforcement

  • Orders from the Electricity Ombudsman are binding on all parties and must be implemented promptly.
  • Non-compliance could lead to violations under Sections 142 and 146 of the Electricity Act, 2003.
  • Complainants can seek enforcement from the Commission if orders are not followed within stipulated timelines.

Right to Information

  • Individuals can request copies of Ombudsman orders without needing to justify their request.
  • Certain information may be withheld to protect commercial interests or during investigations.

Inspection Costs

  • Inspection expenses related to third-party inspections are borne by the Distribution Licensee; costs may factor into tariff determinations if deemed reasonable.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Description

This quiz explores the regulations and standards of performance for distribution licensees under the Electricity Supply Code. It focuses on understanding the principles governing the harmonization of these regulations with existing guidelines. Test your knowledge about the relevant provisions and their applications.

Use Quizgecko on...
Browser
Browser