Podcast
Questions and Answers
Which document should receive the Owner's approval before implementing Procurement requirements?
Which document should receive the Owner's approval before implementing Procurement requirements?
- The Contractor's Qualification Statement (A305)
- The Owner/Contractor Agreement (A101)
- The General Conditions (A201)
- Any document prepared by the Architect (correct)
Which of the following statements about Procurement requirements is true?
Which of the following statements about Procurement requirements is true?
- They should be prepared by the Architect without the Owner's assistance
- They should include duplicated operative figures also listed in the Contract Documents
- They do not become Contract Documents, except in special circumstances (correct)
- They become Contract Documents
Which of the following is NOT listed as a Contract Document?
Which of the following is NOT listed as a Contract Document?
- Addenda
- Contractor's Qualification Statement (A305) (correct)
- Contract Drawings
- Specifications
What is the purpose of the Contractor's Qualification Statement (A305)?
What is the purpose of the Contractor's Qualification Statement (A305)?
Which document should the Architect prepare the first draft of, according to the text?
Which document should the Architect prepare the first draft of, according to the text?
What type of insurance coverage is specifically mentioned for the Architect?
What type of insurance coverage is specifically mentioned for the Architect?
Which of the following statements about operative figures (e.g. dollar amounts, times, dates, etc.) is true?
Which of the following statements about operative figures (e.g. dollar amounts, times, dates, etc.) is true?
Which of the following is NOT listed as part of the Contract Documents?
Which of the following is NOT listed as part of the Contract Documents?
What impacts does the Date of Substantial Completion have?
What impacts does the Date of Substantial Completion have?
What happens when the Contractor believes they have reached final completion?
What happens when the Contractor believes they have reached final completion?
What does the Architect do after receiving all closeout documents from the Contractor?
What does the Architect do after receiving all closeout documents from the Contractor?
What does the Architect prepare after verifying final completion of the Work?
What does the Architect prepare after verifying final completion of the Work?
When does the Construction phase formally end according to the provided text?
When does the Construction phase formally end according to the provided text?
What does the Architect signify by issuing the Final Certificate for Payment?
What does the Architect signify by issuing the Final Certificate for Payment?
When do Architect's CA services officially end as per the text?
When do Architect's CA services officially end as per the text?
What should be included in the Project Closeout Documents?
What should be included in the Project Closeout Documents?
What is the consequence if the Owner fails to purchase and maintain required property insurance?
What is the consequence if the Owner fails to purchase and maintain required property insurance?
Under what conditions can the Contractor terminate the contract?
Under what conditions can the Contractor terminate the contract?
What is the consequence if the Contractor terminates the contract due to the conditions mentioned in the text?
What is the consequence if the Contractor terminates the contract due to the conditions mentioned in the text?
What happens if the Work has stopped for a period of 60 days because the Owner has repeatedly failed to fulfill their obligations?
What happens if the Work has stopped for a period of 60 days because the Owner has repeatedly failed to fulfill their obligations?
What happens if the Owner suspends the Work for 15 days?
What happens if the Owner suspends the Work for 15 days?
What is the nature of the relationship between the Contractor and the Owner?
What is the nature of the relationship between the Contractor and the Owner?
Which of the following is NOT a role of the Construction Manager-Constructor (CM-C) in advising the project team?
Which of the following is NOT a role of the Construction Manager-Constructor (CM-C) in advising the project team?
In the bidding and negotiations phase, what is the CM-C responsible for providing?
In the bidding and negotiations phase, what is the CM-C responsible for providing?
What is the primary reason for the architect to review the CM-C's scope of work before issuance for bidding?
What is the primary reason for the architect to review the CM-C's scope of work before issuance for bidding?
Why might an architect's fees and scope need to be increased for a CM-C project?
Why might an architect's fees and scope need to be increased for a CM-C project?
In a Multiple Prime Contractor delivery method, what level of Spearin Risk does the Owner carry?
In a Multiple Prime Contractor delivery method, what level of Spearin Risk does the Owner carry?
What is a potential advantage of using the Multiple Prime Contractor delivery method?
What is a potential advantage of using the Multiple Prime Contractor delivery method?
Which statement best describes the role of the A101 agreement in a Multiple Prime Contractor project?
Which statement best describes the role of the A101 agreement in a Multiple Prime Contractor project?
What is a crucial aspect of document tracking in a CM-C project, particularly with early or multiple release packages?
What is a crucial aspect of document tracking in a CM-C project, particularly with early or multiple release packages?
Which project delivery method places the highest amount of Spearin Gap risk on the Owner?
Which project delivery method places the highest amount of Spearin Gap risk on the Owner?
Which project delivery method theoretically carries less Spearin Gap risk than Design-Bid-Build for the Owner?
Which project delivery method theoretically carries less Spearin Gap risk than Design-Bid-Build for the Owner?
Which type of project is Construction Manager most advantageous for?
Which type of project is Construction Manager most advantageous for?
What is the main role of a CM-Advisor (A132)?
What is the main role of a CM-Advisor (A132)?
Which project delivery method has no Spearin Gap risk for the Owner?
Which project delivery method has no Spearin Gap risk for the Owner?
Which project delivery method is good for fast-track projects and allows for early trade release?
Which project delivery method is good for fast-track projects and allows for early trade release?
Which project delivery method has a contractual relationship between the Construction Manager and the Architect or Contractor?
Which project delivery method has a contractual relationship between the Construction Manager and the Architect or Contractor?
Which project delivery method is best suited for very large or overly complex projects?
Which project delivery method is best suited for very large or overly complex projects?