Podcast
Questions and Answers
What is the primary purpose of the Negotiation process in Contract Formulation?
What is the primary purpose of the Negotiation process in Contract Formulation?
What is the primary output of the Signing of Contract Agreement process?
What is the primary output of the Signing of Contract Agreement process?
What is included in a Construction Contract Document?
What is included in a Construction Contract Document?
What is the primary goal of Contract Administration?
What is the primary goal of Contract Administration?
Signup and view all the answers
What is the relationship between Contract Formulation and Contract Administration?
What is the relationship between Contract Formulation and Contract Administration?
Signup and view all the answers
What is the primary responsibility of Stakeholders in Contract Administration?
What is the primary responsibility of Stakeholders in Contract Administration?
Signup and view all the answers
What is the process that ensures the successful completion of the project under consideration?
What is the process that ensures the successful completion of the project under consideration?
Signup and view all the answers
What is included in the activities or tasks of Contract Administration services?
What is included in the activities or tasks of Contract Administration services?
Signup and view all the answers
What is the primary challenge of a Contract Administrator?
What is the primary challenge of a Contract Administrator?
Signup and view all the answers
What is the primary focus of the Maintenance Period?
What is the primary focus of the Maintenance Period?
Signup and view all the answers
What is the purpose of the Completion Certificate?
What is the purpose of the Completion Certificate?
Signup and view all the answers
What is the role of the Closing of Accounts phase?
What is the role of the Closing of Accounts phase?
Signup and view all the answers
What are the two most important issues in Contract Changes Management?
What are the two most important issues in Contract Changes Management?
Signup and view all the answers
What is the purpose of the Provisional Certificate of Completion?
What is the purpose of the Provisional Certificate of Completion?
Signup and view all the answers
What is the typical duration of the Maintenance Period?
What is the typical duration of the Maintenance Period?
Signup and view all the answers
What is the purpose of remedial works during the Maintenance Period?
What is the purpose of remedial works during the Maintenance Period?
Signup and view all the answers
What is the purpose of Clauses 51 and 52 of the General Conditions of FIDIC Red Book?
What is the purpose of Clauses 51 and 52 of the General Conditions of FIDIC Red Book?
Signup and view all the answers
What can requirement changes cause?
What can requirement changes cause?
Signup and view all the answers
What is a unilateral change order?
What is a unilateral change order?
Signup and view all the answers
What is the purpose of a change order?
What is the purpose of a change order?
Signup and view all the answers
What happens when a contractor is entitled to request and agree upon new or existing rates for changes?
What happens when a contractor is entitled to request and agree upon new or existing rates for changes?
Signup and view all the answers
What is a bilateral change order?
What is a bilateral change order?
Signup and view all the answers
How can requirement changes modify contracts?
How can requirement changes modify contracts?
Signup and view all the answers
What type of contract is suitable for construction works where contractors have prior experience?
What type of contract is suitable for construction works where contractors have prior experience?
Signup and view all the answers
Why are cost plus contracts used in certain situations?
Why are cost plus contracts used in certain situations?
Signup and view all the answers
What is the main advantage of cost plus fixed fee contracts?
What is the main advantage of cost plus fixed fee contracts?
Signup and view all the answers
When is a cost plus percentage contract preferred?
When is a cost plus percentage contract preferred?
Signup and view all the answers
How is the fee determined in a cost plus fixed fee contract?
How is the fee determined in a cost plus fixed fee contract?
Signup and view all the answers
Why is it essential to define the scope of work for a cost plus fixed fee contract?
Why is it essential to define the scope of work for a cost plus fixed fee contract?
Signup and view all the answers
What is a key factor in selecting a contractor for a cost plus fixed fee contract?
What is a key factor in selecting a contractor for a cost plus fixed fee contract?
Signup and view all the answers
What type of contracts are used in situations where the amount of effort required depends on another contractor's work?
What type of contracts are used in situations where the amount of effort required depends on another contractor's work?
Signup and view all the answers
What is the primary effect of time extension in a project?
What is the primary effect of time extension in a project?
Signup and view all the answers
What is the condition for a project doer to be entitled to compensation and time extension?
What is the condition for a project doer to be entitled to compensation and time extension?
Signup and view all the answers
What is the purpose of acceleration in a project?
What is the purpose of acceleration in a project?
Signup and view all the answers
What is the process for claiming compensation and time extension?
What is the process for claiming compensation and time extension?
Signup and view all the answers
Why is entitlement to compensation associated with causes of delay?
Why is entitlement to compensation associated with causes of delay?
Signup and view all the answers
What is the relationship between delay and disruption clauses in the Conditions of Contract?
What is the relationship between delay and disruption clauses in the Conditions of Contract?
Signup and view all the answers
Study Notes
Contract Types and Management
- Cost-plus contracts are used in situations where it's difficult or impossible to predict costs during the negotiation, bid, and award process.
- Factors that make cost calculation impossible include unpredictable weather, remote locations, combat, or war, and contracts dependent on another contractor's work.
Cost-Plus Fixed Fee Contract
- A cost-plus fixed fee contract is desirable when the scope and nature of the work can be broadly defined.
- The fee amount is determined as a lump sum based on the scope of work, approximate cost, nature of work, estimated time of construction, manpower, and equipment requirements.
Contract Formulation
- Involves two sub-processes: Negotiation and Signing of Contract Agreement.
- Negotiation is a process where project owners and their representatives deal with the recommended winner of the tender to agree on the requirements.
- Contract agreement is signed, forming the contract document that serves as the basis for contract administration.
Contract Administration
- Ensures the successful completion of the project under consideration with substantial compliance of the Terms of the Contract.
- Activities included in Contract Administration services:
- Identifying contractual responsibilities of stakeholders
- Monitoring and influencing the contractor's activities without jeopardizing the owner's interests
- Ensuring compliance with the terms of the contract
Closing of Contract
- Involves issues related to Maintenance Period and Remedial works, dealing with Left Over Claims and Disputes, and Closing of Accounts.
- Maintenance Period usually lasts one year, focusing on quality problems overseen by supervisors.
- Left Over Claims and Disputes are settled during this phase.
Contract Changes Management
- Uncertainties and Changes are the two most important issues considered in contract change management.
- Clauses 51 and 52 of the General Conditions of FIDIC Red Book provide provisions for Alterations (Additions and Omissions).
- Requirement changes can be additional or excess, and the contractor is entitled to request and agree upon new or existing rates for such changes.
Change Orders
- Written instructions directing the Project Doer to make changes with or without the Consent of Regulatory Bodies.
- There are three kinds of Change Orders:
- Unilateral Change Order: provides the right to any party to make changes without affecting the other parties.
- Bilateral Change Order: requires the agreement and consent of the two contracting parties.
- Multilateral Change Order: requires the agreement and consent of three or more contracting parties.
Time and Cost Changes
- Requirement changes based on the different types of change orders modify contracts in one of or a combination of the following ways:
- Time changes only
- Time changes accompanied by Cost Compensations
- Cost Changes only
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
This quiz covers the different types of contracts used in construction, including cost-plus contracts, and their suitability for various projects.