Contracts and Claims - 1999
24 Questions
4 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

In which FIDIC 1999 form is the Contract administered by the Engineer appointed by the Employer?

  • Red Book (correct)
  • Yellow Book
  • Silver Book
  • None of the above
  • Which FIDIC 1999 form is recommended for building and engineering works if most (or all) of the works are to be designed by (or on behalf of) the Contractor?

  • Red Book
  • Yellow Book (correct)
  • Silver Book
  • None of the above
  • For which type of project is the FIDIC 1999 Silver Book suitable?

  • Infrastructure project
  • Building and engineering works with Employer's design
  • Process or power plant (correct)
  • None of the above
  • Under which FIDIC 1999 form does the Employer (unless appointing an Employer's Representative) administer the Contract and endeavor to reach agreement with the Contractor on each claim?

    <p>Silver Book</p> Signup and view all the answers

    What is the consequence of the Employer taking early possession without consent?

    <p>The Contractor is entitled to an extension of time</p> Signup and view all the answers

    What is the Contractor entitled to if the Employer suspends work due to default?

    <p>An extension of time</p> Signup and view all the answers

    What is the consequence of the Employer's risk?

    <p>The Contractor is entitled to additional payment</p> Signup and view all the answers

    When can the Contractor consider themselves entitled to an Extension of Time (EOT) or extra payment?

    <p>After 42 days notice for a fully detailed claim</p> Signup and view all the answers

    What is the consequence of an unforeseeable condition?

    <p>The Contractor is entitled to an extension of time</p> Signup and view all the answers

    What is the Contractor's entitlement if the Employer terminates the contract at will?

    <p>Immediate payment in full</p> Signup and view all the answers

    What is the consequence of a prolonged prevention of performance?

    <p>The Contractor is released from the contract</p> Signup and view all the answers

    What is the Contractor's entitlement if performance is impossible, unlawful, or released by law?

    <p>Immediate termination of the contract</p> Signup and view all the answers

    Who is responsible for executing the works in accordance with the Contract and Engineer's instructions?

    <p>The Contractor</p> Signup and view all the answers

    How are interim and final payments certified?

    <p>Based on actual quantities of works and rates in the Bill of Quantities</p> Signup and view all the answers

    What triggers the Employer's claims procedures?

    <p>Performance security</p> Signup and view all the answers

    What are the Contractor's claims procedures related to?

    <p>Delayed drawings</p> Signup and view all the answers

    What restricts the Employer's common law right to set off?

    <p>Sub-Clause 2.5</p> Signup and view all the answers

    What determines the allocation of risks between parties?

    <p>Insurability, project management principles, and ability to foresee and mitigate circumstances</p> Signup and view all the answers

    Where are the Employer's Claims procedures outlined?

    <p>Sub-Clause 2.5</p> Signup and view all the answers

    What is the role of the Dispute Adjudication Board (DAB) in resolving disputes?

    <p>It resolves disputes</p> Signup and view all the answers

    What are the Employer's options in case of determined amounts to be deducted?

    <p>Make a separate claim against the Contractor</p> Signup and view all the answers

    What do Tenderers require more of to evaluate risks?

    <p>Data on Site conditions and time</p> Signup and view all the answers

    What is specified for Contractor's claims depending on the event triggering the claim?

    <p>Different types of costs and profits</p> Signup and view all the answers

    What does the provisions cover related to termination?

    <p>Costs for completion, losses, and damages</p> Signup and view all the answers

    Study Notes

    Construction Contract Provisions and Claims Procedures

    • Disputes are resolved through a Dispute Adjudication Board (DAB)
    • The Contractor is responsible for executing the works in accordance with the Contract and Engineer's instructions
    • Interim and final payments are certified by the Engineer based on actual quantities of works and rates in the Bill of Quantities
    • Risks are allocated between parties based on insurability, project management principles, and ability to foresee and mitigate circumstances
    • Tenderers require more data on Site conditions and time to evaluate risks
    • Employer's Claims procedures are outlined in Sub-Clause 2.5 and involve discussions with the Engineer and the Contractor
    • The Employer has options to deduct determined amounts from payment certificates or make a separate claim against the Contractor
    • The Employer's common law right to set off is restricted under Sub-Clause 2.5
    • Various events trigger Employer's claims procedures, including performance security, failure to pass tests, and termination
    • Contractor's claims procedures involve events such as delayed drawings, late access to the site, and setting-out errors
    • Different types of costs and profits are specified for Contractor's claims, depending on the event triggering the claim
    • The provisions cover insurance for works and Contractor's equipment, termination, and costs for completion, losses, and damages

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Test your knowledge of construction contract provisions, claims procedures, and the responsibilities of the employer and contractor. Explore topics such as dispute resolution, payment certification, risk allocation, and various events triggering claims procedures.

    More Like This

    R 2017 - 19
    37 questions

    R 2017 - 19

    AstoundedHamster avatar
    AstoundedHamster
    Claims in Construction Contracts
    34 questions
    Use Quizgecko on...
    Browser
    Browser