Podcast
Questions and Answers
The Executed Agreement is subordinate to the General Specifications in governing the contract.
The Executed Agreement is subordinate to the General Specifications in governing the contract.
False (B)
The General Conditions include provisions for payment terms and hold-backs.
The General Conditions include provisions for payment terms and hold-backs.
True (A)
Quality assurance and dealing with defective work are not mentioned in the General Conditions.
Quality assurance and dealing with defective work are not mentioned in the General Conditions.
False (B)
The Supplementary General Conditions provide site-specific instructions for the project.
The Supplementary General Conditions provide site-specific instructions for the project.
The General Conditions address security measures required for the project.
The General Conditions address security measures required for the project.
Issued for Review (IFR) drawings are not intended to be modified by the design engineer.
Issued for Review (IFR) drawings are not intended to be modified by the design engineer.
Issued for Tender (IFT) drawings are finalized and cannot change during the tendering phase.
Issued for Tender (IFT) drawings are finalized and cannot change during the tendering phase.
It is crucial to reference the correct drawings during construction to avoid potential issues.
It is crucial to reference the correct drawings during construction to avoid potential issues.
Issued for Construction drawings are the final drawings used by the contractor to proceed with the construction.
Issued for Construction drawings are the final drawings used by the contractor to proceed with the construction.
Detailed Technical Specifications include payments for each completed activity.
Detailed Technical Specifications include payments for each completed activity.
The numbering of Divisions and Sections changes from project to project.
The numbering of Divisions and Sections changes from project to project.
Bidders are allowed to submit incomplete bids if they provide the necessary documents later.
Bidders are allowed to submit incomplete bids if they provide the necessary documents later.
Addenda are used to provide additional information after the bid has been submitted.
Addenda are used to provide additional information after the bid has been submitted.
Unit Prices provided by contractors become the basis for prices if their bid is awarded.
Unit Prices provided by contractors become the basis for prices if their bid is awarded.
The Form of Agreement outlines the terms and conditions that both parties must follow.
The Form of Agreement outlines the terms and conditions that both parties must follow.
Specific instructions on how to submit a bid are optional for bidders to follow.
Specific instructions on how to submit a bid are optional for bidders to follow.
General Conditions govern over Specifications in the hierarchy of documents.
General Conditions govern over Specifications in the hierarchy of documents.
Corporate seals are required on bid documents to validate the submission.
Corporate seals are required on bid documents to validate the submission.
Phase VI refers to the stage of Project Closure and Signoff.
Phase VI refers to the stage of Project Closure and Signoff.
A Request For Proposal is primarily used to obtain price quotations.
A Request For Proposal is primarily used to obtain price quotations.
Bidding Documents can be posted on social media platforms.
Bidding Documents can be posted on social media platforms.
The National Master Specification is a collection of procedures used solely in environmental construction practices.
The National Master Specification is a collection of procedures used solely in environmental construction practices.
A Request For Quotation can sometimes be used interchangeably with a Request For Proposal.
A Request For Quotation can sometimes be used interchangeably with a Request For Proposal.
Contract Specifications are meant to provide general guidelines without specific procedures.
Contract Specifications are meant to provide general guidelines without specific procedures.
The Engineer's Stamp is a requirement in the sign-off process for project closure.
The Engineer's Stamp is a requirement in the sign-off process for project closure.
Bidding Documents are posted exclusively on government websites.
Bidding Documents are posted exclusively on government websites.
Environmental measures in specifications for construction contracts are less emphasized than typical contracts.
Environmental measures in specifications for construction contracts are less emphasized than typical contracts.
Bidders should provide prices for contingencies to protect the client from additional change orders.
Bidders should provide prices for contingencies to protect the client from additional change orders.
The role of a site professional includes ensuring compliance with health and safety regulations.
The role of a site professional includes ensuring compliance with health and safety regulations.
As-built drawings are not required in the closure report after remedial activities.
As-built drawings are not required in the closure report after remedial activities.
Daily reports are optional for site professionals during the project.
Daily reports are optional for site professionals during the project.
Phase I Environmental Site Assessments primarily involve field work.
Phase I Environmental Site Assessments primarily involve field work.
Phase II Environmental Site Assessments determine the pathways and receptors of contaminants.
Phase II Environmental Site Assessments determine the pathways and receptors of contaminants.
Phase III focuses on fine-tuning the assessment by outlining spatial relationships of known contaminants.
Phase III focuses on fine-tuning the assessment by outlining spatial relationships of known contaminants.
The Remedial Action Plan (RAP) is defined as a strategy for immediate site cleanup without regard to regulatory frameworks.
The Remedial Action Plan (RAP) is defined as a strategy for immediate site cleanup without regard to regulatory frameworks.
Implementability is one of the considerations during the remedial design phase in Phase IV.
Implementability is one of the considerations during the remedial design phase in Phase IV.
Phase V of the Environmental Site Assessments focuses solely on documentation and reporting.
Phase V of the Environmental Site Assessments focuses solely on documentation and reporting.
The outcome of Phase IV indicates that the site is clean to the present standards.
The outcome of Phase IV indicates that the site is clean to the present standards.
Phase I Environmental Site Assessment outcomes concern the likelihood of having a problem at the site.
Phase I Environmental Site Assessment outcomes concern the likelihood of having a problem at the site.
Flashcards
Phase I Environmental Site Assessment
Phase I Environmental Site Assessment
A preliminary investigation to assess the likelihood of environmental contamination at a site.
Phase II Environmental Site Assessment
Phase II Environmental Site Assessment
Field work involving sampling and characterizing potentially contaminated site media.
Phase III Environmental Site Assessment
Phase III Environmental Site Assessment
A detailed assessment to fully characterize the site, including all contaminants and their spatial relationships.
Phase IV Environmental Site Assessment
Phase IV Environmental Site Assessment
Signup and view all the flashcards
Phase V - Implementation
Phase V - Implementation
Signup and view all the flashcards
Remediation
Remediation
Signup and view all the flashcards
Regulatory Framework
Regulatory Framework
Signup and view all the flashcards
Remediation Considerations
Remediation Considerations
Signup and view all the flashcards
Request For Proposal (RFP)
Request For Proposal (RFP)
Signup and view all the flashcards
Request For Quotation (RFQ)
Request For Quotation (RFQ)
Signup and view all the flashcards
National Master Specification (NMS)
National Master Specification (NMS)
Signup and view all the flashcards
Construction Documents
Construction Documents
Signup and view all the flashcards
Where are bidding documents posted?
Where are bidding documents posted?
Signup and view all the flashcards
Where do you post bidding documents?
Where do you post bidding documents?
Signup and view all the flashcards
Bidding Documents
Bidding Documents
Signup and view all the flashcards
What are General Conditions?
What are General Conditions?
Signup and view all the flashcards
What are Supplementary General Conditions?
What are Supplementary General Conditions?
Signup and view all the flashcards
What document takes precedence in a construction contract?
What document takes precedence in a construction contract?
Signup and view all the flashcards
What do General Specifications cover?
What do General Specifications cover?
Signup and view all the flashcards
What are the provisions for unexpected discoveries during construction?
What are the provisions for unexpected discoveries during construction?
Signup and view all the flashcards
Detailed Technical Specifications
Detailed Technical Specifications
Signup and view all the flashcards
Issued for Review (IFR)
Issued for Review (IFR)
Signup and view all the flashcards
Issued for Tender (IFT)
Issued for Tender (IFT)
Signup and view all the flashcards
Issued for Construction (IFC)
Issued for Construction (IFC)
Signup and view all the flashcards
Using the Correct Drawings
Using the Correct Drawings
Signup and view all the flashcards
Detailed Stamped Engineering Drawings
Detailed Stamped Engineering Drawings
Signup and view all the flashcards
Environmental Management Plan (EMP)
Environmental Management Plan (EMP)
Signup and view all the flashcards
Environmental Protection Plan (EPP)
Environmental Protection Plan (EPP)
Signup and view all the flashcards
Role of Site Professional
Role of Site Professional
Signup and view all the flashcards
Closure Report
Closure Report
Signup and view all the flashcards
Consistent Numbering System
Consistent Numbering System
Signup and view all the flashcards
Key Requirements in Instructions to Bidders
Key Requirements in Instructions to Bidders
Signup and view all the flashcards
Instruction to Bidders Processes
Instruction to Bidders Processes
Signup and view all the flashcards
Cost Section in Bid Documents
Cost Section in Bid Documents
Signup and view all the flashcards
Original Corporate Seals in Bid Forms
Original Corporate Seals in Bid Forms
Signup and view all the flashcards
Form of Agreement in Bid Documents
Form of Agreement in Bid Documents
Signup and view all the flashcards
General Conditions in Contract Documents
General Conditions in Contract Documents
Signup and view all the flashcards
General Conditions: Definitions and Roles
General Conditions: Definitions and Roles
Signup and view all the flashcards
Study Notes
Phase I Environmental Site Assessments
- Review of existing information, commonly including records review (multiple sources), aerial photography, site visits, and interviews
- Reporting is crucial
- Outcome: Determine if there's a likely problem at the site (Desktop Exercise)
Phase II Environmental Site Assessments
- Field Work is key, involving site characterization for potentially contaminated media.
- Sampling of site media is performed.
- Pathways and receptors are determined.
- Outcome: Identify contaminants, their location, concentration, and types at the site.
Phase III Environmental Site Assessments
- Detailed assessment of the site for characterized contaminants and their relationships.
- Pathways and receptors are further clarified.
- Remedial and risk assessment inputs are identified.
- Outcome: All required inputs for a remedial plan determination (Go out to know more if required)
Phase IV Environmental Site Assessments
- Remedial Action Plan (RAP) implementation, defining the process of bringing site media to acceptable regulatory levels.
- Remedial design phase involves identifying, evaluating, and selecting best options, using criteria, matrices, etc.
- Considerations include implementability, climate, cost, and timeframes.
- Outcome: Job is finished, site is clean, following the current standards. Phase IV is outdated term.
Phase V - Implementation
- Implementation of plans, specifications, health, and safety procedures.
- Phase V is outdated term.
Phase VI - Closure and Signoff
- Project Closure
- Sign Off (with Engineer's Stamp and Client signatures)
- Phase VI is outdated term.
Types of Documents
- RFP (Request for Proposal): A procurement document requesting proposals from prospective sellers of products or services.
- RFQ (Request for Quotation): A type of procurement document used to request price quotations from sellers of common or standard products or services
Construction Documents
- Tenders: Proposals to undertake or manage construction projects
Bidding Documents
- Various sources, for example, newspapers, social media, websites (like Nova Scotia Tender Notices, MERX - Canadian Public Tenders, Construction Association of Nova Scotia)
Contract Specifications
- National Master Specification (NMS): A comprehensive text base for project procedures, products, and methods.
- Utilizes editing to suit project requirements.
- Developed by Public Services and Procurement Canada within the National Master Specification Secretariat (NMSS).
- Includes environmentally responsible material and work practices.
- A hyperlinked, bilingual, generic construction specification (available commercially in North America).
Instruction to Bidders
- Key Requirements: How, When, Where, What
- Very Prescribed format required
- Incomplete bids if not followed carefully
Instruction To Bidders (queries & clarifications)
- Process
- Addenda (Singular form Addendum)
- Revisions & modifications of key information
- Site visits
- Bidder Briefing (Mandatory/Non-mandatory)
- Bid Submission (Specific instructions, forms and envelopes)
Unit Price Bid Form
- Provides a schedule of quantities and unit prices for construction work as defined by the project.
Bid Forms (general)
- Detailed outline of frequently used bid forms, such as Tender Price Amendment Form, Appendix A/B/C/D/E/F/G, Form of Agreement, General Conditions, and more.
Drawings
- The importance of using correct drawings
- Issued for Review (IFR) are used for stakeholder review prior to tender.
- Issued for Tendering (IFT) used for contractors for pricing purposes.
- Issued for Construction (IFC) are actual drawings used for construction.
General Conditions (cont'd)
- Detailed descriptions of responsibilities, terms, adherence to laws/regulations, liabilities, resolving disputes, quality assurance, defective work/supplies, time extensions (warranties, insurance, bonds, permits)
Supplementary General Conditions
- Instructions specific to each project and encompassing requirements of drawings and documents to be on site, co-operation, procedures, utilities, progress meetings, examinations, intents, notices, permits, contractor insurance, and security.
Supplementary General Conditions (cont'd)
- General instructions for work, including approval of materials, debris control, site access, quality of workmanship, fossils/artifacts.
Bonding
- Security requirements include bid deposits, certified cheques, performance guarantees, and indemnity bonds.
Insurance Requirements
- Insurance requirements, including general liability, automobile liability, all-risk builder's risk (from a third-party perspective, for property damage, defence costs, personal injuries, and the extended discovery period), with insurance amounts depending on project size.
General Requirements
- Lists the various topics associated with a construction project, from work summaries and restrictions to payments, testing, progress scheduling, and more, to closeout procedures. Include items associated with health, environmental, quality control and assurance procedures, and temporary/permanent facilities.
General Comments
- The stress on environmental measures in specifications is notable
- Contingency pricing in bids must be included.
- Bidders must include data such as borehole/test pit logs, laboratory analyses, geotechnical reports, and pre-existing ESA reports.
Role of Site Professional
- Ensuring compliance with safety and environmental plans, creating daily reports, collecting and sharing images/videos, and handling incident reports.
- Liaising between the client and contractor.
Closure
- Preparing closure reports, detailing remedial activities, verifying sample results, assessing objective achievement, monitoring variance, and creating as-built drawings.
- The report should suggest performance-monitoring plans, certificates, completion details, and correspondence letters and related documents.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.