COMMON CAUSES OF CLAIMS
45 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What defines extra work claims in a construction context?

  • Routine tasks included in the contract
  • Requests for tasks that were not originally stated in the contract (correct)
  • Changes in project timing due to weather conditions
  • Tasks delegated to subcontractors before the contract signing
  • What typically leads to contractual claims?

  • Oral agreements made during meetings
  • Detailed and clear contracts
  • Agreed modifications documented between parties
  • Poorly written contracts (correct)
  • What constitutes a different site condition claim?

  • Normal variations that occur during the construction process
  • Physical aspects that materially differ from contracted documents (correct)
  • Standard project risks identified in the contract
  • Weather-related issues altering construction schedules
  • Which of the following is NOT a potential cause of contractual claims?

    <p>Explicit project timelines</p> Signup and view all the answers

    Which of the following claims arises from additional requests after construction has commenced?

    <p>Extra work claims</p> Signup and view all the answers

    What is a built environment claim?

    <p>A request for compensation for damages due to contractual obligations</p> Signup and view all the answers

    Which of the following is a common cause of claims in construction contracts?

    <p>Insufficient communication among parties</p> Signup and view all the answers

    How can early settlement of claims benefit project relationships?

    <p>It reduces strained relationships and financial repercussions</p> Signup and view all the answers

    What happens when one party fails to fulfill a contractual obligation?

    <p>It may result in legal action or a change order</p> Signup and view all the answers

    What is the primary aim of distinguishing between claims and change orders?

    <p>To identify sources and causes of claims</p> Signup and view all the answers

    What is a key aspect of the claim impact criteria?

    <p>Scope of work changes</p> Signup and view all the answers

    When does the greatest opportunity to prevent claims occur in a construction project?

    <p>Once tender documents are finalized and the contract is awarded</p> Signup and view all the answers

    Which of the following is NOT a potential consequence of a claim in construction?

    <p>Guaranteed project delay</p> Signup and view all the answers

    What is a Claim in the context of a contract?

    <p>A request for damages due to another party's failure to fulfill obligations.</p> Signup and view all the answers

    What is the primary purpose of a Change Order?

    <p>To document approved changes in contract items.</p> Signup and view all the answers

    What are common causes of claims in contract management?

    <p>Delays, unforeseen circumstances, and insufficient information.</p> Signup and view all the answers

    How are most claims typically settled?

    <p>By negotiation or dispute resolution.</p> Signup and view all the answers

    What role might a Claim Review Board (CRB) have in contract disputes?

    <p>To help introduce consistency and fairness in reviewing claims.</p> Signup and view all the answers

    What factor does NOT contribute to the causes of claims?

    <p>Changes in project budget.</p> Signup and view all the answers

    What is NOT a characteristic used to classify claims?

    <p>Timeframe of project completion.</p> Signup and view all the answers

    Which statement best describes the term 'Change Order'?

    <p>A documented agreement on changes in contract specifications.</p> Signup and view all the answers

    What is the primary function of the Change Control Board (CCB)?

    <p>Evaluating and assessing proposed changes</p> Signup and view all the answers

    Which statement accurately describes change orders in relation to claims?

    <p>Some contracts impose stricter deadlines on change orders than on claims.</p> Signup and view all the answers

    What might be one of the claim impact criteria relevant to the Avo scenario?

    <p>Impact on project stakeholders</p> Signup and view all the answers

    Which of the following is NOT a characteristic of change orders?

    <p>Claim substitution</p> Signup and view all the answers

    How do time deadlines typically apply to change orders?

    <p>They are not normally subjected to the same deadlines as claims.</p> Signup and view all the answers

    What is characteristic of time-barred clauses?

    <p>They can limit the time frame to file a claim.</p> Signup and view all the answers

    When it comes to change orders, which statement is true?

    <p>Their evaluation may vary depending on contract provisions.</p> Signup and view all the answers

    Which of the following best describes a built environment change order?

    <p>A mutual agreement to add or subtract work from a contract.</p> Signup and view all the answers

    What leads to differences in pricing at the final stage of construction?

    <p>Differences in material pricing</p> Signup and view all the answers

    What circumstance typically causes acceleration claims to arise?

    <p>Owner-directed acceleration</p> Signup and view all the answers

    In cases of damage claims, who is generally held responsible for the site?

    <p>The contractor</p> Signup and view all the answers

    What is a possible outcome when added work occurs during construction?

    <p>Difference in pricing</p> Signup and view all the answers

    Who is obligated to compensate for additional costs due to delays?

    <p>The party responsible for the slowdown</p> Signup and view all the answers

    What common issue can lead to damage claims during construction?

    <p>Fault of the owner or safety issues</p> Signup and view all the answers

    What typically happens during acceleration claims?

    <p>The project must be completed within an agreed time frame</p> Signup and view all the answers

    Which of the following is NOT typically involved in measuring claims differences?

    <p>Owner's project financing</p> Signup and view all the answers

    Which claim category is defined as claims arising from breaches specified in the contract?

    <p>Contractual claim</p> Signup and view all the answers

    What is characteristic of an extra-contractual claim?

    <p>Arises from moral grounds</p> Signup and view all the answers

    In the context of claims, what does the term 'ex gratia claim' imply?

    <p>A claim filed for moral reasons</p> Signup and view all the answers

    Which claim category would involve delays caused by the contracted entity in completing their work?

    <p>Breach of time frame claim</p> Signup and view all the answers

    What is a defining factor in proving a breach of time frame claim?

    <p>There must be evidence showing fault</p> Signup and view all the answers

    Which scenario best represents a contractual claim?

    <p>A property owner claims damages for late work completion as per contract terms</p> Signup and view all the answers

    What allows an owner to recover damages from delays according to the claim categories?

    <p>Proven fault by the contracted entity</p> Signup and view all the answers

    Which of the following is NOT true about ex gratia claims?

    <p>They have a legal foundation in contract law</p> Signup and view all the answers

    Study Notes

    Construction Contract and Risk Management

    • Common Causes of Claims: Claims in construction projects often arise due to delays, changes, unforeseen circumstances, insufficient information, and other work-related conflicts.
    • Objectives: Key objectives of the course include reviewing common claim causes, distinguishing claims and change orders, identifying sources and causes of claims, and recognizing various claim types.
    • Claims in the Built Environment: Effective claim resolution is vital to prevent strained relationships and financial repercussions.
    • Claims vs. Change Orders: Claims are requests for compensation due to contractual obligations not fulfilled, while change orders are agreed adjustments to the project scope.
    • Built Environment Claim Definition: A claim is a formal request for compensation due to a party's failure to meet contractual obligations, potentially leading to legal action or a change order.
    • Claim Impact Criteria: Key impact factors of claims include scope of work changes, increased time and expenses, and added recovery costs.
    • Claim Deadlines: Time deadlines and time-barred clauses are significant elements of claims management.
    • Built Environment Change Order Definition: A change order is mutual agreement between involved parties to alter the project scope (sequence, addition, or subtraction of tasks). It isn't a replacement for a claim.
    • Change Order Deadlines: Change orders typically aren't subject to the same deadlines as claims. Some contracts might have no deadlines, while others have stricter deadlines for change orders versus claims. The Change Control Board (CCB) assesses proposed changes, evaluates their impact, and decides whether to accept or reject them.
    • Summary of Claim vs. Change Order: A claim is a formal request for compensation, while a change order is a mutual agreement to adjust scope.

    Claim Review Board

    • Reflect on the Avocet Island Initiative: The discussion explores how a Change Review Board (CRB) might affect the Avocet Island project.

    Causes and Sources of Claims

    • Claims Cause Research: Many construction claims are settled through negotiation, dispute resolution processes, and claims research.
    • Causes of Claims: Typical causes include delays, unforeseen circumstances, insufficient information, and other work-related conflicts (disputes).

    Classifying Claims

    • Classifying Claims: Claims can be categorized as contractual, extra-contractual, or ex gratia, based on their origin and the parties involved. Other categories include issues relating to rights claimed, legal basis, and claim characteristics.

    Claim Categories

    • Claim Categories: Key claim categories covered include contractual claims, extra-contractual claims, ex gratia claims, extension of time claims, and breach of time frame claims.
    • Payment-Related Claims: Common forms of payment-related claims include non-payment, delayed payment, deductions from bills without explanation, and delays in payment security and maintenance deposit.

    Change Claims

    • Change Claims: Project changes, revisions involving the scope of work, and additional work can lead to change claims.

    Delay Claims

    • Delay Claims: Delays arising from unforeseen circumstances impact project timelines. Proving these delays can be challenging, particularly in large-scale projects.

    Extra Work Claims

    • Extra Work Claims: Claims typically happen if a project involves additional work not stated in the initial contract, after construction starts.

    Contractual Claims

    • Contractual Claims: Disputes over responsibilities, liabilities not in documents, or poorly written contracts can lead to contractual claims.

    Different Site Conditions Claims

    • Different Site Conditions Claims: Unexpected site conditions that differ from the initial contract documentation can lead to site condition claims.

    Differences in Pricing and Measuring Claims

    • Pricing and Measuring Claims: Disputes over measurement and pricing discrepancies during the project's final stages occur in pricing and measuring claims.

    Acceleration Claims

    • Acceleration Claims: Owner-directed acceleration can create disputes and lead to claims regarding the required speed to complete projects in agreed on time frames.

    Damage Claims

    • Damage Claims: Damage claims typically occur if the owner is at fault or safety issues arise. Contractors are usually held accountable for site safety and damages in most situations.

    Contract Termination Claims

    • Contract Termination Claims: Claims arise if a contract is terminated early (either by the owner or contractor) before all contractual obligations are fulfilled.

    Documentation and Data Analysis

    • Documentation and Data Analysis: Identifying, documenting, and analyzing data, highlighting problem areas, and maintaining records are vital for handling claims effectively.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Test your knowledge on construction claims, including extra work claims, different site condition claims, and the implications of change orders. Explore common causes of contractual claims and understand how effective claim management can enhance project relationships.

    More Like This

    Use Quizgecko on...
    Browser
    Browser