Podcast
Questions and Answers
What defines extra work claims in a construction context?
What defines extra work claims in a construction context?
- Routine tasks included in the contract
- Requests for tasks that were not originally stated in the contract (correct)
- Changes in project timing due to weather conditions
- Tasks delegated to subcontractors before the contract signing
What typically leads to contractual claims?
What typically leads to contractual claims?
- Oral agreements made during meetings
- Detailed and clear contracts
- Agreed modifications documented between parties
- Poorly written contracts (correct)
What constitutes a different site condition claim?
What constitutes a different site condition claim?
- Normal variations that occur during the construction process
- Physical aspects that materially differ from contracted documents (correct)
- Standard project risks identified in the contract
- Weather-related issues altering construction schedules
Which of the following is NOT a potential cause of contractual claims?
Which of the following is NOT a potential cause of contractual claims?
Which of the following claims arises from additional requests after construction has commenced?
Which of the following claims arises from additional requests after construction has commenced?
What is a built environment claim?
What is a built environment claim?
Which of the following is a common cause of claims in construction contracts?
Which of the following is a common cause of claims in construction contracts?
How can early settlement of claims benefit project relationships?
How can early settlement of claims benefit project relationships?
What happens when one party fails to fulfill a contractual obligation?
What happens when one party fails to fulfill a contractual obligation?
What is the primary aim of distinguishing between claims and change orders?
What is the primary aim of distinguishing between claims and change orders?
What is a key aspect of the claim impact criteria?
What is a key aspect of the claim impact criteria?
When does the greatest opportunity to prevent claims occur in a construction project?
When does the greatest opportunity to prevent claims occur in a construction project?
Which of the following is NOT a potential consequence of a claim in construction?
Which of the following is NOT a potential consequence of a claim in construction?
What is a Claim in the context of a contract?
What is a Claim in the context of a contract?
What is the primary purpose of a Change Order?
What is the primary purpose of a Change Order?
What are common causes of claims in contract management?
What are common causes of claims in contract management?
How are most claims typically settled?
How are most claims typically settled?
What role might a Claim Review Board (CRB) have in contract disputes?
What role might a Claim Review Board (CRB) have in contract disputes?
What factor does NOT contribute to the causes of claims?
What factor does NOT contribute to the causes of claims?
What is NOT a characteristic used to classify claims?
What is NOT a characteristic used to classify claims?
Which statement best describes the term 'Change Order'?
Which statement best describes the term 'Change Order'?
What is the primary function of the Change Control Board (CCB)?
What is the primary function of the Change Control Board (CCB)?
Which statement accurately describes change orders in relation to claims?
Which statement accurately describes change orders in relation to claims?
What might be one of the claim impact criteria relevant to the Avo scenario?
What might be one of the claim impact criteria relevant to the Avo scenario?
Which of the following is NOT a characteristic of change orders?
Which of the following is NOT a characteristic of change orders?
How do time deadlines typically apply to change orders?
How do time deadlines typically apply to change orders?
What is characteristic of time-barred clauses?
What is characteristic of time-barred clauses?
When it comes to change orders, which statement is true?
When it comes to change orders, which statement is true?
Which of the following best describes a built environment change order?
Which of the following best describes a built environment change order?
What leads to differences in pricing at the final stage of construction?
What leads to differences in pricing at the final stage of construction?
What circumstance typically causes acceleration claims to arise?
What circumstance typically causes acceleration claims to arise?
In cases of damage claims, who is generally held responsible for the site?
In cases of damage claims, who is generally held responsible for the site?
What is a possible outcome when added work occurs during construction?
What is a possible outcome when added work occurs during construction?
Who is obligated to compensate for additional costs due to delays?
Who is obligated to compensate for additional costs due to delays?
What common issue can lead to damage claims during construction?
What common issue can lead to damage claims during construction?
What typically happens during acceleration claims?
What typically happens during acceleration claims?
Which of the following is NOT typically involved in measuring claims differences?
Which of the following is NOT typically involved in measuring claims differences?
Which claim category is defined as claims arising from breaches specified in the contract?
Which claim category is defined as claims arising from breaches specified in the contract?
What is characteristic of an extra-contractual claim?
What is characteristic of an extra-contractual claim?
In the context of claims, what does the term 'ex gratia claim' imply?
In the context of claims, what does the term 'ex gratia claim' imply?
Which claim category would involve delays caused by the contracted entity in completing their work?
Which claim category would involve delays caused by the contracted entity in completing their work?
What is a defining factor in proving a breach of time frame claim?
What is a defining factor in proving a breach of time frame claim?
Which scenario best represents a contractual claim?
Which scenario best represents a contractual claim?
What allows an owner to recover damages from delays according to the claim categories?
What allows an owner to recover damages from delays according to the claim categories?
Which of the following is NOT true about ex gratia claims?
Which of the following is NOT true about ex gratia claims?
Flashcards
What is a claim?
What is a claim?
A formal request for additional compensation, often due to unforeseen circumstances or changes in the project.
What is a change order?
What is a change order?
An official document that changes the original contract terms, often adding work or time, and impacts all parties involved.
What are sources of claims?
What are sources of claims?
Claims can arise from various sources, including design errors, unforeseen site conditions, delays due to weather, and more.
What impact do claims have?
What impact do claims have?
Signup and view all the flashcards
When is the best time to prevent claims?
When is the best time to prevent claims?
Signup and view all the flashcards
What are the risks of unresolved claims?
What are the risks of unresolved claims?
Signup and view all the flashcards
Why is early claim settlement beneficial?
Why is early claim settlement beneficial?
Signup and view all the flashcards
What situations trigger claims?
What situations trigger claims?
Signup and view all the flashcards
Claim Impact Criteria
Claim Impact Criteria
Signup and view all the flashcards
Time-barred Clauses
Time-barred Clauses
Signup and view all the flashcards
Built Environment Change Order
Built Environment Change Order
Signup and view all the flashcards
Change Order Deadlines
Change Order Deadlines
Signup and view all the flashcards
Change Control Board (CCB)
Change Control Board (CCB)
Signup and view all the flashcards
Claims
Claims
Signup and view all the flashcards
Change Orders
Change Orders
Signup and view all the flashcards
Change Order vs. Claim
Change Order vs. Claim
Signup and view all the flashcards
Change Review Board (CRB)
Change Review Board (CRB)
Signup and view all the flashcards
Causes of Claims
Causes of Claims
Signup and view all the flashcards
Claim Resolution
Claim Resolution
Signup and view all the flashcards
Classifying Claims
Classifying Claims
Signup and view all the flashcards
Claims Cause Research
Claims Cause Research
Signup and view all the flashcards
Extra Work Claims
Extra Work Claims
Signup and view all the flashcards
Contractual Claims
Contractual Claims
Signup and view all the flashcards
Different Site Conditions Claims
Different Site Conditions Claims
Signup and view all the flashcards
How to prevent Claims?
How to prevent Claims?
Signup and view all the flashcards
Extra-contractual Claims
Extra-contractual Claims
Signup and view all the flashcards
Ex Gratia Claims
Ex Gratia Claims
Signup and view all the flashcards
Extension of Time Claim
Extension of Time Claim
Signup and view all the flashcards
Breach of Time Frame
Breach of Time Frame
Signup and view all the flashcards
Claim Categories
Claim Categories
Signup and view all the flashcards
What are claims?
What are claims?
Signup and view all the flashcards
Price and Measurement Difference Claim
Price and Measurement Difference Claim
Signup and view all the flashcards
Added Work Claim
Added Work Claim
Signup and view all the flashcards
Acceleration Claim
Acceleration Claim
Signup and view all the flashcards
What triggers an acceleration claim?
What triggers an acceleration claim?
Signup and view all the flashcards
Damage Claim
Damage Claim
Signup and view all the flashcards
Why are damage claims rare?
Why are damage claims rare?
Signup and view all the flashcards
Who pays for delays?
Who pays for delays?
Signup and view all the flashcards
What are common sources of claims?
What are common sources of claims?
Signup and view all the flashcards
Study Notes
Construction Contract and Risk Management
- Common Causes of Claims: Claims in construction projects often arise due to delays, changes, unforeseen circumstances, insufficient information, and other work-related conflicts.
- Objectives: Key objectives of the course include reviewing common claim causes, distinguishing claims and change orders, identifying sources and causes of claims, and recognizing various claim types.
- Claims in the Built Environment: Effective claim resolution is vital to prevent strained relationships and financial repercussions.
- Claims vs. Change Orders: Claims are requests for compensation due to contractual obligations not fulfilled, while change orders are agreed adjustments to the project scope.
- Built Environment Claim Definition: A claim is a formal request for compensation due to a party's failure to meet contractual obligations, potentially leading to legal action or a change order.
- Claim Impact Criteria: Key impact factors of claims include scope of work changes, increased time and expenses, and added recovery costs.
- Claim Deadlines: Time deadlines and time-barred clauses are significant elements of claims management.
- Built Environment Change Order Definition: A change order is mutual agreement between involved parties to alter the project scope (sequence, addition, or subtraction of tasks). It isn't a replacement for a claim.
- Change Order Deadlines: Change orders typically aren't subject to the same deadlines as claims. Some contracts might have no deadlines, while others have stricter deadlines for change orders versus claims. The Change Control Board (CCB) assesses proposed changes, evaluates their impact, and decides whether to accept or reject them.
- Summary of Claim vs. Change Order: A claim is a formal request for compensation, while a change order is a mutual agreement to adjust scope.
Claim Review Board
- Reflect on the Avocet Island Initiative: The discussion explores how a Change Review Board (CRB) might affect the Avocet Island project.
Causes and Sources of Claims
- Claims Cause Research: Many construction claims are settled through negotiation, dispute resolution processes, and claims research.
- Causes of Claims: Typical causes include delays, unforeseen circumstances, insufficient information, and other work-related conflicts (disputes).
Classifying Claims
- Classifying Claims: Claims can be categorized as contractual, extra-contractual, or ex gratia, based on their origin and the parties involved. Other categories include issues relating to rights claimed, legal basis, and claim characteristics.
Claim Categories
- Claim Categories: Key claim categories covered include contractual claims, extra-contractual claims, ex gratia claims, extension of time claims, and breach of time frame claims.
Payment-Related Claims
- Payment-Related Claims: Common forms of payment-related claims include non-payment, delayed payment, deductions from bills without explanation, and delays in payment security and maintenance deposit.
Change Claims
- Change Claims: Project changes, revisions involving the scope of work, and additional work can lead to change claims.
Delay Claims
- Delay Claims: Delays arising from unforeseen circumstances impact project timelines. Proving these delays can be challenging, particularly in large-scale projects.
Extra Work Claims
- Extra Work Claims: Claims typically happen if a project involves additional work not stated in the initial contract, after construction starts.
Contractual Claims
- Contractual Claims: Disputes over responsibilities, liabilities not in documents, or poorly written contracts can lead to contractual claims.
Different Site Conditions Claims
- Different Site Conditions Claims: Unexpected site conditions that differ from the initial contract documentation can lead to site condition claims.
Differences in Pricing and Measuring Claims
- Pricing and Measuring Claims: Disputes over measurement and pricing discrepancies during the project's final stages occur in pricing and measuring claims.
Acceleration Claims
- Acceleration Claims: Owner-directed acceleration can create disputes and lead to claims regarding the required speed to complete projects in agreed on time frames.
Damage Claims
- Damage Claims: Damage claims typically occur if the owner is at fault or safety issues arise. Contractors are usually held accountable for site safety and damages in most situations.
Contract Termination Claims
- Contract Termination Claims: Claims arise if a contract is terminated early (either by the owner or contractor) before all contractual obligations are fulfilled.
Documentation and Data Analysis
- Documentation and Data Analysis: Identifying, documenting, and analyzing data, highlighting problem areas, and maintaining records are vital for handling claims effectively.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on construction claims, including extra work claims, different site condition claims, and the implications of change orders. Explore common causes of contractual claims and understand how effective claim management can enhance project relationships.