Questions and Answers
According to the Indian Railway Code, which chapters contain the rules and procedure for calling tenders and entering into contracts for the Engineering Department?
According to the Indian Railway Code, which chapters contain the rules and procedure for calling tenders and entering into contracts for the Engineering Department?
What is the primary consideration while preparing tender schedules?
What is the primary consideration while preparing tender schedules?
Which of the following documents is NOT part of the contract?
Which of the following documents is NOT part of the contract?
Who should possess copies of the instructions to parties tendering, tender form, and other contract documents?
Who should possess copies of the instructions to parties tendering, tender form, and other contract documents?
Signup and view all the answers
What is the primary objective of ensuring that contract documents are comprehensive and explicit?
What is the primary objective of ensuring that contract documents are comprehensive and explicit?
Signup and view all the answers
Which department's code contains the procedure and rules for calling tenders and entering into contracts for the supply of materials?
Which department's code contains the procedure and rules for calling tenders and entering into contracts for the supply of materials?
Signup and view all the answers
What is the purpose of dovetailing works, as mentioned in the content?
What is the purpose of dovetailing works, as mentioned in the content?
Signup and view all the answers
What is included in the scope of work documentation, according to the content?
What is included in the scope of work documentation, according to the content?
Signup and view all the answers
What should be ensured to avoid disputes with contractors?
What should be ensured to avoid disputes with contractors?
Signup and view all the answers
What document should be obtained from the contractor after completing every work?
What document should be obtained from the contractor after completing every work?
Signup and view all the answers
What should be done if there is a likelihood of a dispute with a contractor?
What should be done if there is a likelihood of a dispute with a contractor?
Signup and view all the answers
What should be instructed to the contractor to submit in case of a dispute?
What should be instructed to the contractor to submit in case of a dispute?
Signup and view all the answers
What should be done if the contractor refuses to sign the final contract certificate?
What should be done if the contractor refuses to sign the final contract certificate?
Signup and view all the answers
How should disputes arising out of a contract be referred?
How should disputes arising out of a contract be referred?
Signup and view all the answers
What should be kept up to date and complete with reference to agreements?
What should be kept up to date and complete with reference to agreements?
Signup and view all the answers
What should be done every month or when 'on account' bills are made out?
What should be done every month or when 'on account' bills are made out?
Signup and view all the answers
If a tenderer fails to execute the contract documents within the stipulated time, what will be the consequence?
If a tenderer fails to execute the contract documents within the stipulated time, what will be the consequence?
Signup and view all the answers
What is the requirement for the contract agreement required to be executed by the successful tenderer?
What is the requirement for the contract agreement required to be executed by the successful tenderer?
Signup and view all the answers
Who shall vet the draft of the contract agreement?
Who shall vet the draft of the contract agreement?
Signup and view all the answers
What is the purpose of supplying a copy of the contract documents to the inspecting agency?
What is the purpose of supplying a copy of the contract documents to the inspecting agency?
Signup and view all the answers
What is the consequence if a tenderer refuses to execute the contract documents?
What is the consequence if a tenderer refuses to execute the contract documents?
Signup and view all the answers
Where shall the sufficient number of copies of the contract documents be available?
Where shall the sufficient number of copies of the contract documents be available?
Signup and view all the answers
What is the requirement for every contract?
What is the requirement for every contract?
Signup and view all the answers
Who shall appear at the office of the concerned Chief Signal and Telecommunication Engineer/Construction/Projects or Sr.Divisional Signal and Telecommunication Engineer/Dy.Chief Signal and Telecommunication Engineer?
Who shall appear at the office of the concerned Chief Signal and Telecommunication Engineer/Construction/Projects or Sr.Divisional Signal and Telecommunication Engineer/Dy.Chief Signal and Telecommunication Engineer?
Signup and view all the answers
What is the primary responsibility of the officer/incharge and supervisor/incharge of the work?
What is the primary responsibility of the officer/incharge and supervisor/incharge of the work?
Signup and view all the answers
What is the requirement for modifying contract provisions after the contract documents have been signed?
What is the requirement for modifying contract provisions after the contract documents have been signed?
Signup and view all the answers
What happens if a verbal or written arrangement is made to abandon, modify, extend, reduce, or supplement the contract or any of its terms?
What happens if a verbal or written arrangement is made to abandon, modify, extend, reduce, or supplement the contract or any of its terms?
Signup and view all the answers
Who is responsible for ensuring that the contract documents are thoroughly studied?
Who is responsible for ensuring that the contract documents are thoroughly studied?
Signup and view all the answers
What is the requirement for executing items of work not included in the contract documents?
What is the requirement for executing items of work not included in the contract documents?
Signup and view all the answers
What is the consequence of not adhering to the provisions contained in the contract documents?
What is the consequence of not adhering to the provisions contained in the contract documents?
Signup and view all the answers
What is the purpose of the contract documents?
What is the purpose of the contract documents?
Signup and view all the answers
Who has the authority to sanction deviations in the contract documents?
Who has the authority to sanction deviations in the contract documents?
Signup and view all the answers
Who is responsible for drawing the Completion Report after the work is completed?
Who is responsible for drawing the Completion Report after the work is completed?
Signup and view all the answers
What is the primary purpose of obtaining finance concurrence of the Completion Estimate?
What is the primary purpose of obtaining finance concurrence of the Completion Estimate?
Signup and view all the answers
What is the significance of the measurement book in contract management?
What is the significance of the measurement book in contract management?
Signup and view all the answers
What should be done if a mistake is made in the measurement book?
What should be done if a mistake is made in the measurement book?
Signup and view all the answers
What should be included in the description of work in the measurement book?
What should be included in the description of work in the measurement book?
Signup and view all the answers
What is the purpose of crossing the entry of the number and page of measurements affected with red ink diagonally?
What is the purpose of crossing the entry of the number and page of measurements affected with red ink diagonally?
Signup and view all the answers
What should be done after the completion of the work and the submission of the Completion Report?
What should be done after the completion of the work and the submission of the Completion Report?
Signup and view all the answers
What is the significance of Annexure 10-A1 in the context of measurement recordkeeping?
What is the significance of Annexure 10-A1 in the context of measurement recordkeeping?
Signup and view all the answers
What is the primary purpose of having a comprehensive and explicit contract document?
What is the primary purpose of having a comprehensive and explicit contract document?
Signup and view all the answers
What should be done to ensure uniformity of equipment in a section or division?
What should be done to ensure uniformity of equipment in a section or division?
Signup and view all the answers
Who should be familiar with the provisions of the contract documents?
Who should be familiar with the provisions of the contract documents?
Signup and view all the answers
What is the purpose of including the scope of work and time scales in the contract documents?
What is the purpose of including the scope of work and time scales in the contract documents?
Signup and view all the answers
What is the consequence of not having a comprehensive and explicit contract document?
What is the consequence of not having a comprehensive and explicit contract document?
Signup and view all the answers
What should be done before preparing tender schedules?
What should be done before preparing tender schedules?
Signup and view all the answers
What is the primary purpose of including the location particulars of the work in the contract documents?
What is the primary purpose of including the location particulars of the work in the contract documents?
Signup and view all the answers
What should be ensured while preparing tender schedules?
What should be ensured while preparing tender schedules?
Signup and view all the answers
What is the primary objective of ensuring that all necessary documents are collected and stored in safe custody during a dispute with a contractor?
What is the primary objective of ensuring that all necessary documents are collected and stored in safe custody during a dispute with a contractor?
Signup and view all the answers
What should the contractor be instructed to submit with a certificate, if a dispute arises?
What should the contractor be instructed to submit with a certificate, if a dispute arises?
Signup and view all the answers
What should be done if a contractor refuses to sign the final contract certificate?
What should be done if a contractor refuses to sign the final contract certificate?
Signup and view all the answers
What should be kept up to date and complete with reference to agreements, work orders, abstracts in measurement books, and amounts?
What should be kept up to date and complete with reference to agreements, work orders, abstracts in measurement books, and amounts?
Signup and view all the answers
What should be commenced with a headline 'without prejudice' in all correspondence with the contractor, in case of a dispute?
What should be commenced with a headline 'without prejudice' in all correspondence with the contractor, in case of a dispute?
Signup and view all the answers
What should be obtained from the contractor after completing every work?
What should be obtained from the contractor after completing every work?
Signup and view all the answers
Where should all necessary documents be stored, in case of a dispute with a contractor?
Where should all necessary documents be stored, in case of a dispute with a contractor?
Signup and view all the answers
How should disputes arising out of a contract be referred?
How should disputes arising out of a contract be referred?
Signup and view all the answers
Who is responsible for ensuring that the measurements are made in a timely manner and recorded by the SSE/JE(Signal)/incharge of the work?
Who is responsible for ensuring that the measurements are made in a timely manner and recorded by the SSE/JE(Signal)/incharge of the work?
Signup and view all the answers
What should be done after the quantities are computed in the measurement book?
What should be done after the quantities are computed in the measurement book?
Signup and view all the answers
What should be headed in the abstract prepared in the measurement book?
What should be headed in the abstract prepared in the measurement book?
Signup and view all the answers
What should be ensured by the official in charge before recording the certificate in the measurement book?
What should be ensured by the official in charge before recording the certificate in the measurement book?
Signup and view all the answers
Who should do the test check of works as per extant norms?
Who should do the test check of works as per extant norms?
Signup and view all the answers
Where should the abstract be prepared in the measurement book?
Where should the abstract be prepared in the measurement book?
Signup and view all the answers
What is the consequence of executing items of work not included in the contract documents without the sanction of the competent authority?
What is the consequence of executing items of work not included in the contract documents without the sanction of the competent authority?
Signup and view all the answers
What should be shown in the abstract prepared in the measurement book?
What should be shown in the abstract prepared in the measurement book?
Signup and view all the answers
Who is responsible for ensuring that no item of work not included in the contract is carried out without the sanction of the competent authority?
Who is responsible for ensuring that no item of work not included in the contract is carried out without the sanction of the competent authority?
Signup and view all the answers
What is the requirement for modifying contract provisions after the contract documents have been signed?
What is the requirement for modifying contract provisions after the contract documents have been signed?
Signup and view all the answers
What should be done after the quantities are computed and entered in the 'contents' column of the measurement book?
What should be done after the quantities are computed and entered in the 'contents' column of the measurement book?
Signup and view all the answers
What is the consequence of not adhering to the provisions contained in the contract documents?
What is the consequence of not adhering to the provisions contained in the contract documents?
Signup and view all the answers
Who has the authority to sanction deviations in the contract documents?
Who has the authority to sanction deviations in the contract documents?
Signup and view all the answers
What is the purpose of executing items of work not included in the contract documents?
What is the purpose of executing items of work not included in the contract documents?
Signup and view all the answers
What is the requirement for the contract agreement?
What is the requirement for the contract agreement?
Signup and view all the answers
What is the consequence of making a verbal or written arrangement to abandon, modify, extend, reduce, or supplement the contract or any of its terms?
What is the consequence of making a verbal or written arrangement to abandon, modify, extend, reduce, or supplement the contract or any of its terms?
Signup and view all the answers
What is the primary purpose of maintaining a separate measurement book for large works?
What is the primary purpose of maintaining a separate measurement book for large works?
Signup and view all the answers
What information should be given at the top of the first page of measurements relating to a work?
What information should be given at the top of the first page of measurements relating to a work?
Signup and view all the answers
Who should carefully check the measurements book to ensure that they are kept up as complete records?
Who should carefully check the measurements book to ensure that they are kept up as complete records?
Signup and view all the answers
What should be done whenever progress on a work is reported in lump sum quantities under sub-heads of works?
What should be done whenever progress on a work is reported in lump sum quantities under sub-heads of works?
Signup and view all the answers
Why should the measurements relating to one work be kept together?
Why should the measurements relating to one work be kept together?
Signup and view all the answers
What should be done when an Divisional/Assistant Signal and Telecommunication Engineer is required to submit his measurement book?
What should be done when an Divisional/Assistant Signal and Telecommunication Engineer is required to submit his measurement book?
Signup and view all the answers
What should be estimated and set apart for the purpose of recording the measurements consecutively?
What should be estimated and set apart for the purpose of recording the measurements consecutively?
Signup and view all the answers
Where should the measurement books be eventually returned to?
Where should the measurement books be eventually returned to?
Signup and view all the answers
Study Notes
Register of Contracts and Agreements
- The Register shall be kept up to date and complete with information on agreements, work orders, abstracts in measurement books, and amounts.
Dispute Resolution with Contractors
- Efforts should be made to avoid disputes with contractors by ensuring supply of drawings, handing over of site, deputing of staff for supervision, materials, budget for work, and timely payments to contractors.
Contract Dispute Resolution Process
- On completion of work, a 'No claims certificate' shall be obtained from the contractor according to the relevant clause or clauses in the condition of contract.
- The contractor shall submit a list of outstanding claims, if any, every month or when 'on account' bills are made out.
- If a dispute arises, all documents, measurements, and letters related to the case shall be collected and stored safely with the officer responsible for the case.
- Correspondence with the contractor shall commence with the headline 'without prejudice'.
- The contractor shall submit complete details of claims in writing with a certificate to the effect that these are final.
Arbitration
- Disputes arising out of the contract for a work between the contractor and the Railway Administration shall be referred for arbitration in accordance with the relevant clause in the General Conditions of Contract.
Contracts for Works
General
- The procedure and rules for calling for tenders and entering into contracts for execution of works and supply of materials are contained in Chapter XII of the Indian Railway Code for the Engineering Department and Chapters III, IV, and VII of the Indian Railway Code for the Stores Department.
Tender Schedules and Contract Documents
- Tender schedules shall be prepared keeping in view scope of work, tentative drawings issued, existing installation, and after a careful site survey.
- The documents which form a contract include instructions to parties tendering, tender form, specifications, schedule of items and quantities, rates, conditions of contract, agreement form, scope of work, time scales, location particulars of the work, and equipment details.
- Each Sr Divisional Signal and Telecommunication Engineer shall be in possession of copies of these documents and acquaint himself with the provisions contained therein.
Items of Works Not Included in Contract Documents
- Officers and supervisors shall ensure that no item of work not included in the contract is carried out without the sanction of the competent authority.
- Items of work not included in a contract may be executed under the contract at mutually agreed rates.
Modifications to Contract
- Modifications to the contract shall be made in writing and signed by the Railway and the contractor, and no work shall proceed under such modifications until this has been done.
Execution of Contract Documents
- The tenderer whose tender is accepted shall execute the contract documents within the stipulated time period.
- Failure to do so shall constitute a breach of the agreement, and the earnest money accompanying the tender may be forfeited.
Form of Contract Documents
- Every contract shall be complete in respect of the documents it constitutes.
- The contract agreement shall be in the form prescribed by the Administration for the purpose.
Copies of Contract Documents
- Sufficient number of copies of the contract documents shall be available for use in the offices of the Sr Divisional Signal and Telecommunication Engineer/Dy. Chief Signal and Telecommunication Engineer and the SSE/JE (Signal)/incharge.
Completion Reports
- After completion of a work, a completion report shall be drawn up by the Sr. DSTE/Dy. CSTE incharge of the work.
- All expenditures like stores, contract, adjustment memos, workshop debits, D&G charges, etc., shall be properly accounted.
- Finance concurrence of the completion estimate shall be obtained from the associated finance and sanction from the competent authority.
Instructions for Recording Measurements
- The measurement book is the basis of all accounts of quantities of work done by contract and shall be kept so that the transactions may be readily traceable into the accounts.
- All measurements are to be taken down in ink in this book, and the description of work must be lucid to admit easy identification and check.
- No erasures are allowed; mistakes shall be neatly scored out, and correct entries made, and every correction shall be initialled.
Code References for Contracts
- The procedure and rules for calling for tenders and entering into contracts for execution of works and supply of materials are contained in Chapter XII of the Indian Railway Code for the Engineering Department and Chapters III, IV, and VII of the Indian Railway Code for the Stores Department.
Basis for Inviting Tenders and Entering into Contracts
- Tender schedules shall be prepared considering scope of work, tentative drawing issued, existing installation, and after careful site survey.
- Documents that form a contract include:
- Instructions to parties tendering
- Tender form
- Specifications (standard and special)
- Schedule of items and quantities, rates, etc.
- Conditions of contract (general and special)
- Agreement Form
- Scope of the work
- Time scales
- Location particulars of the work
- Equipment details (in case of Annual maintenance contract)
- Each Sr Divisional Signal and Telecommunication Engineer shall be in possession of copies of the above-mentioned documents and acquaint himself with the provisions contained therein.
Executing Contracts
- Officer/incharge & supervisor/incharge of the work shall ensure that no item of work not included in the contract is carried out without the sanction of the competent authority.
- Items of work not included in a contract may be executed under the contract at mutually agreed rates.
Modifying Contracts
- Modifications to contract shall be made in writing and signed by the Railway and the contractor.
- No work shall proceed under such modifications until they are incorporated in a formal instrument signed by the Railway and the contractor.
Measurements and Computation of Quantities
- The Assistant/Divisional Signal and Telecommunication Engineer shall be responsible for the correctness of the measurements, quantity, and adherence to clauses and specifications laid down in the contract.
- Measurements shall be recorded in the measurement book and computations of quantities shall be done timely and in the specified manner.
- Abstracts shall be prepared in the measurement book, showing the correct description of the item, total quantity done up-to-date, rate, and total value for each item measured/checked.
Disputes with Contractors
- Every effort must be made to ensure supply of drawings, handing over of site, deputing of staff for supervision, materials (if any), budget for work, and timely payments to contractor, to avoid disputes with the contractor.
- On completion of every work, a 'No claims certificate' shall be obtained from the contractor according to the relevant clause or clauses in the condition of contract.
- In case of disputes, all documents, measurements, and letters bearing on the case shall be collected and stored in safe custody with the officer responsible for the case.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the procedures and guidelines for preparing completion reports after finishing a project, including accounting for expenditures and obtaining necessary concurrences and sanctions.