CCM Estimation Process Quiz
46 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the primary purpose of contingency in the CCM estimation process?

  • To ensure that all activities are completed on time
  • To add extra time to the overall project duration without justification
  • To account for statistical variations in activity durations (correct)
  • To minimize the overall cost of the project

In the context of CCM estimation, how is the total duration calculated?

  • By averaging the duration of each activity
  • By summing the durations of all activities only
  • By adding duration and contingency for all activities involved (correct)
  • By taking the maximum duration from the activities

What ensures that the project plan in CCM is shorter compared to standard approaches?

  • Using historical data without adjustments
  • Excluding contingency buffer in the planning
  • Combining duration with contingency and summing variances (correct)
  • Applying a single fixed duration for all tasks

What happens during plan execution if activities last longer than planned?

<p>The contingency buffer may overflow, which is acceptable up to a limit (B)</p> Signup and view all the answers

What does overallocation refer to in resource management?

<p>Using a resource above its maximum capability (D)</p> Signup and view all the answers

What is one key aspect of the basic idea behind CCM?

<p>Making the contingency buffer explicit and monitoring activity chains (B)</p> Signup and view all the answers

In the provided example, during which week is Resource 1 overallocated?

<p>Week 3 (A), Week 2 (C)</p> Signup and view all the answers

What is one proposed method to prevent resource overallocation?

<p>Resource leveling by inserting soft constraints (A)</p> Signup and view all the answers

What does a 'vertical' sum over work assignments indicate?

<p>Summing the workload over a specific resource across different tasks (A)</p> Signup and view all the answers

Why might a project have hard constraints regarding deliverables?

<p>Management has established unmovable deadlines (A)</p> Signup and view all the answers

Which task combination leads to the overallocation of Resource 1 in the example?

<p>Task 1 and Task 3 (C)</p> Signup and view all the answers

What is the primary indicator that resource management has reached a problem?

<p>A resource is allocated to two tasks simultaneously (A)</p> Signup and view all the answers

When managing a project, failing to recognize overallocation can lead to what outcome?

<p>Burnout of overworked resources (B)</p> Signup and view all the answers

What is the primary mechanism of fast tracking in project management?

<p>Overlapping activities that would normally be performed in sequence (D)</p> Signup and view all the answers

Why might a team decide to deliver work late instead of working overtime?

<p>To ensure higher quality outputs (B)</p> Signup and view all the answers

What does fast tracking rely on during the execution of activities?

<p>Incrementally producing and refining deliverables (D)</p> Signup and view all the answers

When considering fast tracking, what must a project manager assess about the intermediate outputs?

<p>How stable the intermediate outputs will be (C)</p> Signup and view all the answers

What is a significant risk of fast tracking in project management?

<p>It may cause increased rework later in the process (B)</p> Signup and view all the answers

When determining which dependencies to break for fast tracking, what should be closely assessed?

<p>The risk involved in changes to the output (A)</p> Signup and view all the answers

In the context of fast tracking, why is it beneficial to start dependent activities earlier?

<p>If the last portion of the deliverable is not critical (D)</p> Signup and view all the answers

Which of the following represents a misconception about fast tracking?

<p>It ensures that all tasks are completed as planned (B)</p> Signup and view all the answers

What is the primary assumption of Critical Chain Management regarding activity duration estimates?

<p>They are averages and can vary in actual completion time. (D)</p> Signup and view all the answers

In Critical Chain Management, what is the purpose of 'padding' estimations?

<p>To account for potential variations and uncertainties. (A)</p> Signup and view all the answers

What is a key characteristic of the standard deviation of a chain of activities in Critical Chain Management?

<p>It is less than the sum of the standard deviations of the activities in the chain. (D)</p> Signup and view all the answers

What does 'contingency' refer to in the context of activity duration estimates?

<p>The difference in duration between a 50% and a 90% probable estimate. (D)</p> Signup and view all the answers

Why is Critical Chain Management considered effective?

<p>It uses most probable estimates rather than overly pessimistic estimates. (C)</p> Signup and view all the answers

How does Critical Chain Management handle the problem of traditional estimation techniques?

<p>By incorporating continuous feedback and adjustment. (D)</p> Signup and view all the answers

What is the consequence of assuming activity durations are purely pessimistic?

<p>Potential for significant project delays. (D)</p> Signup and view all the answers

What does Critical Chain Management emphasize when planning project activities?

<p>The interdependencies and relationships among activities. (B)</p> Signup and view all the answers

What is the primary focus of a manager in the context of chain management?

<p>Managing the chains (D)</p> Signup and view all the answers

In the contingency buffer management, what is a sign that action may be needed?

<p>Overflow in the contingency buffer (D)</p> Signup and view all the answers

Which question relates to the concept of budgeting in software project management?

<p>How much does the development of the software cost? (C)</p> Signup and view all the answers

When considering buffer definition, what must be determined?

<p>Which chains are best to consider (A)</p> Signup and view all the answers

What happens if A1 lasts longer than planned in a chain?

<p>It leads to the chain entering the contingency buffer. (C)</p> Signup and view all the answers

Which option best describes the role of chains in project management?

<p>Chains are sequences of tasks impacting overall project duration. (C)</p> Signup and view all the answers

Which of the following is NOT part of buffer management?

<p>Calculating project profitability (C)</p> Signup and view all the answers

What implication does a task that lasts as planned have for the contingency buffer?

<p>It indicates that some buffer may be spared. (D)</p> Signup and view all the answers

What is the primary focus of budgeting in project management?

<p>Preparing the financial records to monitor expenditure (A)</p> Signup and view all the answers

Which of the following best describes direct costs in a project?

<p>Costs related to the production of project outputs (C)</p> Signup and view all the answers

What does the Cost Element Structure help achieve in project cost management?

<p>It reduces the risk of double accounting of expenses (B)</p> Signup and view all the answers

Which of the following is considered an indirect cost?

<p>Office space costs such as rent and utilities (C)</p> Signup and view all the answers

What is the purpose of life cycle cost (LCC) in project management?

<p>To determine the total costs required to operate a system throughout its lifecycle (C)</p> Signup and view all the answers

Which option accurately describes indirect costs allocation?

<p>Indirect costs can be allocated using a flat or proportional rate based on effort (D)</p> Signup and view all the answers

What is included under personnel direct costs in a project?

<p>Salaries of individuals directly involved in project execution (A)</p> Signup and view all the answers

What is the primary role of cost control in budgeting?

<p>To monitor project expenses and ensure they align with the budget (C)</p> Signup and view all the answers

What is meant by 'project overheads'?

<p>Overheads that can be directly assigned to a specific larger project (C)</p> Signup and view all the answers

Flashcards

Resource Usage

The total work required for a resource during a specific period.

Overallocation

A situation where a resource is assigned more work than its capacity.

Resource Leveling

A technique to prevent resource overallocation by inserting soft constraints in a project plan.

Project Plan Constraints

Limitations that cannot be altered in a project's schedule.

Signup and view all the flashcards

Task Allocation

Assigning specific tasks to particular resources.

Signup and view all the flashcards

Resource Capacity

The maximum amount of work a resource can handle within a specific time frame.

Signup and view all the flashcards

Overallocation Example

One resource being assigned to multiple tasks exceeding its capacity.

Signup and view all the flashcards

Project Schedule

A plan outlining the sequence and timing of tasks in a project.

Signup and view all the flashcards

Fast Tracking

A project management technique that overlaps sequential activities to shorten the project schedule.

Signup and view all the flashcards

Overlapping Activities

Carrying out multiple tasks concurrently rather than sequentially.

Signup and view all the flashcards

Deliverable Incrementality

The gradual development and refinement of a deliverable throughout the activity, not just at the end.

Signup and view all the flashcards

Project Schedule Shortening

The goal of fast tracking, to complete the project sooner.

Signup and view all the flashcards

Rework Risk

The chance that changes or rework might be needed due to fast-tracking overlapping tasks.

Signup and view all the flashcards

Dependency Analysis

Evaluating the connections between activities in a project to determine the importance of breaking dependencies.

Signup and view all the flashcards

Intermediate Outputs

Parts of a deliverable created and reviewed during an activity rather than only at the end.

Signup and view all the flashcards

Stability of Intermediate Outputs

Assessing the extent to which intermediate outputs are reliably completed and evaluated before incorporating them into the overall deliverable.

Signup and view all the flashcards

CCM Estimation

A method for estimating project duration and contingency that accounts for potential variations in activity durations.

Signup and view all the flashcards

Item 1 (duration + contingency)

The initial estimate of the project's duration, including a buffer for unexpected delays.

Signup and view all the flashcards

Item 2 (sum of variances)

The total potential variation in activity durations, calculated by adding the variances of each activity.

Signup and view all the flashcards

CCM: Buffer Overflow

When the total variation in activity durations exceeds the contingency buffer, indicating potential delays.

Signup and view all the flashcards

CCM Approach: Shorter Plan?

CCM aims to create a more realistic schedule compared to traditional methods by incorporating potential variations.

Signup and view all the flashcards

Critical Chain Management

A project management approach that focuses on managing the "critical chain" of activities, recognizing that estimations are average guesses, and contingencies are often unnecessary.

Signup and view all the flashcards

Contingency

The difference in duration between a 50% probable estimate and a 90% probable estimate in project management.

Signup and view all the flashcards

Project estimations

Average guesses about how long an activity will take, often padded with extra time (pessimistic estimation) to account for potential issues.

Signup and view all the flashcards

Critical Chain

The sequence of tasks in a project that determine the project's overall duration if all tasks are finished in 'most probable' time, excluding contingencies.

Signup and view all the flashcards

Standard Deviation

A measure of the variability or dispersion of a set of project estimations.

Signup and view all the flashcards

Probability (in project estimates)

The likelihood a given project task will be completed by a certain point in time. It relates to the most probable, best-case, and worst-case scenarios.

Signup and view all the flashcards

Activity Duration

The predicted time required to complete a specific task or activity in a project.

Signup and view all the flashcards

Traditional Estimation

A project estimation method that often overestimates project times due to adding padding to the pessimistic side.

Signup and view all the flashcards

Chain Management

Managing a series of dependent tasks that must be completed in a specific order to achieve a project milestone. Focuses on the flow of work and preventing delays caused by bottlenecks.

Signup and view all the flashcards

Contingency Buffer

A reserve of time or resources allocated in a project plan to handle unexpected delays or unforeseen events.

Signup and view all the flashcards

CCM (Critical Chain Method)

A project management technique that emphasizes managing chains of dependent tasks to identify and mitigate potential delays. Focuses on minimizing overall project risk and uncertainty.

Signup and view all the flashcards

What chains are best to consider?

Deciding which chains of tasks are most critical to the project's success and should be prioritized for buffer allocation.

Signup and view all the flashcards

Buffer Overflow

When the contingency buffer allocated for a chain is depleted due to delays or unexpected events.

Signup and view all the flashcards

When to start worrying about overflow?

Determines the point at which project managers need to take action when a contingency buffer is nearing depletion. Actions may include adjusting the plan, identifying new resources, or taking other mitigation measures.

Signup and view all the flashcards

Project Budget

The financial plan for a project, outlining the estimated costs of resources, labor, and other expenses.

Signup and view all the flashcards

Software Cost Estimation

Estimating the total cost of developing and deploying software, including factors such as staff salaries, equipment, licenses, and other expenses.

Signup and view all the flashcards

Project Cost

The total expense needed to complete a project, excluding profit. It comprises direct and indirect costs.

Signup and view all the flashcards

Direct Costs

Expenses directly related to the actual production of the project's outputs. Examples include employee salaries, materials, and specific hardware.

Signup and view all the flashcards

Indirect Costs

Expenses incurred to run the facility and support the project indirectly. Examples include office rent, administrative staff, and general equipment.

Signup and view all the flashcards

Cost Element Structure

A hierarchical breakdown of cost items used to determine the project budget. This helps organize and monitor expenses to prevent double-counting.

Signup and view all the flashcards

What are the two main types of project costs?

Direct costs are directly related to the project's outputs, while indirect costs are general expenses for running the project's operations.

Signup and view all the flashcards

What is the purpose of the Cost Element Structure?

To organize the costs of a project into a clear and hierarchical system, making it easier to monitor and avoid double-counting expenses.

Signup and view all the flashcards

General Overheads

Indirect costs related to running the general facility, like office space, utilities, and administrative staff.

Signup and view all the flashcards

Project Overheads

Indirect costs specifically attributed to a particular project, like specific resources or expenses dedicated to it.

Signup and view all the flashcards

What is the strategy for allocating indirect costs?

Indirect costs are allocated to projects based on a chosen method, such as the project's effort or budget, to ensure fair distribution.

Signup and view all the flashcards

Personnel Costs: Gross vs. Net

When calculating personnel costs, use the gross salary (including taxes and contributions) since it reflects the actual expenditure by the company.

Signup and view all the flashcards

Study Notes

Optimizing the Plan

  • Critical Path Method (CPM) focuses on duration, not risk or difficulty
  • Activities outside the critical path can still delay the overall project if the delay is significant.
  • Delays in non-critical activities can impact critical path activities and project timelines.
  • Inputs for planning include activities, constraints, effort, team, and delivery dates.

Resource Allocation and Leveling

  • Resource allocation assigns resources to tasks based on availability and needs.
  • Over-allocation (exceeding maximum availability) is a constraint that must be managed.
  • Resource leveling adjusts assignments to avoid over-allocation.
  • If no solution is found, testing different hypotheses (e.g., increasing team size or relaxing constraints) can help.

Resource Allocation Examples

  • Resource allocation examples show resource assignment percentages and hours per week.
  • R1 is allocated 50% of time to Task 1 and 50% to Task 3; R2 is fully allocated to Task 2 and 50% to Task 3.
  • R1 works 20 hours each week, while R2 works 40 hours per week.

Resource Usage

  • Manpower usage refers to the time each resource is needed.
  • Equipment usage counts the items of equipment needed.
  • Material usage tracks the quantity of materials required.

How is Resource Usage Computed?

  • Resource usage sums work allocated for each period, essentially taking a vertical total over the work assignments.

  • Overallocation happens when resource use exceeds maximum capability.

Example

  • R1 is overallocated in week 2 (T+1w) and week 3 (T+2w).

More Complete Example

  • The provided example visually highlights constraints and shows two resources assigned to Task 2 to accommodate those constraints.

Example

  • Task 1 and Task 3 require the same resource resulting in overallocation

Example

  • Solution 1 involves resource leveling with soft constraints to prevent overallocation.
  • Solution 2 discusses several compression techniques.

Goals of the Unit

  • Learn techniques to shorten project plans.
  • Understand risks associated with shortening project plans.

Change Control and Configuration Management

  • This relates to quality, risk and resource management during the project execution.

Preliminary Consideration

  • The initial plan often reveals the project won't meet the deadline given assumptions.
  • If the plan is accurate, options include not starting the project or shortening it.
  • Revising the estimations isn't a recommended approach.

Making your plan feasible

  • Change project hypotheses (reduce scope, quality, outsource).
  • Adjust the project logic; e.g., increase resources, change the process.
  • Break constraints (e.g., fast tracking).
  • Manage probability of delivering on time (e.g., critical chain management).

Project Crashing

  • Project crashing shortens the project timeline by accelerating critical path activities within the project.
  • It focuses on reducing duration while minimizing cost impact.
  • More labor or resources are applied to critical path activities, which may increase the project cost.
  • The decision to use crashing is based on a tradeoff between time and cost.

Project Crashing Example

  • Project crashing examples illustrate cost/benefit analysis between increased costs and faster project completion timeline in scenarios

Project Crashing (Simple) Example

  • Late projects incur delay costs.
  • Activities (e.g., task 2 and 3) can be shortened by adding resources; the costs are given as example figures

Project Crashing (Simple) Example

  • The best way to proceed depends on whether shortening project and increasing resulting costs are a preferred solution

Fast Tracking

  • Overlapping activities in a project (that were sequential / finish to start) can shorten the project timeline.
  • This method leverages the fact that some project deliverables/outcomes are incrementally produced/refined during the activity execution.

Fast Tracking, Issues and Rules

  • Fast tracking carries risks, including rework. Evaluating dependencies' effects, such as intermediate outputs and stability, is critical.
  • Rework in a subsequent activity might negatively impact the overall plan, and this is a risk that must be assessed

Fast Tracking, Pros and Cons

  • Pros include no extra costs and shortened project time, while cons include increased risk due to more sensitive networks and greater need for communication.

Fast Tracking vs Resource Crashing

  • Comparison of fast tracking and resource crashing is presented visually.

Critical Chain Management

  • Critical Chain Management assumes that estimations are average guesses and thus projects are likely completed later than expected
  • Attempts to manage contingencies via padding estimates to be a pessimistic / more likely completion times

CCM: Item 1 (Estimates)

  • In CCM, project estimations focus on probable duration estimates rather than worst-case scenarios

CCM: Item 2 (Sum of Variances)

  • Using chains for activities reduces the variance in overall time estimations compared to summing each individual activity uncertainty. Variance calculation of projects (consist of multiple activities) is less than the sum of individual activities variance.

CCM Basic Idea

  • CCM emphasizes considering chains of activities, and the explicit allocation of contingency buffers to handle uncertainty in estimations.
  • Statistical variation during project execution might cause delays, but having buffer time within the plan helps to manage that uncertainty

CCM: Managing Chains

  • Identifying how chains of activities will be prioritized and how to adjust for contingency is crucial in project estimation models using CCM

Costing and Budgeting (from cost to value)

  • Budgeting entails assessing financial needs and recording relevant expenditure and income data.

Goals of the Unit (Costing and Budgeting)

Understand software development costs. Determine whether a project stays on budget.

Some Definitions

  • Costing defines the bare cost of the project (excluding profit)
  • Budgeting/cost control addresses the project's financial needs and the recording of expenditure and income.
  • Pricing estimates how much a product or project will cost
  • LCC (Life Cycle Costs) examines the total cost anticipated for the entire project lifecycle

(Software) Project Costing

Project Cost Management

  • Defines policies and procedures for cost planning, management, tracking and control. Summarizes associated processes.

Project Cost Management (Process)

  • Highlighting all of the costing management input parameters, along with the Plan Cost Management process itself, as well as the output.

Project Cost Management (Process)

  • Defines the various input components involved in the management process.

Project Cost Management

  • Shows detailed definition of components that influence costing, including units of measure, cost levels, accounting relationships, acceptable thresholds for variance from budget, earned value, and reporting formats.

Estimate Costs

  • This process uses inputs like a cost management plan and a project schedule to estimate the resources needed to complete the project.

Project Cost Management

  • Defines the budget as the aggregate of the individual activity costs. Defines various inputs (Cost management plan, Scope baseline, Activity Cost Estimates, Basis of Estimates, Project Schedule, Resource calendars etc.) for the determination of the budget.

Project Costing (Software)

  • Project cost is defined as total expenditures
  • Cost element structure comprises direct and indirect costs

Direct Costs

  • Direct costs include salaries of project personnel, materials, supplies, hardware, and software; travel, meetings and miscellaneous expenses.

Indirect Costs

  • Indirect costs consist of general overheads, such as office space rent and utilities, materials, administrative staff, and project overhead expenses specific to the project.

Indirect Costs Computation

  • Determining indirect costs may involve analysis of previous expenditure, projection of future costs, estimation of work output, and rate of overhead determination

Personnel Costs (Gross vs. Net)

  • Gross pay excludes deductions, whereas net pay reflects salary after these deductions, including taxes, retirement, and other contributions.

Project Cost Formula

  • Provides a mathematical and defined formula for calculating project costs

Project Cost

  • Project costs can be viewed from several perspectives.

Managing Project Costs

  • Project goals include ensuring funds are available for spending and that project expenditure adheres to the budget.
  • Key means include defining a baseline/cash flow, expense authorization, and expenditure tracking.

Project Costs and Project Structure

  • Illustrates a visual mapping (WBS, Work Breakdown Structure) of cost elements.

Project Costs and Time

  • Depicts a financial status (of project costs and incomes) over various measurement periods (e.g., quarters), demonstrating project performance and financial need status.

Project Costs and Time

  • Shows costs (e.g., expenses and incomes) across multiple time quarters (e.g., Q1, Q2). Provides a summary of financial status at points in time

Project Costs and Time (Banana Shape)

  • Shows the ideal project cost trend over time graphically. Indicates typical and realistic cost profiles for projects.

Expenditure/Load Profile

  • Workload distribution over time, not necessarily uniform, can be front-end loaded or back loaded as well as linear, and project planning may use this information.

Expense Authorization

  • Project management/financial management teams usually operate in different structures.
  • Authorizations for expenses and payments might be managed by the project managers or via workflow approvals requiring more complex procedures

Expense Authorization (Example)

  • Example workflow diagram illustrating the step by step required expense authorization process

End of Period Reporting

  • Documentation about project financial status is developed for each accounting period.
  • Information includes budgeted expenditure vs. actual expenditure as well as expenditure recording for the project. This data is essential for monitoring budgets, analyzing variances and future predictions as well as reporting processes at the close of each accounting period

The Workflow

  • Workflows are presented graphically, showing steps involved in budgeting, spending, and managing expenditures for projects

What information you are interested in

  • Key information for managing budgets as well as associated variances and expenditure includes details such as budget, transfers, and actual expenditure amounts.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

Optimizing the Plan PDF

Description

Test your understanding of the Critical Chain Method (CCM) estimation process. This quiz covers key concepts like resource overallocation, project duration calculations, and the implications of plan execution on project management timelines. Explore the important strategies for effective resource management in project planning.

More Like This

Use Quizgecko on...
Browser
Browser