What is required for ensuring safety when working near overhead electrical equipment?
What is required for ensuring safety when working near overhead electrical equipment?
- A safety helmet
- A trained supervisor present
- Standard protective gloves
- Possession of a 'Permit to Work' (correct)
What role does the RE organization play in the 22 kV power supply arrangement?
What role does the RE organization play in the 22 kV power supply arrangement?
- They oversee the installation of step-down transformers.
- They are responsible for repairing broken equipment.
- They monitor energy consumption levels.
- They must man the supply arrangement round the clock. (correct)
What type of transformer is used for the 22 kV energization?
What type of transformer is used for the 22 kV energization?
- Isolation transformer
- Step-up transformer (correct)
- Auto transformer
- Step-down transformer
What must be included in the schematic diagram for the 22 kV power supply arrangement?
What must be included in the schematic diagram for the 22 kV power supply arrangement?
How should the organization respond to breakdowns in the 22 kV supply arrangement?
How should the organization respond to breakdowns in the 22 kV supply arrangement?
What is the purpose of the First-Aid Boxes in the specified locations?
What is the purpose of the First-Aid Boxes in the specified locations?
Which procedure is necessary before work can commence near overhead electrical equipment?
Which procedure is necessary before work can commence near overhead electrical equipment?
What is required to be published at least a month in advance of energization?
What is required to be published at least a month in advance of energization?
What is the significance of the audible and visual indication arrangement in the power supply arrangement?
What is the significance of the audible and visual indication arrangement in the power supply arrangement?
Which notification is NOT included in the public notifications for energization?
Which notification is NOT included in the public notifications for energization?
What is one of the responsibilities of maintenance staff in relation to insulated tools?
What is one of the responsibilities of maintenance staff in relation to insulated tools?
What should be done with the OHE during night hours?
What should be done with the OHE during night hours?
What should be displayed prominently at each station to ensure safety?
What should be displayed prominently at each station to ensure safety?
Which certificate is necessary regarding the removal of L.T and H.T infringements?
Which certificate is necessary regarding the removal of L.T and H.T infringements?
Who issues the joint safety certificate regarding safety to traffic?
Who issues the joint safety certificate regarding safety to traffic?
What kind of certificate is required for the Department of Telecommunications?
What kind of certificate is required for the Department of Telecommunications?
Which safety measure should be communicated to loco drivers?
Which safety measure should be communicated to loco drivers?
An application to EIG is required for what purpose?
An application to EIG is required for what purpose?
What kind of warnings should be stenciled on diesel and steam locos?
What kind of warnings should be stenciled on diesel and steam locos?
What is the primary purpose of energizing OHE at 2.2kV?
What is the primary purpose of energizing OHE at 2.2kV?
Which stakeholders are involved in ensuring knowledge about safety among staff?
Which stakeholders are involved in ensuring knowledge about safety among staff?
During which hours is the anti-theft energization of OHE allowed?
During which hours is the anti-theft energization of OHE allowed?
Which of the following works must be completed before 2.2kV energization of OHE?
Which of the following works must be completed before 2.2kV energization of OHE?
What requirement must all HT crossings meet for the anti-theft energization?
What requirement must all HT crossings meet for the anti-theft energization?
What must replace existing DC track relays to accommodate 2.2kV energization?
What must replace existing DC track relays to accommodate 2.2kV energization?
What should be implemented on existing semaphore signals if the electrical clearance is insufficient?
What should be implemented on existing semaphore signals if the electrical clearance is insufficient?
Which precaution must be taken regarding overhead structures like ROBs and FOBs?
Which precaution must be taken regarding overhead structures like ROBs and FOBs?
What is the alternative to providing bonding and earthing work in station areas if it has not been completed?
What is the alternative to providing bonding and earthing work in station areas if it has not been completed?
Before anti-theft energization, what must be set up at all level crossings?
Before anti-theft energization, what must be set up at all level crossings?
Which of the following does NOT need to be completed prior to the 2.2kV anti-theft energization?
Which of the following does NOT need to be completed prior to the 2.2kV anti-theft energization?
What must be obtained prior to the energisation of a section at 2.2 kV?
What must be obtained prior to the energisation of a section at 2.2 kV?
Who may conduct the joint checks and tests prior to commissioning?
Who may conduct the joint checks and tests prior to commissioning?
Which of the following checks is NOT typically performed prior to energisation?
Which of the following checks is NOT typically performed prior to energisation?
What test is specifically mentioned for continuity and insulation of the OHE?
What test is specifically mentioned for continuity and insulation of the OHE?
What is the purpose of creating an earth fault during testing?
What is the purpose of creating an earth fault during testing?
Who certifies that the section can be energized at 2.2 kV for test purposes?
Who certifies that the section can be energized at 2.2 kV for test purposes?
What must be checked regarding earthing and bonding of the OHE?
What must be checked regarding earthing and bonding of the OHE?
What type of fault tests are required after certification to energise the section?
What type of fault tests are required after certification to energise the section?
What is indicated as a requirement for height at level crossings?
What is indicated as a requirement for height at level crossings?
What should be done with overhead equipment adjacent to the section to be energized?
What should be done with overhead equipment adjacent to the section to be energized?
What is required to be prominently displayed at each station regarding safety?
What is required to be prominently displayed at each station regarding safety?
Which certificate is specifically related to the telecommunications aspect of the energization process?
Which certificate is specifically related to the telecommunications aspect of the energization process?
What is the purpose of issuing notifications to users of level crossings before energization?
What is the purpose of issuing notifications to users of level crossings before energization?
Who is responsible for issuing the certificate regarding the removal of L.T and H.T infringements?
Who is responsible for issuing the certificate regarding the removal of L.T and H.T infringements?
What type of warning should be communicated to steam/diesel loco drivers regarding safety?
What type of warning should be communicated to steam/diesel loco drivers regarding safety?
Which of the following is NOT included as part of the safety certificates required after completion of work?
Which of the following is NOT included as part of the safety certificates required after completion of work?
What should be included in the public notifications regarding the energization of sections?
What should be included in the public notifications regarding the energization of sections?
What is the purpose of the application to EIG concerning energization?
What is the purpose of the application to EIG concerning energization?
Which of the following safety measures is essential before anti-theft energization?
Which of the following safety measures is essential before anti-theft energization?
What is the maximum allowed duration for anti-theft energization of OHE?
What is the maximum allowed duration for anti-theft energization of OHE?
Which of the following is NOT a requirement to be completed before 2.2kV anti-theft energization?
Which of the following is NOT a requirement to be completed before 2.2kV anti-theft energization?
What voltage level must HT crossings meet for the 2.2kV anti-theft energization?
What voltage level must HT crossings meet for the 2.2kV anti-theft energization?
Which component must be replaced to accommodate the 2.2 kV energization procedures?
Which component must be replaced to accommodate the 2.2 kV energization procedures?
What safety feature must be implemented if the electrical working clearance is insufficient?
What safety feature must be implemented if the electrical working clearance is insufficient?
What must be done regarding the return conductor (RC) in station areas if bonding and earthing work remain incomplete?
What must be done regarding the return conductor (RC) in station areas if bonding and earthing work remain incomplete?
To which structures should height gauges and caution boards be provisioned?
To which structures should height gauges and caution boards be provisioned?
What modifications to communication line track crossings are required for 2.2kV energization?
What modifications to communication line track crossings are required for 2.2kV energization?
What type of boards must be present on over line structures like ROBs and FOBs?
What type of boards must be present on over line structures like ROBs and FOBs?
Which of the following works is NOT specifically mentioned as necessary for 2.2 kV energization?
Which of the following works is NOT specifically mentioned as necessary for 2.2 kV energization?
What is the required distance personnel must maintain from the overhead electrical equipment unless they have a 'Permit to Work'?
What is the required distance personnel must maintain from the overhead electrical equipment unless they have a 'Permit to Work'?
Which of the following is NOT a part of the 22 kV energization process described?
Which of the following is NOT a part of the 22 kV energization process described?
What must the organization issue in the form of a circular concerning the 22 kV power supply?
What must the organization issue in the form of a circular concerning the 22 kV power supply?
Which precaution is advised for personnel working with overhead equipment during the night?
Which precaution is advised for personnel working with overhead equipment during the night?
What does the joint procedure order need to indicate?
What does the joint procedure order need to indicate?
What type of arrangements are necessary for the 22 kV power supply to include?
What type of arrangements are necessary for the 22 kV power supply to include?
Who is responsible for completing the checks and tests prior to commissioning?
Who is responsible for completing the checks and tests prior to commissioning?
What is one of the safety measures to be adhered to regarding the Over Head Equipment?
What is one of the safety measures to be adhered to regarding the Over Head Equipment?
What specific obligation does the RE organization have regarding the 22 kV supply arrangement?
What specific obligation does the RE organization have regarding the 22 kV supply arrangement?
What must be included in the joint safety certificate regarding safety to traffic?
What must be included in the joint safety certificate regarding safety to traffic?
Which individual is preferred for nomination to conduct joint checks and tests before energisation?
Which individual is preferred for nomination to conduct joint checks and tests before energisation?
What is the minimum requirement concerning the height of contact wire at level crossings?
What is the minimum requirement concerning the height of contact wire at level crossings?
What type of fault tests are to be conducted after certifying that a section can be energized at 2.2 kV?
What type of fault tests are to be conducted after certifying that a section can be energized at 2.2 kV?
Which of the following checks ensures the safety of overhead equipment before energisation?
Which of the following checks ensures the safety of overhead equipment before energisation?
Which action is NOT part of the checks carried out before energisation?
Which action is NOT part of the checks carried out before energisation?
Who is responsible for certifying that the section can be energized at 2.2 kV?
Who is responsible for certifying that the section can be energized at 2.2 kV?
What is required in terms of earthing and bonding within station areas?
What is required in terms of earthing and bonding within station areas?
What determines whether the Joint check and tests will be carried out with CEE oversight?
What determines whether the Joint check and tests will be carried out with CEE oversight?
What safety measures are stipulated for overhead equipment adjacent to the energized section?
What safety measures are stipulated for overhead equipment adjacent to the energized section?
Which verification involves clearance compliance with specified dimensions?
Which verification involves clearance compliance with specified dimensions?
Flashcards
Anti-theft energization of OHE
Anti-theft energization of OHE
Energizing Overhead Line Equipment (OHE) at 2.2kV to deter theft of wires, but not for train operation.
Energization Time
Energization Time
Anti-theft energization is limited to nighttime hours, 7 PM to 7 AM.
Structure Bonding (Open Route)
Structure Bonding (Open Route)
Establishing electrical connections between OHE structures and ground in open routes to prevent electrical hazards.
Station Area Bonding
Station Area Bonding
Signup and view all the flashcards
LT Modification
LT Modification
Signup and view all the flashcards
HT Crossing Modifications
HT Crossing Modifications
Signup and view all the flashcards
Semaphore Signal Platform
Semaphore Signal Platform
Signup and view all the flashcards
Track Relays
Track Relays
Signup and view all the flashcards
Communication Line Crossings
Communication Line Crossings
Signup and view all the flashcards
Level Crossings / Caution
Level Crossings / Caution
Signup and view all the flashcards
Public Notifications
Public Notifications
Signup and view all the flashcards
Diesel/Steam Loco Warning
Diesel/Steam Loco Warning
Signup and view all the flashcards
L.T and H.T Infringements
L.T and H.T Infringements
Signup and view all the flashcards
DOT Clearance
DOT Clearance
Signup and view all the flashcards
OHE Work Completion
OHE Work Completion
Signup and view all the flashcards
Level Crossing Gauges
Level Crossing Gauges
Signup and view all the flashcards
Safety to Traffic
Safety to Traffic
Signup and view all the flashcards
Staff Knowledge
Staff Knowledge
Signup and view all the flashcards
EIG Sanction
EIG Sanction
Signup and view all the flashcards
Anti-theft Energization
Anti-theft Energization
Signup and view all the flashcards
Sanction for Energization
Sanction for Energization
Signup and view all the flashcards
Joint Check and Tests
Joint Check and Tests
Signup and view all the flashcards
Clearance in Schedule of Dimensions
Clearance in Schedule of Dimensions
Signup and view all the flashcards
OHE Bonding and Earthing
OHE Bonding and Earthing
Signup and view all the flashcards
Contact Wire Height at Level Crossings
Contact Wire Height at Level Crossings
Signup and view all the flashcards
Protective Screens in Crossings
Protective Screens in Crossings
Signup and view all the flashcards
Isolation of Adjacent Equipment
Isolation of Adjacent Equipment
Signup and view all the flashcards
AC Immune Track Relays
AC Immune Track Relays
Signup and view all the flashcards
Megger Tests for OHE
Megger Tests for OHE
Signup and view all the flashcards
Fault Tests at 2.2 kV
Fault Tests at 2.2 kV
Signup and view all the flashcards
22 kV Power Supply
22 kV Power Supply
Signup and view all the flashcards
22 kV Supply Staff
22 kV Supply Staff
Signup and view all the flashcards
OHE Energization: Live at All Times
OHE Energization: Live at All Times
Signup and view all the flashcards
‘Permit to Work’
‘Permit to Work’
Signup and view all the flashcards
Joint Procedure Order
Joint Procedure Order
Signup and view all the flashcards
Purpose of Public Warning Boards
Purpose of Public Warning Boards
Signup and view all the flashcards
Insulated Tools for Maintenance Staff
Insulated Tools for Maintenance Staff
Signup and view all the flashcards
Modification to Watering Arrangements
Modification to Watering Arrangements
Signup and view all the flashcards
Anti-theft Energization: Purpose
Anti-theft Energization: Purpose
Signup and view all the flashcards
Electrical Rules and Precautions
Electrical Rules and Precautions
Signup and view all the flashcards
When is Anti-theft Energization Used?
When is Anti-theft Energization Used?
Signup and view all the flashcards
Structure Bonding
Structure Bonding
Signup and view all the flashcards
Semaphore Signal Platform Safety
Semaphore Signal Platform Safety
Signup and view all the flashcards
Track Relays Conversion
Track Relays Conversion
Signup and view all the flashcards
Level Crossing Safety
Level Crossing Safety
Signup and view all the flashcards
OHE Energization: When?
OHE Energization: When?
Signup and view all the flashcards
Who Needs a Permit to Work?
Who Needs a Permit to Work?
Signup and view all the flashcards
Public Warning Boards: Where?
Public Warning Boards: Where?
Signup and view all the flashcards
Insulated Tools for Maintenance
Insulated Tools for Maintenance
Signup and view all the flashcards
22 kV Power Supply: How?
22 kV Power Supply: How?
Signup and view all the flashcards
22 kV Supply Staff: Who?
22 kV Supply Staff: Who?
Signup and view all the flashcards
Anti-theft Energization: Why?
Anti-theft Energization: Why?
Signup and view all the flashcards
What is the purpose of 2.2kV energization on OHE?
What is the purpose of 2.2kV energization on OHE?
Signup and view all the flashcards
When are public notifications required for OHE energization?
When are public notifications required for OHE energization?
Signup and view all the flashcards
Why are steam/diesel loco drivers warned?
Why are steam/diesel loco drivers warned?
Signup and view all the flashcards
What certificates are required for OHE energization?
What certificates are required for OHE energization?
Signup and view all the flashcards
Who approves OHE energization at 2.2kV?
Who approves OHE energization at 2.2kV?
Signup and view all the flashcards
What safety measures are taken for steam and diesel locos?
What safety measures are taken for steam and diesel locos?
Signup and view all the flashcards
Why is DOT clearance necessary?
Why is DOT clearance necessary?
Signup and view all the flashcards
What is the purpose of protective screens on ROBs and FOBs?
What is the purpose of protective screens on ROBs and FOBs?
Signup and view all the flashcards
How is staff knowledge regarding safety ensured?
How is staff knowledge regarding safety ensured?
Signup and view all the flashcards
What is the role of the CEE(P), CSTE(P), and CE(P) in OHE energization?
What is the role of the CEE(P), CSTE(P), and CE(P) in OHE energization?
Signup and view all the flashcards
Study Notes
General Guidelines for Anti-theft Charging of OHE
- Anti-theft energization of overhead contact wire (OHE) at 2.2kV is used to deter theft
- This measure is for preventing theft, not for train operation
- It is unlikely to affect signaling and telecommunication systems because of low current
- Works such as installing isolators, section insulators, switches, and adjustments must be completed (or at least checked) prior to charging at 2.2kV
- Anti-theft charging is limited to night hours (7 PM to 7 AM)
Works to be Completed Prior to 2.2kV Energization
-
Structure and Rail Bonding: Complete bonding and earthing in accordance with the bonding and earthing code. Station areas, if bonding/earthing is incomplete, use the return conductor (RC) as earth wire attached to structures/supports via jumpers.
-
Low Tension (LT) Modifications: All necessary LT modifications must be done
-
High Tension (HT) Crossing Modifications: All HT crossings must meet the 2.2kV standards
-
Semaphore Signals: Wire mesh screens on working platforms of existing semaphore signals (if working clearance of 2m isn't available)
-
Signal Post Clearances: No part of a signal post/fitting should be less than 700mm from the live conductor
-
Communication Line Conversion: Convert track crossings to cable and remove overhead wires
-
Level Crossing Provisions: Height gauges, caution boards (25kV), public warning boards, and first-aid boxes installed at level crossings
-
Staff Safety: Insulated tools and modified watering arrangements, water columns for staff
-
Other Important Preparations: all relevant rules and precautions according to Indian Electricity Rules applied to the work
22kV Power Supply Arrangement
- Local 22kV supply available at a station with a step-up transformer, fuses, audible and visual indications.
- A schematic diagram needs to be approved by the EIG (Engineering Inspectorate Group).
- 22kV supply arrangement to have round-the-clock operation by Railway employee (RE). Responsibilities and staff availability in normal and abnormal situations must be detailed and distributed.
- OHE is energized at night, but must be considered live and hazardous to all people who aren't authorized.
- A permit to work procedure is necessary for personnel working or near the energized system.
Energization Procedures
- Publication and display notices a month before energization: Public notices and notifications (English, Hindi, local) are mandatory about the section(s) that will be energized, including level crossings
- Display visual warnings: caution notices at all important locations, including signage on diesel/steam locomotives, locosheds and warning messages
- Detailed checklist given for checks and tests before charging: including clearances between live and earthed structures, earthing/bonding, proper height of contact wires, protective screens on critical equipment, appropriate earthing/isolation of overhead equipment and appropriate removal of wires.
Tests
- Megger tests for OHE continuity and insulation
- Earth fault tests at the farthest parts of the energized OHE, to ensure fuses are working properly.
- Tests to be carried out by a designated officer from the Government for Railways or the authorized representative from the Railway side
- Certificates should be obtained from the concerned authorities.
- A notification that the OHE is energized is required.