Which of the following best defines an activity in a project?
Which of the following best defines an activity in a project?
- The actual performance of a task (correct)
- The completion of a specific event
- A recognizable part of a work project
- A task that consumes time and resources
What is the difference between an activity and an event in a project?
What is the difference between an activity and an event in a project?
- An activity requires time and resources, while an event is any portion of a project
- An activity is the work required to complete a specific event (correct)
- An activity is a recognizable part of a work project, while an event is the actual performance of a task
- An activity consumes time and resources, while an event is the completion of a specific task
Which of the following best describes an activity in a project?
Which of the following best describes an activity in a project?
- A task that requires manpower, material, and facilities
- A task that consumes time or resources and has a specific start and end (correct)
- The actual performance of a task
- A recognizable part of a work project
What is the purpose of an activity in a project?
What is the purpose of an activity in a project?
Which of the following is NOT required for the completion of an activity in a project?
Which of the following is NOT required for the completion of an activity in a project?