According to the text, what is the time frame for appointing a Project Mediator?
According to the text, what is the time frame for appointing a Project Mediator?
- Within 10 Working Days after the parties neglected to make an appointment
- Within 10 Working Days after the Contract was awarded
- Within 20 Working Days after the Contract was awarded (correct)
- Within 20 Working Days after the parties neglected to make an appointment
According to the text, what happens if a party accepts a finding of the Construction Manager or the Consultant?
According to the text, what happens if a party accepts a finding of the Construction Manager or the Consultant?
- The party waives and releases the other party from any claims in respect of the particular matter dealt with in that finding (correct)
- The party can still send a Notice in Writing of dispute to the other party, the Construction Manager, and the Consultant
- The party can request the Project Mediator to assist in resolving the dispute
- The party can refer the dispute to be finally resolved by arbitration
According to the text, what is the next step if a dispute has not been resolved within 10 Working Days after the Project Mediator was requested?
According to the text, what is the next step if a dispute has not been resolved within 10 Working Days after the Project Mediator was requested?
- The parties refer the dispute to the courts
- The parties request arbitration
- The Project Mediator terminates the mediated negotiations (correct)
- The parties request further mediation
According to the text, when can disputes referred to arbitration be held in abeyance?
According to the text, when can disputes referred to arbitration be held in abeyance?
Who is responsible for construction health and safety at the Place of the Project?
Who is responsible for construction health and safety at the Place of the Project?
What should the Trade Contractor do if they observe or suspect the presence of mould at the Place of the Project?
What should the Trade Contractor do if they observe or suspect the presence of mould at the Place of the Project?
Who is responsible for the cost of remediating or disposing of mould if it was caused by the Trade Contractor's operations under the Contract?
Who is responsible for the cost of remediating or disposing of mould if it was caused by the Trade Contractor's operations under the Contract?
What should the Owner do if they agree that the presence of mould was not caused by the Trade Contractor's operations?
What should the Owner do if they agree that the presence of mould was not caused by the Trade Contractor's operations?
According to the text, who is responsible for protecting the Project and the Owner's property from damage caused by the Trade Contractor's operations under the Contract?
According to the text, who is responsible for protecting the Project and the Owner's property from damage caused by the Trade Contractor's operations under the Contract?
Before commencing any Work, what must the Trade Contractor do?
Before commencing any Work, what must the Trade Contractor do?
Who is responsible for making good any damage to the Work or Owner's property for which the Trade Contractor is not responsible?
Who is responsible for making good any damage to the Work or Owner's property for which the Trade Contractor is not responsible?
Who is responsible for taking all necessary steps to dispose of, store, or render harmless toxic or hazardous substances that were present at the Place of the Project prior to the Trade Contractor commencing the Work?
Who is responsible for taking all necessary steps to dispose of, store, or render harmless toxic or hazardous substances that were present at the Place of the Project prior to the Trade Contractor commencing the Work?
According to Part 8 of the General Conditions, disputes between the parties to the Contract that are not resolved by the Construction Manager or the Consultant shall be settled in accordance with the requirements of which section?
According to Part 8 of the General Conditions, disputes between the parties to the Contract that are not resolved by the Construction Manager or the Consultant shall be settled in accordance with the requirements of which section?
If a dispute arises under the Contract in respect of a matter in which neither the Construction Manager nor the Consultant have authority to make a finding, which procedures apply to that dispute?
If a dispute arises under the Contract in respect of a matter in which neither the Construction Manager nor the Consultant have authority to make a finding, which procedures apply to that dispute?
If a dispute is not resolved promptly, what instructions will the Construction Manager give?
If a dispute is not resolved promptly, what instructions will the Construction Manager give?
By acting immediately according to the Construction Manager's instructions in the event of a dispute, what will the parties not jeopardize?
By acting immediately according to the Construction Manager's instructions in the event of a dispute, what will the parties not jeopardize?
According to the text, which section of the General Conditions addresses dispute resolution?
According to the text, which section of the General Conditions addresses dispute resolution?
According to the text, what is the exception to the taxes and customs duties included in the Contract Price?
According to the text, what is the exception to the taxes and customs duties included in the Contract Price?
If a party does not accept the expert's finding, what steps are they required to take according to the text?
If a party does not accept the expert's finding, what steps are they required to take according to the text?
According to the text, what is the purpose of GC 9.5 - MOULD?
According to the text, what is the purpose of GC 9.5 - MOULD?
According to the text, what section of the General Conditions addresses taxes and duties?
According to the text, what section of the General Conditions addresses taxes and duties?
According to the text, if the Owner and Trade Contractor agree that toxic or hazardous substances were brought onto the Place of the Project by the Trade Contractor or anyone for whom the Trade Contractor is responsible, what is the responsibility of the Trade Contractor?
According to the text, if the Owner and Trade Contractor agree that toxic or hazardous substances were brought onto the Place of the Project by the Trade Contractor or anyone for whom the Trade Contractor is responsible, what is the responsibility of the Trade Contractor?
According to the text, if the Owner and Trade Contractor do not agree on the existence or significance of toxic or hazardous substances brought onto the Place of the Project, what action should the Owner take?
According to the text, if the Owner and Trade Contractor do not agree on the existence or significance of toxic or hazardous substances brought onto the Place of the Project, what action should the Owner take?
According to the text, if the Owner and Trade Contractor agree that toxic or hazardous substances were not brought onto the Place of the Project by the Trade Contractor or anyone for whom the Trade Contractor is responsible, what action should the Owner take?
According to the text, if the Owner and Trade Contractor agree that toxic or hazardous substances were not brought onto the Place of the Project by the Trade Contractor or anyone for whom the Trade Contractor is responsible, what action should the Owner take?
According to the text, if the Owner and Trade Contractor do not accept the expert's findings on the existence or significance of toxic or hazardous substances, how should the disagreement be settled?
According to the text, if the Owner and Trade Contractor do not accept the expert's findings on the existence or significance of toxic or hazardous substances, how should the disagreement be settled?
True or false: The Contract Price includes all taxes and customs duties except for Value Added Taxes payable by the Owner to the Trade Contractor as stipulated in Article A-4 of the Agreement - CONTRACT PRICE.
True or false: The Contract Price includes all taxes and customs duties except for Value Added Taxes payable by the Owner to the Trade Contractor as stipulated in Article A-4 of the Agreement - CONTRACT PRICE.
True or false: Disputes referred to arbitration can be held in abeyance until the Project Mediator has been appointed.
True or false: Disputes referred to arbitration can be held in abeyance until the Project Mediator has been appointed.
True or false: By acting immediately according to the expert's determination in the event of a dispute, neither party will jeopardize any claim they may have to be reimbursed as provided by GC 9.5 - MOULD.
True or false: By acting immediately according to the expert's determination in the event of a dispute, neither party will jeopardize any claim they may have to be reimbursed as provided by GC 9.5 - MOULD.
True or false: According to the text, disputes between the parties to the Contract that are not resolved by the Construction Manager or the Consultant shall be settled in accordance with the requirements of Part 8 of the General Conditions - DISPUTE RESOLUTION.
True or false: According to the text, disputes between the parties to the Contract that are not resolved by the Construction Manager or the Consultant shall be settled in accordance with the requirements of Part 8 of the General Conditions - DISPUTE RESOLUTION.
True or false: The Trade Contractor is responsible for making good any damage to the Work or Owner's property for which they are not responsible.