CIAP Document 102: Uniform General Conditions of Contract for Private Construction (Philippines) PDF

Loading...
Loading...
Loading...
Loading...
Loading...
Loading...
Loading...

Summary

This document is an in-depth look at CIAP Document 102, a set of uniform general conditions for private construction contracts in the Philippines. It covers key definitions, procedures, and responsibilities of parties involved. The document aims to enhance fair contractual relationships in the construction industry.

Full Transcript

CIAP Document 102: Uniform General Conditions of Contract for Private An in-depth look at CIAP Document 102 for private construction Construction contracts Introduction to CIAP Document 102 What is CIAP Document 102? CIAP Document 102 or the “Uniform General Conditions of Cont...

CIAP Document 102: Uniform General Conditions of Contract for Private An in-depth look at CIAP Document 102 for private construction Construction contracts Introduction to CIAP Document 102 What is CIAP Document 102? CIAP Document 102 or the “Uniform General Conditions of Contract for Private Construction” contains terms and conditions ordinarily established in construction contracts. It is intended for use in contracts for private construction in the Philippines. What is the intent of CIAP Document 102? CIAP Document 102 was formulated to provide the procedures, guidelines, and criteria to be used by parties in a construction Contract, or reference to the Contract to address deficiencies and/or any ambiguity. The CIAP Document 102 will contribute to the enhancement of fair contractual relationships in the construction industry. What is a Construction Contract? A typical Construction Contract consists of an Agreement, General Conditions, Drawings, Specifications, and other documents. Key Definitions and Documents Contract Agreement used to describe the combination of used to describe the agreement two (2) sets of documents: the signed by the Owner and the Agreement and the Contract Contractor, excluding the Contract Documents. Documents. Contract Documents are attached to the Agreement identified therein as Contract Documents, including all additions, deletions and modifications which generally include the following: Special Provisions or Conditions; General Conditions; Specifications; Drawings; and other Bid Documents. Key Definitions and Documents Special Provisions or Specifications Conditions are instructions which are issued are the written or printed prior to bidding to supplement description of the work to be done and/or modify the Drawings, describing qualities of the material Specifications and/or General to be used, the equipment to be Conditions of the Contract. installed and the mode of Drawings General Conditions of construction. are graphical presentations of the pertain Contract to the roles, rights and Work, including supplementary obligations of the contracting details and shop drawings. parties, and the rules and procedures by which the parties and everyone concerned will be able to meet their obligations and perform the Works covered under the Contract. CIAP Document 102 contains these conditions which are generally applicable for all types of construction contracts, to wit: Section I. Definitions and Documents (Art. 1 Definitions; Art. 2 Execution, Correlation, Meaning of Terms and Intent of Documents; Art. 3 Drawings and Specifications; Art. 4 Detail Drawings and Instructions; Art. 5 Shop Drawings) Section II. Laws, Regulations, Site Conditions, Permits & Taxes (Art. 6 Laws and Site Conditions; Art. 7 Permits, Taxes and Surveys) Section III. Equipment and Materials (Art. 8 General; Art. 9 Equipment; Art. 10 Materials, Fixtures, Appliances, and Fittings Furnished by the Contractor; Art. 11 Materials, Equipment, Fixtures, Appliances and Fittings Furnished by the Owner; Art. 12 Royalties and Patents; Art. 13 Manufacturer’s Directions) Section IV. Premises and Temporary Structures (Art. 14 Use of Premises; Art. 15 Temporary Structures and Facilities) CIAP Document 102 contains these conditions which are generally applicable for all types of construction contracts, to wit: Section V. Protection of Work and Property (Art. 16 Protection of Work and Owner’s Property; Art. 17 Protection of Adjacent Property and Existing Utilities; Art. 18 Protection of Life, Work and Property During an Emergency) Section VI. Labor, Work and Payments (Art. 19 Labor; Art. 20 Work; Art. 21 Time of Completion of Work; Art. 22 Payments) Section VII. Contractor-Separate Contractor-Subcontractors Relationship (Art. 23 Separate Contracts with Other Contractors; Art. 24 Contractor-Separate Contractors Relations; Art. 25 Sub-Contracts) CIAP Document 102 contains these conditions which are generally applicable for all types of construction contracts, to wit: Section VIII. Suspension of Work and Termination of Contract (Art. 26 Contractor’s Rights to Suspend Work or Terminate Contract; Art. 27 Owner’s Right to Suspend the Work; Art. 28 Owner’s Right to Terminate Contract; Art. 29 Owner’s Right to proceed with the Work After Reduction in Contractor’s Scope of Work, Partial Takeover from Contractor) Section IX. Responsibilities and Liabilities of Contractor and of Owner (Art. 30 Contractor’s Responsibility for Accidents and Damages; Art. 31 Contractor’s Insurance and Bonds; Art. 32 Owner’s Responsibilities and Liabilities; Art. 33 Liens, Disputes and Arbitration) Section X. Owner’s Representative Section XI. Schedule of Time Limits What is the importance of clear contract terms and harmonized contract documents? Many disputes in construction arise from inconsistent and ambiguous contract terms and conditions which lead to varied interpretations and conflict between the contracting parties. To avoid disputes that may affect the completion of the Work and strain the relationship of the parties, it is important that contract documents objectively reflect the agreement and true intent of the parties. Section I (Definitions and provides the definitions Documents) of the terms used and the execution, correlation, and intent of contract documents, as well as the rules to be followed in case of conflict or discrepancy. Section II (Laws, Regulations, Site Conditions, Permits stipulates and compliance with all Laws in so far as Taxes) they are binding upon or affect the parties to the Contract. What are the obligations of the contracting parties when it comes to permits and licenses, and payment of taxes? The Owner, with the Contractor’s assistance, shall secure and pay all construction permits and licenses necessary for the execution of the Work. The Contractor shall secure the Final Occupancy Permit, but he shall not be responsible to the Owner if, without his fault, the license is not issued or there was delay in its issuance. The Contractor shall pay all taxes as required by Laws pertinent to the construction of the project Who is in charge of the safety and Who has the obligation to protect sanitation in the work premises? the Work and the Owner’s property Pursuant to Section IV & VI, the Contractor is from damage? in charge of the safety and sanitation at the Section V (Protection of Work and Property) work site during and upon completion of provides that it is the obligation of the work. Contractor to protect the work and the Owner’s property from damage. Who is responsible for accidents in the work premises? Section IX, Article 30 (Contractor’s Responsibility for Accidents and Damages) states that the Contractor shall be primarily responsible for all safety measures in executing the Work. What are the bonds and guarantees required of the Contractor? Section IX, Article 31 (Contractor’s Insurance and Bonds), enumerates the insurance, bonds, and guarantees required of the contractor, to wit: 1. Contractor’s Liability Insurance (Contractor, Subcontractors and Owner) 2. Accident Insurance for Workers 3. Contractor’s Fire Insurance 4. Contractor’s Performance and Payment Bonds 5. Contractor’s Guarantee Bond Is the Owner required to obtain Is the Subcontractor also required to insurance? obtain bonds and insurance? Article 32.02 states that the Owner may opt Article 33.03 provides that the Subcontract to obtain an insurance that will protect him must require the Subcontractor to obtain the from his contingent liability. same bonds and insurance coverage as are required of the Contractor What is the difference in the contractual relationship between the Owner and “Separate Contractor” and between the Contractor and the “Subcontractor”? The Owner shall provide for the coordination of the work performed by the Separate Contractor with the Work of the Contractor. The Contractor is fully responsible to the Owner for the acts and omissions of his Subcontractors. Is there a contractual relationship between the Owner and the Subcontractor? The consent of the Owner to the Contractor’s engagement of a Subcontractor shall not create any contractual relation between the Subcontractor and the Owner. Is it required to appoint an Owner’s representative? Section X, Article 34 (Owner’s Representative) provides for the appointment of the representative of the Owner, and the extent and limitation of the authority granted to the representative. Is the Owner required to make advance payment to the Contractor? Article 32 (Owner’s Responsibilities and Liabilities) provides that the Owner shall pay the Contractor an advance payment, which shall be used for mobilization, purchase of materials, and shall be recouped pro rata in the progress billings. Can the Contractor commence with the Work even without the consent of the Owner? Article 21.01 (Notice to Proceed, when required) states that premature commencement of construction shall be at the Contractor’s risk, and the Owner gives the Contractor express or implied authority to do so. How can the Owner ensure the quality and efficient execution of the Work? Section VI (Labor, Work and Payments) provides that the Owner shall at all times have access to the Work and shall provide sufficient number of inspectors while Work is in progress to ensure quality. Is substitution of materials and equipment allowed? Section III (Equipment and Materials) provides that all materials and equipment must conform to all Laws that are in force and applicable during the period of construction, and that the Contractor shall bear all damages by reason of any delay in the Work arising from failure to comply with such Laws. What constitutes Change Order and adjustment of contract price? Section VI, Article 20 (Work) describes the circumstances that are covered by a Change Order and that warrant adjustment in contract price and, if necessary, corresponding adjustment in completion time. What are the conditions for the release of payment to the Contractor? Art. 22.01 provides that the Contractor shall submit to the Owner the Breakdown of Work and Corresponding Value of the Contract Amount showing the value assigned to each part of the Work. What is Progress Payment? The Contractor may submit periodically but not more than once each month a Request for Payment for work done. Each request for progress payment shall be computed from the work completed on all items listed in the Breakdown of Work and Corresponding Value, less a retention of 10% of the progress payment to the Contractor. What is Retention Money? Progress payments are subject to retention of ten percent (10%). The purpose of retention is to cover uncorrected discovered defects and third party liabilities. (Not in CIAP Doc. 102) What are the documents to be submitted by the Contractor to the Owner before final payment? 1. Certificate of Final Building Occupancy; 2. Certificate of Final Inspection of electrical, telephone, sanitary, mechanical, water, gas, safety and other utilities; 3. Original and three (3) sets of prints of “As-Built Drawings” of electrical, sanitary, gas, telephone, and mechanical works; 4. Three (3) copies of Directory of Panel Boards and list of circuits; 5. Three (3) copies of Instructions and Manual for operating and maintaining of fixtures and equipment; 6. Three (3) copies of Keying Schedule; and 7. Release of liens arising under the Contract (Sworn Statement or Indemnity Bond). Does the release of final payment relieve the Contractor of liability for any defect in the Work? After release of final payment and acceptance by the Owner of the Work, the Contractor is still liable for any defect in the Work, if: 1. the defect is hidden; 2. the Owner’s acceptance of the Work was made with reservations to specific portion of the Work; 3. inferior work or work which does not comply with the Drawings and Specifications and is apparent upon inspection by the Owner within one year from final payment; and 4. hidden defect discovered within the warranty period or within one year from posting of the Guarantee Bond. The Contractor is likewise liable for damages if the edifice falls, within fifteen years from completion of the structure, on account of defects in the construction or the use of materials of inferior quality or due to any violation of the terms of the Contract as provided When shall the Owner release the retention money? The amount retained by the Owner under the provision of the Contract shall be released not later than the expiration of the “Period of Making Good of Known Defects”. What does “Period of Making Good of Known Defects” mean? The expression “Period of Making Good of Known Defects” shall mean a period of not more than thirty (30) calendar days, calculated from the date of receipt by the Contractor of the last item in the punch list. If after release to the Contractor of final payment or retention there are still unpaid claims of Subcontractors and/or suppliers, is the Owner obliged to pay such claims? Section IX, Article 33.01 provides that, as a condition to final payment and/or release of the retention, the Contractor shall release the Work from any legal liens. Can the Owner take possession of and use any completed portion of the Work prior to overall completion? Section VI, Article 20.10 (Use of Completed Portions of Work) provides that the Owner may take possession of and use any completed or partially completed portion of the Work prior to overall completion, and shall issue a Certificate of Completion for such portion taken over and release retention as required by the Contract. What is substantial completion? Section VI, Article 20.11 (Substantial Completion and its Effect) provides that there is substantial completion when the Contractor completes ninety five percent (95%) of the Work. What is a punch list? Punch list, as defined under Article 20.11 C (a), is the list of defects found or discovered on the completed work and which should be received by the Contractor not later than 30 days from date of substantial completion. What is the penalty for delay? Article 21.05 provides that upon failure of the Contractor to complete the Work within the Completion Time, the Contractor shall pay the Owner liquidated damages in the amount stipulated in the Contract as indemnity, but shall not exceed ten percent (10%) of the total contract price [Art. 29.06 (3)] What is Mediation? Mediation, as defined under Section 6 of the CIAC Mediation Rules, shall mean a voluntary process in which a mediator, selected by the disputing parties, facilitates communication and negotiation, and assists the parties in reaching a voluntary agreement regarding a dispute. What is Arbitration? Arbitration is defined as the investigation and determination of matters of differences between contending parties by one or more unofficial persons, called arbitrators or referees, chosen by the parties. It is intended to avoid the formalities, the delay, the expense and vexation of ordinary litigation. Understanding the Contracts For disputes and differences Understanding the Contracts What are the grounds for the suspension of the Work or termination of the Contract? Section 8 (Suspension of Work and Termination of Contract) illustrates the conditions by which the Contractor or the Owner may suspend the Work or terminate the Contract. How can interested parties avail of CIAC facilities? If a dispute arises, a party may initiate the mediation by delivering a written Request for Mediation to the other party in accordance with the CIAC Mediation Rules, or if mediation fails, a Request for Arbitration in accordance with the CIAC Rules of Procedure Governing Construction Arbitration What circumstances necessitate an extension of time? Article 21.04 (Extension of Time) provides that the Contractor shall be entitled to an equitable adjustment of completion time subject to certain conditions. Article 21.04 (D) states that delay in the payment of any progress billing shall automatically extend the Completion Time by a period equal to the delay. Understanding the Contracts In case of disagreements in the interpretation and implementation of the contract conditions, how can CIAP help resolve such disputes? Section IX, Article 33.04 provides that in case of disagreements, the parties may engage the services of an adjudicator to resolve their disputes, and that if either of the party disagrees with the resolution of the adjudicator, the parties may submit such disputes to arbitration. What are the issues that can be submitted for mediation or arbitration? The jurisdiction of the CIAC may include, but is not limited to, the following: - violation of specifications for materials and workmanship; - violation of the terms of agreement; - interpretation and/or application of contractual provisions; - commencement time and delays; - maintenance and defects; - changes in contract cost - payment default of employer or contractor; and - amount of damages and penalties. RESOLUTION CLAUSES Any dispute or differences arising out or in connection with this contract shall be referred to the Construction Industry Arbitration Commission (CIAC) for settlement, first through mediation under its Mediation Rules; or failing which, by arbitration under its Rules of Procedure Governing Construction Arbitration by [indicate number; one or three] arbitrator(s). The appointment of mediator or arbitrator/s shall be made in accordance with such Rules. The place of Mediation and Arbitration (by mediation or arbitration shall be [indicate place]. Any dispute arising out of or in connection with this contract, including any question regarding its existence, CIAC) validity or termination shall be referred to and finally resolved by arbitration under the Rules of Procedure Governing Construction Arbitration promulgated by the Construction Industry Arbitration Commission, by [indicate number: one or three] arbitrator(s) to be appointed in accordance with such Rules. The place of arbitration shall Purely Arbitration (by CIAC)be [indicate place]. Any dispute or differences arising out or in connection with this contract shall be settled by negotiation within a non- extendible period of 30 days from written demand by either party. If such negotiation should fail, the same shall be referred to the Construction Industry Arbitration Commission (CIAC) for settlement; first, through mediation under its Mediation Rules within a non-extendible period of 48 days; or failing which, by arbitration under its Rules of By negotiation among the Procedure Governing Construction Arbitration by [indicate parties (w/ time frame), number: one or three] arbitrator(s). The appointment of Mediation and Arbitration mediator or arbitrator/s shall be made in accordance with (by CIAC) such Rules promulgated by the CIAC. The place of mediation or arbitration shall be [indicate place] SECTION XI SCHEDULE OF TIME LIMITS Are there prescribed periods within which the contracting parties shall perform their respective obligations under the Contract? CIAP Document 102 provides the prescribed time limits for the execution of the contract conditions in order to facilitate the performance of the Works covered under the Contract [Section XI (Schedule of Time Limits)]. The Contractor shall perform his work subject to certain Time Limits. This indexed section, as based on the entire General Conditions, is provided for in order to facilitate the execution of his work. Reference No. & Title Time Limit Article No. 1.CONTRACT TIME 1.1 Contract Time The Contractor shall commence the Work 21.02 Reckoning within seven (7) days from receipt of Notice to Proceed (NTP) unless NTP provides for a 1.2 Request for Time later date 21.04 To be filed within fifteen (15) days from occurrence of event which caused delay (par. B) 2. CONTRACT SUM 2.1 Breakdown of Work To be submitted within fifteen days from 22.01 & Corresponding Value receipt of the Notice to Proceed 2.2 Claim for Extra Cost Notice to be given to Owner within fifteen 20.08 (15) days (1) after receipt of instruction involving extra cost, or (2) after recognition of delay due to Owner’s fault 3. PROGRESS/FINAL PAYMENT 3.1 Owner’s Action To be made within thirty (30) days 22.05 on Payment after receipt of request for Request payment 3.2 Owner’s Action To act within thirty (30) days from on receipt of the request for payment Final Payment 22.05 Request Delay in payment of the amount 3.3 Delayed due shall entitle the Contractor to Payment interest from due date based on the thirty (30) day loan rate of the 22.11 Land Bank of the Philippines To be released not later than sixty 3.4 Release of (60) days from substantial Retention completion upon posting of Contractor’s Guarantee Bond. 4. SUBSTANTIAL Substantial Completion is attained if the 20.11 COMPLETION and its Contractor completes ninety-five percent EFFECTS (95%) of the works; or the Owner approves the Contractor’s billing for completing at least 95% of the works unless the Owner can establish that the unfinished portion prevents the normal use of the completed portion [par. A (a) & (b)]. The Owner may issue a Certificate of Substantial Completion or equivalent document but the date of document is not controlling if substantial completion is shown to have been attained earlier, unless the Contractor accepts the certificate without taking any exceptions thereto in writing within fifteen (15) days from receipt of the certificate [par. A (c)]. 5. CORRECTION OF WORK 5.1 Issuance of Punch The Owner shall issue the punch list/s which 20.11 List the Contractor must receive not later than thirty (30) days from date of substantial completion [par C (a)]. The Owner may add to the punch list items but only as to corrective work in the original punch list/s not later than sixty (60) days from substantial completion [par. C (b)]. 5.2 Correction Before or 22.10 After Final Payment Poor or inferior work, apparent upon inspection to be condemned & Contractor notified to enable him to correct, remove & replace the same. Owner has one year from date of final payment to condemn poor or inferior work, otherwise, instructions to remove or replace 5.3 Making Good of such shall be treated as change order. Known Defects 20.12 & Thirty (30) days from receipt by the Contractor 20.13 of the last item in the punchlist 6. CONTRACTOR’S RIGHT TO Contractor may suspend work or terminate 26.00 SUSPEND WORK OR Contract upon 15 days written notice to Owner, TERMINATE CONTRACT for any of the following reasons: (1) If any court or other public authority orders work to be stopped or suspended for ninety (90) days through no fault of the Contractor or his employees; (2) If Owner fails to pay Contractor the approved request for payment within thirty (30) days from receipt. (3) If Owner fails to pay Contractor the agreed sum within thirty (30) days after its award by arbitrators. (4) If the Owner suspends the work without cause for more than fifteen (15) days without Contractor’s consent. (5) If the Owner fails to deliver at the construction site Owner-supplied/furnished materials and/or equipment, for work along the critical path beyond fifteen (15) days after its scheduled delivery date. (6) If approval of Variation Orders for additional works along the critical path is delayed beyond fifteen (15) days after submission for approval by the Owner. 7. OWNER’S RIGHT TO May be done immediately and without notice if 28.01 TERMINATE CONTRACT Contractor should: (1) Declare bankruptcy, become insolvent or assigns his assets for the benefit of his creditors or appointment of trustee/receiver for Contractor or any of its property. 28.02 May be done after giving fifteen (15) days written notice to Contractor or to his Surety if Contractor should: (1) Disregard or violate provisions of the Contract Documents or Owner’s instructions; (2) Fail to provide skilled superintendent, workmen or suitable materials or equipment; (3) Fail to make prompt payment to subcontractors, for labor or materials or equipment; (4) Disregard the authority of the Owner’s Representative (5) Violates in any substantial way any provisions of the Contract Documents (6) Repeatedly delays prosecution of work per agreed Construction Schedule and/or PERT/CPM plus any time extension duly 8. DISPUTES The Owner or his representative shall act 33.04 within a period of fifteen (15) days on all & matters under the Contract requiring the 33.05 Owner’s approval, acceptance or decision. If the Contractor disagrees with the determination by the Owner or his representative, the same shall be submitted to an adjudicator to be jointly engaged by the parties within 15 days before the commencement of the work. If either party disagrees with the resolution of the adjudicator, such shall be deemed a dispute that may be submitted to arbitration. 9. GUARANTEE BOND To be furnished the Owner upon release of 31.05 9.1 Contractor’s Guarantee retention and shall be effective for a period of Bond one year commencing from the date of acceptance as a guarantee that all materials and workmanship installed are of good quality. THANK YOU Copies of this Primer, CIAP Document 102, the CIAC Mediation Rules and Rules of Procedure Governing Construction Arbitration, are available at the CIAP website at www.ciap.dti.gov.ph

Use Quizgecko on...
Browser
Browser