Document Details

FasterMistletoe

Uploaded by FasterMistletoe

Tags

project estimation project management estimating techniques project cost

Summary

This document contains questions on project estimation, covering topics like project lifecycle, estimation methods (e.g., parametric, bottom-up), and considerations for risk. It includes practical applications for different project scenarios.

Full Transcript

1\. \*\*What is the primary challenge of estimating early in the project lifecycle?\*\* \- A) The lack of available estimating techniques \- B) High levels of uncertainty due to incomplete information \- C) The abundance of skilled labor to assist with estimates \- D) Inability to create a proje...

1\. \*\*What is the primary challenge of estimating early in the project lifecycle?\*\* \- A) The lack of available estimating techniques \- B) High levels of uncertainty due to incomplete information \- C) The abundance of skilled labor to assist with estimates \- D) Inability to create a project budget baseline \*\*Answer:\*\* B) High levels of uncertainty due to incomplete information 2\. \*\*In cost estimation, what does the \'accuracy trumpet\' depict?\*\* \- A) The increasing variance in project costs as the project progresses \- B) The decreasing range of estimation error as the project planning improves \- C) The maximum cost estimate acceptable for contingency reserves \- D) The allocation of costs to different project phases \*\*Answer:\*\* B) The decreasing range of estimation error as the project planning improves 3\. \*\*Which estimation method is most appropriate when a project scope is well defined and historical data is available?\*\* \- A) Top-down/Analogous Estimating \- B) Parametric Estimating \- C) Three-Point Estimating \- D) Bottom-up Estimating \*\*Answer:\*\* D) Bottom-up Estimating 4\. \*\*What is a key disadvantage of using a \'parametric estimation\' approach?\*\* \- A) It is highly time-consuming and resource-intensive \- B) It relies heavily on historical data, which may not be accurate \- C) It only considers optimistic scenarios \- D) It is limited to use only at the end of the project lifecycle \*\*Answer:\*\* B) It relies heavily on historical data, which may not be accurate 5\. \*\*In the context of estimating, what does \'padding\' refer to?\*\* \- A) Including allowances for additional costs in the estimate \- B) A deliberate underestimation of project costs \- C) Adding unnecessary tasks to inflate the project budget \- D) Using a single cost figure without accounting for variability \*\*Answer:\*\* A) Including allowances for additional costs in the estimate 6\. \*\*The \'Three-Point Estimating\' method uses which formula for the Beta (PERT) estimate?\*\* \- A) (O + P + M) / 3 \- B) (O + 4M + P) / 6 \- C) (O + M) / 2 \- D) (M + P - O) / 4 \*\*Answer:\*\* B) (O + 4M + P) / 6 7\. \*\*When should the \'Rough Order of Magnitude\' (ROM) estimate be used?\*\* \- A) During project execution \- B) In the early project initiation phase \- C) After the project closure \- D) Only when the project scope is finalized \*\*Answer:\*\* B) In the early project initiation phase 8\. \*\*How can the impact of optimistic bias in estimates be minimized?\*\* \- A) By using the most optimistic scenarios for all estimates \- B) By avoiding the use of historical data \- C) Through independent reviews and using Three-Point Estimating \- D) By assigning estimates only to the most optimistic team members \*\*Answer:\*\* C) Through independent reviews and using Three-Point Estimating 9\. \*\*The learning curve effect is most useful when:\*\* \- A) Tasks are performed by inexperienced staff only once \- B) Repeated tasks show a reduction in effort over time \- C) Tasks are complex and performed under different conditions each time \- D) The project requires a high degree of multitasking \*\*Answer:\*\* B) Repeated tasks show a reduction in effort over time 10\. \*\*Which of the following is NOT a typical component of a project cost baseline?\*\* \- A) Direct costs \- B) Contingency reserves \- C) Management reserves \- D) Overhead costs \*\*Answer:\*\* C) Management reserves 1\. \*\*You are tasked with preparing a quick estimate for a project with limited scope definition. The project sponsor needs this estimate within the hour. Which estimation method should you use?\*\* \- A) Bottom-up Estimating \- B) Parametric Estimating \- C) Analogous Estimating \- D) Monte Carlo Simulation \*\*Answer:\*\* C) Analogous Estimating 2\. \*\*Your team has consistently underestimated task durations due to optimism bias. What is the best approach to mitigate this in future estimates?\*\* \- A) Increase the contingency reserve for all tasks \- B) Use Three-Point Estimating to account for uncertainty \- C) Use the most optimistic estimates from historical projects \- D) Assign the tasks to faster team members \*\*Answer:\*\* B) Use Three-Point Estimating to account for uncertainty 3\. \*\*You are preparing a cost estimate for a project that involves complex, repetitive tasks. What method would most likely yield the most accurate estimate?\*\* \- A) Expert Judgment \- B) Learning Curve Analysis \- C) Rough Order of Magnitude (ROM) \- D) Top-down Estimating \*\*Answer:\*\* B) Learning Curve Analysis 4\. \*\*The project sponsor has requested a detailed estimate for a critical deliverable that has a high level of risk and uncertainty. Which estimating technique should you apply?\*\* \- A) Analogous Estimating \- B) Parametric Estimating \- C) Bottom-up Estimating \- D) Expert Judgment \*\*Answer:\*\* C) Bottom-up Estimating 5\. \*\*A stakeholder is concerned that your estimates may be padded. How can you justify your estimates and demonstrate transparency?\*\* \- A) Show the range of estimates using Three-Point Estimating and explain the variance \- B) Increase the estimate to include an extra 10% contingency \- C) Use only historical data to create a single-point estimate \- D) Agree to reduce the estimate to satisfy the stakeholder \*\*Answer:\*\* A) Show the range of estimates using Three-Point Estimating and explain the variance 6\. \*\*You are working with a team member who consistently applies deliberate padding to their estimates due to fear of missing deadlines. What is the best approach to handle this issue?\*\* \- A) Reduce their estimates by 20% to remove the padding \- B) Use a Three-Point Estimating approach to balance optimistic, most likely, and pessimistic estimates \- C) Accept the padded estimates to ensure a buffer for the project \- D) Instruct them to provide single-point estimates without any buffer \*\*Answer:\*\* B) Use a Three-Point Estimating approach to balance optimistic, most likely, and pessimistic estimates 7\. \*\*The project involves tasks that your team has never performed before, and there is limited historical data available. What estimating method should you consider using?\*\* \- A) Parametric Estimating \- B) Analogous Estimating \- C) Expert Judgment \- D) Bottom-up Estimating \*\*Answer:\*\* C) Expert Judgment 8\. \*\*Your team has completed a rough order of magnitude (ROM) estimate early in the project. As the project progresses and more information becomes available, what should you do with the initial estimate?\*\* \- A) Keep the ROM estimate unchanged as a baseline \- B) Refine the estimate using a more detailed estimating method like Bottom-up Estimating \- C) Discard the ROM estimate and start fresh \- D) Add a 10% contingency to the original ROM estimate \*\*Answer:\*\* B) Refine the estimate using a more detailed estimating method like Bottom-up Estimating 9\. \*\*You notice that several tasks in your project have been underestimated due to the \'Student Syndrome.\' What is a practical solution to mitigate this behavior in future estimates?\*\* \- A) Increase the overall project schedule \- B) Implement shorter task durations with regular progress checkpoints \- C) Add more resources to complete the tasks faster \- D) Ignore the issue as it's part of normal project variability \*\*Answer:\*\* B) Implement shorter task durations with regular progress checkpoints 10\. \*\*Your sponsor is concerned about the accuracy of the project's cost estimates, given the volatile market conditions. Which action would best address this concern?\*\* \- A) Apply a fixed percentage increase to all estimates \- B) Use a parametric estimate based on current market data and regularly update it \- C) Shift to a top-down estimating approach for simplicity \- D) Ignore the market conditions as they are beyond control \*\*Answer:\*\* B) Use a parametric estimate based on current market data and regularly update it 11\. \*\*A client has requested an estimate for a project where the scope is vaguely defined and may change. Which estimation method would provide the most flexibility?\*\* \- A) Bottom-up Estimating \- B) Rough Order of Magnitude (ROM) \- C) Three-Point Estimating \- D) Parametric Estimating \*\*Answer:\*\* B) Rough Order of Magnitude (ROM) 12\. \*\*During the estimation process, you discover that several team members are affected by Parkinson's Law. How should you address this issue in your estimates?\*\* \- A) Extend the project timeline to accommodate the extra work time \- B) Set strict deadlines with limited flexibility for early completion \- C) Increase the level of detail in the work breakdown structure (WBS) \- D) Add more resources to speed up the tasks \*\*Answer:\*\* B) Set strict deadlines with limited flexibility for early completion 13\. \*\*A project requires multiple iterations of a complex deliverable, with each iteration expected to become more efficient. Which estimating technique would best account for this learning effect?\*\* \- A) Expert Judgment \- B) Analogous Estimating \- C) Learning Curve Analysis \- D) Parametric Estimating \*\*Answer:\*\* C) Learning Curve Analysis 14\. \*\*Your project involves significant overtime, and you notice an increase in defects and errors. What should be your next step?\*\* \- A) Ignore the defects as they are typical with overtime \- B) Re-evaluate the schedule to reduce the reliance on overtime \- C) Increase overtime hours to catch up on the project timeline \- D) Implement stricter quality control measures \*\*Answer:\*\* B) Re-evaluate the schedule to reduce the reliance on overtime 15\. \*\*A stakeholder demands a highly precise estimate early in the project, but the scope is still unclear. How should you respond?\*\* \- A) Provide a detailed estimate using Bottom-up Estimating \- B) Offer a Rough Order of Magnitude (ROM) estimate and explain its limitations \- C) Agree to provide a highly precise estimate despite the uncertainty \- D) Delay the estimate until the scope is finalized \*\*Answer:\*\* B) Offer a Rough Order of Magnitude (ROM) estimate and explain its limitations 16\. \*\*You have been assigned to estimate a project with several unknown risks. What should you include in your estimates to account for these uncertainties?\*\* \- A) Increase the estimate by a fixed percentage \- B) Include a contingency reserve based on risk analysis \- C) Use only optimistic estimates to reduce costs \- D) Apply a learning curve adjustment \*\*Answer:\*\* B) Include a contingency reserve based on risk analysis 17\. \*\*Your client requests a detailed estimate breakdown for a project using a Three-Point Estimating method. They want to understand the most likely, optimistic, and pessimistic scenarios. What is your next step?\*\* \- A) Provide a single-point estimate for simplicity \- B) Calculate and present estimates for each scenario using (O + 4M + P) / 6 \- C) Use historical data to justify only the most likely estimate \- D) Avoid sharing the pessimistic scenario to maintain client confidence \*\*Answer:\*\* B) Calculate and present estimates for each scenario using (O + 4M + P) / 6 18\. \*\*During a review of your estimates, you identify that some tasks have been influenced by the \'planning fallacy.\' What is a good approach to correct this bias?\*\* \- A) Extend the project schedule by 20% \- B) Use reference class forecasting to adjust the estimates based on historical data \- C) Apply a rough order of magnitude (ROM) estimate instead \- D) Ignore the fallacy as it's part of normal project optimism \*\*Answer:\*\* B) Use reference class forecasting to adjust the estimates based on historical data 19\. \*\*The project sponsor has requested an aggressive timeline that significantly shortens the estimated duration. What is the best approach to handle this request?\*\* \- A) Reduce the quality of deliverables to meet the timeline \- B) Implement schedule compression techniques like crashing or fast-tracking \- C) Extend the timeline to avoid compromising the project \- D) Add more resources regardless of their availability \*\*Answer:\*\* B) Implement schedule compression techniques like crashing or fast-tracking 20\. \*\*You are using a bottom-up estimating approach, but one task has highly uncertain resource requirements. What should you do to improve the accuracy of your estimate?\*\* \- A) Use expert judgment to override the bottom-up estimate \- B) Switch to a top-down estimating method for this task \- C) Incorporate a range of estimates using Three-Point Estimating \- D) Use parametric estimation based on unrelated tasks \*\*Answer:\*\* C) Incorporate a range of estimates using Three-Point Estimating 21\. \*\*A key deliverable in your project has a high degree of variability in its cost due to fluctuating material prices. How can you best manage this in your estimate?\*\* \- A) Apply a fixed price regardless of market conditions \- B) Include an economic price adjustment clause in the estimate \- C) Use a single-point estimate to simplify the process \- D) Increase the contingency reserve without justification \*\*Answer:\*\* B) Include an economic price adjustment clause in the estimate 22\. \*\*A task has been completed faster than estimated, but the project budget remains unchanged. What is a potential consequence of this outcome?\*\* \- A) The project's total cost will decrease \- B) Parkinson's Law may take effect, leading to unnecessary rework \- C) The project will be completed ahead of schedule \- D) The contingency reserves will be released \*\*Answer:\*\* B) Parkinson's Law may take effect, leading to unnecessary rework 23\. \*\*Your estimates are being challenged for being too conservative. What can you do to address these concerns while maintaining a realistic project timeline?\*\* \- A) Reduce the estimates by 10% to appease stakeholders \- B) Present historical data and explain the basis of your estimates \- C) Agree to use optimistic estimates moving forward \- D) Increase the project contingency to cover any shortfall \*\*Answer:\*\* B) Present historical data and explain the basis of your estimates 24\. \*\*You are finalizing a cost estimate for a complex deliverable. The team has provided a range of optimistic and pessimistic values. Which method would help you develop a balanced estimate?\*\* \- A) Analogous Estimating \- B) Three-Point Estimating (Beta distribution) \- C) Parametric Estimating \- D) Rough Order of Magnitude (ROM) \*\*Answer:\*\* B) Three-Point Estimating (Beta distribution) 25\. \*\*You have been asked to provide a final estimate for a deliverable with high uncertainty due to ongoing market fluctuations. How should you approach the estimation to account for this risk?\*\* \- A) Use a single-point estimate based on the most likely scenario \- B) Increase the project budget by a fixed percentage to cover any potential changes \- C) Include a management reserve and apply Monte Carlo simulation for risk analysis \- D) Ignore the fluctuations and use historical cost data for consistency \*\*Answer:\*\* C) Include a management reserve and apply Monte Carlo simulation for risk analysis 11\. \*\*Which estimating technique uses historical project data and adjusts for differences in project size and complexity?\*\* \- A) Bottom-up Estimating \- B) Expert Judgment \- C) Parametric Estimating \- D) Top-down/Analogous Estimating \*\*Answer:\*\* D) Top-down/Analogous Estimating 12\. \*\*The use of a learning curve in estimating assumes that:\*\* \- A) Resources will maintain consistent productivity throughout the project \- B) The time required to complete repetitive tasks will decrease with experience \- C) Estimates are always based on pessimistic scenarios \- D) The accuracy of estimates decreases over time \*\*Answer:\*\* B) The time required to complete repetitive tasks will decrease with experience 13\. \*\*What is a significant risk when relying solely on expert judgment for project estimates?\*\* \- A) Overestimating due to historical data analysis \- B) The introduction of subjective bias and optimistic forecasting \- C) Increased complexity in the estimation process \- D) Lack of flexibility in adjusting the project scope \*\*Answer:\*\* B) The introduction of subjective bias and optimistic forecasting 14\. \*\*When should you use the \'parametric estimating\' method in a project?\*\* \- A) When the project scope is unclear and needs rough estimates \- B) When there is a large dataset available for similar activities \- C) When the team lacks historical data or experience \- D) Only at the final stages of the project \*\*Answer:\*\* B) When there is a large dataset available for similar activities 15\. \*\*Which of the following best describes the relationship between the accuracy of an estimate and the level of project planning completed?\*\* \- A) Accuracy decreases as planning progresses \- B) Accuracy increases with the refinement of the project scope and WBS \- C) Estimates become less reliable as more details are added \- D) Accuracy remains constant throughout the project lifecycle \*\*Answer:\*\* B) Accuracy increases with the refinement of the project scope and WBS 16\. \*\*In which scenario would you prefer a Rough Order of Magnitude (ROM) estimate over a Bottom-up estimate?\*\* \- A) When detailed project requirements are defined \- B) During the initiation phase with minimal information available \- C) In the final stages of the project when costs need to be precise \- D) When developing estimates for individual work packages \*\*Answer:\*\* B) During the initiation phase with minimal information available 17\. \*\*How does Parkinson's Law affect project estimation?\*\* \- A) It encourages early task completion \- B) It leads to inflated estimates as tasks expand to fill the available time \- C) It reduces the overall project duration \- D) It decreases the need for contingency reserves \*\*Answer:\*\* B) It leads to inflated estimates as tasks expand to fill the available time 18\. \*\*What is the main advantage of using Three-Point Estimating with the Beta distribution (PERT)?\*\* \- A) It provides a precise single-point estimate \- B) It reduces the need for contingency reserves \- C) It considers a range of scenarios (optimistic, most likely, pessimistic) \- D) It simplifies the estimation process by eliminating variance \*\*Answer:\*\* C) It considers a range of scenarios (optimistic, most likely, pessimistic) 19\. \*\*Why is it important to document the assumptions used in the estimation process?\*\* \- A) To reduce the project scope \- B) To provide a basis for revising estimates if assumptions change \- C) To increase the overall project budget \- D) To eliminate the need for risk management \*\*Answer:\*\* B) To provide a basis for revising estimates if assumptions change 20\. \*\*Which method is most suitable when estimating costs for a project deliverable that has been repeated multiple times across past projects?\*\* \- A) Rough Order of Magnitude (ROM) \- B) Parametric Estimating \- C) Expert Judgment \- D) Bottom-up Estimating \*\*Answer:\*\* B) Parametric Estimating 21\. \*\*In what situation would a management reserve be applied to a project estimate?\*\* \- A) When all project risks are known and documented \- B) To account for unforeseen changes outside the project scope \- C) To adjust the estimate based on optimistic scenarios \- D) When the contingency reserve has been exhausted \*\*Answer:\*\* B) To account for unforeseen changes outside the project scope 22\. \*\*What is the primary purpose of using a \'basis of estimate\' document?\*\* \- A) To track the project's actual costs against the budget \- B) To provide detailed information on how the estimate was developed \- C) To reduce the project duration \- D) To justify the use of historical data only \*\*Answer:\*\* B) To provide detailed information on how the estimate was developed 23\. \*\*Which of the following is a potential drawback of using a Bottom-up Estimating approach?\*\* \- A) It provides less accurate estimates than top-down methods \- B) It can be time-consuming and require significant resources \- C) It relies heavily on market conditions \- D) It cannot be used for complex projects \*\*Answer:\*\* B) It can be time-consuming and require significant resources 24\. \*\*In the estimation process, what does \'contingency reserve\' specifically cover?\*\* \- A) Costs related to unknown unknowns \- B) Adjustments for inflation \- C) Identified risks with a known probability of occurrence \- D) Bonuses for early task completion \*\*Answer:\*\* C) Identified risks with a known probability of occurrence 25\. \*\*What is the main difference between \'direct costs\' and \'overhead costs\' in project estimating?\*\* \- A) Direct costs are fixed, while overhead costs are variable \- B) Direct costs are tied to specific project tasks, while overhead costs cover general administrative expenses \- C) Overhead costs are always included in the project's contingency reserve \- D) Overhead costs are included in the cost baseline, while direct costs are not \*\*Answer:\*\* B) Direct costs are tied to specific project tasks, while overhead costs cover general administrative expenses

Use Quizgecko on...
Browser
Browser